Nadgaon, Thane

Deedo IDDL-THN-NADGAON

10 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects1
Registrations1
Completion still due10 past their date
Median extension24 months100% of registrations extended
Regulatory cases0none on MahaRERA's lists

10 in 10 registrations run late here

1 MahaRERA registration in Nadgaon

1 extended, not yet due

Extended registrations moved their completion date by a median of 24 months.

Projects in Nadgaon

1 project registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Enrich EvaDevdas Tukaram ChaughuleDue Dec 2026, extended 2 yrs—43%
Nadgaon market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Devdas Tukaram Chaughule1 project

Nadgaon, in questions

How many projects in Nadgaon run late?

10 in 10 MahaRERA registrations (1 of 1): their completion date was extended or has passed, data through 7 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nadgaon by Deedo. Medians on fewer than 3 deeds are not shown.

Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology