Silver Oak Prime
Deedo IDDP-SOL-RW85Its promised completion date, Jan 2025, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 69% of its units are booked.
Majrewadi, Solapur 413003 · by Skyline Builders & Developers
Buying a flat here?
See every deed registered on it.
Its promised completion date, Jan 2025, has passed and MahaRERA does not show it completed
- This projectRegistered 8 Sep 2021, completion promised 1 Jan 2025, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52600030702
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52600030702 | 8 Sep 2021 | 1 Jan 2025 | 1 Jan 2025 | Skyline builders & Developers | Project page |
Documents34
2 documents held by Deedo, 32 filings listed on MahaRERA's project page
Show all 34 documentsShow fewer documents
Migrated
- 1 Copy of Layout Approval (in case of layout)skyline layout.pdf · uploaded 26 Aug 2021Source
- 1 Building Plan Approval / NA Order for plotted developmentskyline building plan.pdf · uploaded 26 Aug 2021Source
- 1 Commencement Certificates / NA Order for plotted developmentskyline bandhkam parvana.pdf · uploaded 26 Aug 2021Source
- 1 Declaration about Commencement Certificatedeclaration certificate SL.pdf · uploaded 26 Aug 2021Source
- 1 Declaration in FORM BForm B SL_11zon.pdf · uploaded 26 Aug 2021Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect's certificate sl 1.pdf · uploaded 26 Aug 2021Source
- 1 Proforma of Allotment letterSample Agreement For RERA SL.pdf · uploaded 26 Aug 2021Source
- 2 Proforma of Allotment letterMAHARERA ALLOTMENT LETTER SL.pdf · uploaded 26 Aug 2021Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA certificate SL.pdf · uploaded 27 Aug 2021Source
- 3 Proforma of Allotment letterMaster Draft of Agt to sale (1) (1).pdf · uploaded 2 Dec 2021Source
- 1 Disclosure of sold/ booked inventory2022-10-20_054119newsold.pdf · uploaded 20 Oct 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Silver Oak Form 5 2122 (1).pdf · uploaded 16 Jul 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Siver Oak Form 5 2223 (1).pdf · uploaded 16 Jul 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1_.pdf · uploaded 22 Jul 2023Source
- 2 Disclosure of sold/ booked inventoryjune23soldinventory.pdf · uploaded 22 Jul 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)engineer june23_organized.pdf · uploaded 24 Jul 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 20 Oct 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 20 Oct 2023Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Skyline Builders F1.pdf · uploaded 20 Jan 2024Source
- 3 Disclosure of sold/ booked inventoryMotiwala skyline inventory.pdf · uploaded 20 Jan 2024Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Skyline Builders.pdf · uploaded 22 Jan 2024Source
- 4 Disclosure of sold/ booked inventoryAdobe Scan 20 Jan 2024.pdf · uploaded 22 Jan 2024View
Technical
Technical (Architect)
- DocumentSkyline Builders.pdf · uploaded 22 Jan 2024Source
Technical (Engineer)
- DocumentForm 2.pdf · uploaded 20 Oct 2023Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel Survey no 14/1/B plot no A6
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 2BHK32 units in all
- Address
- Survey no 14 1 B plot no A6, Basweshwar nagar, MajrewadiPIN 413003
- Village
- Solapur (M Corp.), Solapur North taluka
- Land area for this project
- 613 sq m (6,597 sq ft)
- Permissible built-up area
- 1,539 sq m (16,565 sq ft)
- Sanctioned built-up area
- 1,539 sq m (16,565 sq ft)
- Designated bank account
- 29
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
Survey no 14 1 B plot no A6
Boundaries
- North
- plot no A5
- South
- 24 M wide road
- East
- s no 14 A
- West
- 7 m wide road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking32 units
22 of 32 units booked (69%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 58.92 sq m · 634 sq ft | 2 | 2 |
| 2BHK | 59.11 sq m · 636 sq ft | 14 | 10 |
| 2BHK | 59.75 sq m · 643 sq ft | 2 | 1 |
| 2BHK | 59.94 sq m · 645 sq ft | 14 | 9 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Rahul khamitkar | — |
| Chartered accountant | Aditya Kondle | — |
| Engineer | Rhul khamitkar | — |
Source: MahaRERA project page. Contact details are not shown.