Delayed projects in Solapur
156 MahaRERA projects in Solapur are past their promised completion date, and MahaRERA shows no completion for them.
Most overdue first
Late: the latest completion date MahaRERA records (promised, or revised by an extension) has passed. Months late count from the first promised date. Page 3 of 4.
| Project | Locality | Promised | Revised | Delivery |
|---|---|---|---|---|
| Central ParkUsman Hassam Mansuri | Solapur North | Jan 2025 | Dec 2025 | 1 yr 10 mo late |
| Madur SquareShri Mahalaxmi Developers | Solapur (M Corp.) | Jan 2025 | Jan 2025 | 1 yr 10 mo late |
| Maheshwari HeightsMaheshwari Developers And Builders | Solapur (M Corp.) | Jan 2025 | Jan 2025 | 1 yr 10 mo late |
| Padmavati PlazaPopat Rajaram Patil | Pandharpur | Jan 2025 | Jan 2025 | 1 yr 10 mo late |
| Punjabi SquareMohsin Haroon Shaikh | Solapur (M Corp.) | Jan 2025 | Jan 2025 | 1 yr 10 mo late |
| Royal TowerRoyal Infra | Solapur (M Corp.) | Jan 2025 | Jan 2025 | 1 yr 10 mo late |
| Sharda HeightsVijay Constructions | Solapur (M Corp.) | Jan 2025 | Jan 2025 | 1 yr 10 mo late |
| Siddha-Trimbak TowerMinakshi Jayprakash Jankar | Solapur (M Corp.) | Jan 2025 | Jan 2025 | 1 yr 10 mo late |
| Signature SquareMohsin Haroon Shaikh | Solapur (M Corp.) | Jan 2025 | Jan 2025 | 1 yr 10 mo late |
| Silver Oak PrimeSkyline builders & Developers | Majrewadi | Jan 2025 | Jan 2025 | 1 yr 10 mo late |
| Yaseen SquareMohsin Haroon Shaikh | Solapur (M Corp.) | Jan 2025 | Jan 2025 | 1 yr 10 mo late |
| Roshan ApartmentRoshan Builders & Developers | Majrewadi | Mar 2025 | Dec 2025 | 1 yr 8 mo late |
| Khushi HeightsKhushi Builders And Developers | Solapur (M Corp.) | Mar 2025 | Mar 2025 | 1 yr 8 mo late |
| Green OneMohammed Jaweed Nasiruddin Lunje | Solapur (M Corp.) | Mar 2025 | Mar 2025 | 1 yr 8 mo late |
| Kimaya PrimeSamir Amrut Gandhi | Solapur (M Corp.) | Mar 2025 | Mar 2025 | 1 yr 8 mo late |
| Lotus ApartmentLotus Apartment | Akkalkot (M Cl) | Mar 2025 | Mar 2025 | 1 yr 8 mo late |
| Shri Ram Sankul AppartmentChhaya Kamalakar Chafekar | Majrewadi | May 2025 | May 2025 | 1 yr 6 mo late |
| Global AvenueGlobal Infracon | Solapur (M Corp.) | May 2025 | May 2025 | 1 yr 6 mo late |
| Icon TowerSameer Shrikant Tadawalkar & Deepak Navnath Alkunte | Solapur (M Corp.) | May 2025 | May 2025 | 1 yr 6 mo late |
| ShishirShri Mauli Buildcon | Karmala (Rural) | Jun 2025 | Jun 2025 | 1 yr 5 mo late |
| Chandrama ApartmentAshok Shankar Gandhi | Solapur (M Corp.) | Jun 2025 | Jun 2025 | 1 yr 5 mo late |
| Gulmohar SquareSquare One Builders & Developers | Solapur (M Corp.) | Jun 2025 | Jun 2025 | 1 yr 5 mo late |
| Karnul ApartmentRoyal Builders And Developers | Solapur (M Corp.) | Jun 2025 | Jun 2025 | 1 yr 5 mo late |
| Shri Samrat ResidencyShree Construction | Solapur (M Corp.) | Jun 2025 | Jun 2025 | 1 yr 5 mo late |
| Damyanti PlazaShridatta Builders And Developers | Solapur (M Corp.) | Jul 2025 | Jul 2025 | 1 yr 4 mo late |
| Global City ViewGlobal Constructions | Solapur (M Corp.) | Jul 2025 | Jul 2025 | 1 yr 4 mo late |
| Rajdeep homesRajiv Ramchandra Dipali | Solapur (M Corp.) | Aug 2025 | Aug 2025 | 1 yr 3 mo late |
| Rushi PearlMeghshyam Mallikarjun Yemul | Solapur (M Corp.) | Aug 2025 | Aug 2025 | 1 yr 3 mo late |
| Mangalmurti ResidencyGavasane Builders | Solapur (M Corp.) | Aug 2025 | Aug 2025 | 1 yr 3 mo late |
| Seven Hills ApartmentSeven Hills Developers | Majrewadi | Sep 2025 | Sep 2025 | 1 yr 2 mo late |
| Matoshri ResidencyBharat Hambirrav Salunke | Kandar | Nov 2025 | Nov 2025 | 1 yr late |
| Dream City Gowardhan ApartmentSanjay Raghunath Bagal | Kasegaon | Dec 2025 | Dec 2025 | 11 mo late |
| Galaxy 52Swapnil Suhas Raut | Solapur South | Dec 2025 | Dec 2025 | 11 mo late |
| Mahaveer TowerMahaveer Developers And Builders | Barshi | Dec 2025 | Dec 2025 | 11 mo late |
| Alif ResidencyOrion Developers | Solapur (M Corp.) | Dec 2025 | Dec 2025 | 11 mo late |
| Altamash ResidencyAbdulsattar Shaikh | Majrewadi | Dec 2025 | Dec 2025 | 11 mo late |
| Bhaiji ApartmentBhaiji Apartment | Solapur (M Corp.) | Dec 2025 | Dec 2025 | 11 mo late |
| High MarkNishat Motiwala | Majrewadi | Dec 2025 | Dec 2025 | 11 mo late |
| Mangal ResidencyPradnya Abhijit Patil | Barshi | Dec 2025 | Dec 2025 | 11 mo late |
| Patel PlazaEhsan Construction | Solapur (M Corp.) | Dec 2025 | Dec 2025 | 11 mo late |
| Siddh-Khushi ComplexKhushi Builders | Solapur North | Dec 2025 | Dec 2025 | 11 mo late |
| Sudarshan HeightsShri Mahalaxmi Builders And Developers | Solapur (M Corp.) | Dec 2025 | Dec 2025 | 11 mo late |
| SwapnshilpRoyal Buildcons | Solapur (M Corp.) | Dec 2025 | Dec 2025 | 11 mo late |
| H and H HeightsVNS Builders and Developers | Solapur (M Corp.) | Jan 2026 | Jan 2026 | 10 mo late |
| Royal ApartmentImran Mohammed Ismail Attar | Solapur (M Corp.) | Jan 2026 | Jan 2026 | 10 mo late |
| Regal IconVighnesh Developers | Solapur (M Corp.) | Jan 2026 | Jan 2026 | 10 mo late |
| Hmempire210211Heriytage Maniydhari Empire | Solapur (M Corp.) | Mar 2026 | Jul 2026 | 8 mo late |
| Snc Grand ResidenceA S D C Developers | Solapur (M Corp.) | Mar 2026 | Jul 2026 | 8 mo late |
| Ved ResidencySanjay Vishwananth Hankare | Pandharpur | Apr 2026 | Aug 2026 | 7 mo late |
| Nirmiti SakuraNircon Developers | Solapur (M Corp.) | May 2026 | May 2026 | 6 mo late |
Delayed projects by district
All MaharashtraPune · 2,219Thane · 1,161Raigarh · 1,042Mumbai Suburban · 996Nashik · 482Palghar · 364Nagpur · 323Aurangabad · 243Mumbai City · 243Satara · 228Ratnagiri · 193Sangli · 176Solapur · 156Kolhapur · 131Amravati · 72Sindhudurg · 72Ahmednagar · 69Chandrapur · 39Jalgaon · 39Latur · 27Akola · 23Beed · 21Nanded · 18Dhule · 17Wardha · 16Buldana · 14Jalna · 12Parbhani · 9Bhandara · 8Yavatmal · 6
SourcesMahaRERA registrations, extension certificates, project pages and document listsA project counts as completed when MahaRERA shows it so: its status, or a completion or occupancy certificate in its documents. Dates are MahaRERA's; Deedo does not know the day a project was handed over.Report a problemMethodology