Delayed projects in Solapur

156 MahaRERA projects in Solapur are past their promised completion date, and MahaRERA shows no completion for them.

Most overdue first

Late: the latest completion date MahaRERA records (promised, or revised by an extension) has passed. Months late count from the first promised date. Page 3 of 4.

ProjectLocalityPromisedRevisedDelivery
Central ParkUsman Hassam MansuriSolapur NorthJan 2025Dec 20251 yr 10 mo late
Madur SquareShri Mahalaxmi DevelopersSolapur (M Corp.)Jan 2025Jan 20251 yr 10 mo late
Maheshwari HeightsMaheshwari Developers And BuildersSolapur (M Corp.)Jan 2025Jan 20251 yr 10 mo late
Padmavati PlazaPopat Rajaram PatilPandharpurJan 2025Jan 20251 yr 10 mo late
Punjabi SquareMohsin Haroon ShaikhSolapur (M Corp.)Jan 2025Jan 20251 yr 10 mo late
Royal TowerRoyal InfraSolapur (M Corp.)Jan 2025Jan 20251 yr 10 mo late
Sharda HeightsVijay ConstructionsSolapur (M Corp.)Jan 2025Jan 20251 yr 10 mo late
Siddha-Trimbak TowerMinakshi Jayprakash JankarSolapur (M Corp.)Jan 2025Jan 20251 yr 10 mo late
Signature SquareMohsin Haroon ShaikhSolapur (M Corp.)Jan 2025Jan 20251 yr 10 mo late
Silver Oak PrimeSkyline builders & DevelopersMajrewadiJan 2025Jan 20251 yr 10 mo late
Yaseen SquareMohsin Haroon ShaikhSolapur (M Corp.)Jan 2025Jan 20251 yr 10 mo late
Roshan ApartmentRoshan Builders & DevelopersMajrewadiMar 2025Dec 20251 yr 8 mo late
Khushi HeightsKhushi Builders And DevelopersSolapur (M Corp.)Mar 2025Mar 20251 yr 8 mo late
Green OneMohammed Jaweed Nasiruddin LunjeSolapur (M Corp.)Mar 2025Mar 20251 yr 8 mo late
Kimaya PrimeSamir Amrut GandhiSolapur (M Corp.)Mar 2025Mar 20251 yr 8 mo late
Lotus ApartmentLotus ApartmentAkkalkot (M Cl)Mar 2025Mar 20251 yr 8 mo late
Shri Ram Sankul AppartmentChhaya Kamalakar ChafekarMajrewadiMay 2025May 20251 yr 6 mo late
Global AvenueGlobal InfraconSolapur (M Corp.)May 2025May 20251 yr 6 mo late
Icon TowerSameer Shrikant Tadawalkar & Deepak Navnath AlkunteSolapur (M Corp.)May 2025May 20251 yr 6 mo late
ShishirShri Mauli BuildconKarmala (Rural)Jun 2025Jun 20251 yr 5 mo late
Chandrama ApartmentAshok Shankar GandhiSolapur (M Corp.)Jun 2025Jun 20251 yr 5 mo late
Gulmohar SquareSquare One Builders & DevelopersSolapur (M Corp.)Jun 2025Jun 20251 yr 5 mo late
Karnul ApartmentRoyal Builders And DevelopersSolapur (M Corp.)Jun 2025Jun 20251 yr 5 mo late
Shri Samrat ResidencyShree ConstructionSolapur (M Corp.)Jun 2025Jun 20251 yr 5 mo late
Damyanti PlazaShridatta Builders And DevelopersSolapur (M Corp.)Jul 2025Jul 20251 yr 4 mo late
Global City ViewGlobal ConstructionsSolapur (M Corp.)Jul 2025Jul 20251 yr 4 mo late
Rajdeep homesRajiv Ramchandra DipaliSolapur (M Corp.)Aug 2025Aug 20251 yr 3 mo late
Rushi PearlMeghshyam Mallikarjun YemulSolapur (M Corp.)Aug 2025Aug 20251 yr 3 mo late
Mangalmurti ResidencyGavasane BuildersSolapur (M Corp.)Aug 2025Aug 20251 yr 3 mo late
Seven Hills ApartmentSeven Hills DevelopersMajrewadiSep 2025Sep 20251 yr 2 mo late
Matoshri ResidencyBharat Hambirrav SalunkeKandarNov 2025Nov 20251 yr late
Dream City Gowardhan ApartmentSanjay Raghunath BagalKasegaonDec 2025Dec 202511 mo late
Galaxy 52Swapnil Suhas RautSolapur SouthDec 2025Dec 202511 mo late
Mahaveer TowerMahaveer Developers And BuildersBarshiDec 2025Dec 202511 mo late
Alif ResidencyOrion DevelopersSolapur (M Corp.)Dec 2025Dec 202511 mo late
Altamash ResidencyAbdulsattar ShaikhMajrewadiDec 2025Dec 202511 mo late
Bhaiji ApartmentBhaiji ApartmentSolapur (M Corp.)Dec 2025Dec 202511 mo late
High MarkNishat MotiwalaMajrewadiDec 2025Dec 202511 mo late
Mangal ResidencyPradnya Abhijit PatilBarshiDec 2025Dec 202511 mo late
Patel PlazaEhsan ConstructionSolapur (M Corp.)Dec 2025Dec 202511 mo late
Siddh-Khushi ComplexKhushi BuildersSolapur NorthDec 2025Dec 202511 mo late
Sudarshan HeightsShri Mahalaxmi Builders And DevelopersSolapur (M Corp.)Dec 2025Dec 202511 mo late
SwapnshilpRoyal BuildconsSolapur (M Corp.)Dec 2025Dec 202511 mo late
H and H HeightsVNS Builders and DevelopersSolapur (M Corp.)Jan 2026Jan 202610 mo late
Royal ApartmentImran Mohammed Ismail AttarSolapur (M Corp.)Jan 2026Jan 202610 mo late
Regal IconVighnesh DevelopersSolapur (M Corp.)Jan 2026Jan 202610 mo late
Hmempire210211Heriytage Maniydhari EmpireSolapur (M Corp.)Mar 2026Jul 20268 mo late
Snc Grand ResidenceA S D C DevelopersSolapur (M Corp.)Mar 2026Jul 20268 mo late
Ved ResidencySanjay Vishwananth HankarePandharpurApr 2026Aug 20267 mo late
Nirmiti SakuraNircon DevelopersSolapur (M Corp.)May 2026May 20266 mo late

Delayed projects by district

SourcesMahaRERA registrations, extension certificates, project pages and document listsA project counts as completed when MahaRERA shows it so: its status, or a completion or occupancy certificate in its documents. Dates are MahaRERA's; Deedo does not know the day a project was handed over.Report a problemMethodology