Murbad, Thane
Deedo IDDL-THN-MURBAD-28 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects33
Registrations33
Completion still due1815 past their date
Median extension4 months45% of registrations extended
Regulatory cases1on 1 project
8 in 10 registrations run late here
33 MahaRERA registrations in Murbad
6 not yet due12 extended, not yet due15 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Murbad
33 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Sai Siddhi ParkSai Siddhi Developers | Due Dec 2027 | — | — |
| Sujata HeightsMayur Shankar Chaudhari | Due Dec 2028 | — | — |
| Om Sai Krupa ApartmentShivnirman Developers | Due Dec 2028 | — | — |
| Suparshavanath RealitySuparshavanath Reality | Due Apr 2030, extended 4 mo | — | — |
| Shree Ganesh ApartmentVandana Dinesh Kante | Due Jul 2028, extended 4 mo | — | — |
| Shree Darshan HeightsShree Darshan Construction | Due Apr 2030, extended 4 mo | — | — |
| Skyrise VillaSky Rise Builders And Developers | Due Apr 2028, extended 4 mo | — | — |
| Vishwa ComplexVastushilp Construction | Due Oct 2027, extended 4 mo | — | — |
| Shree ApartmentDeepak Shivaji Hindurao | 7 mo late | — | — |
| Sai Krishna HeightsOm Sai Developers | Due Dec 2026 | — | — |
| Om Shree Sai VillaSangita Sharad Suryarav | Due Apr 2027, extended 4 mo | — | — |
| Satish ResidencyNitin Rajaram Gharat | 11 mo late | — | — |
| Sai Krupa ApartmentBhimraj Ganpat More | Due Apr 2027, extended 4 mo | — | — |
| Sarosh ComplexSarosh Imran Kohari | Due Apr 2027, extended 4 mo | — | — |
| Shiv ParadiseEagle Homes Builders And Developers | 8 mo late | — | — |
| Shree Siddhivinayak Park B1 And B2Satyashiv Developers | Due Apr 2031, extended 4 mo | — | — |
| Sai Siddhi ApartmentSai Siddhi Developers | Completed | — | — |
| Mohan HeightsMohan Atmaram Sase | Completed | — | — |
| Shree Prabhucharan Chs.ltdShree Prabhucharan Co-Op Housing Society | Completed | — | — |
| Shree Charan ApartmentShree Mangalmurti Enterprises | Completed | — | 40% |
| Swami Narendra ResidencyRaj Ratneshwari Developers | Due Apr 2027, extended 4 mo | — | 86% |
| Techcons BaseraTechcons Constructional Engineering Co | Due Dec 2026 | — | 72% |
| Sai Balaji ComplexSai Balaji Complex | Completed | — | — |
| Arjun HeightsNanda Arjun Shelke | Completed | — | — |
| Shree Mangalmurti Builders And DevelopersVasanti Kashinath Chaudhari | Completed | — | 100% |
Nearby: other villages in Murbad
Most active promoters
- Sai Siddhi Developers2 projects
- Satyashiv Developers2 projects
- Bhimraj Ganpat More1 project
- Deepak Shivaji Hindurao1 project
- Dys Builtcon1 project
- Eagle Homes Builders And Developers1 project
- Mauli Construction1 project
- Mayur Shankar Chaudhari1 project
- Mohan Atmaram Sase1 project
- Nanda Arjun Shelke1 project
Murbad, in questions
How many projects in Murbad run late?
8 in 10 MahaRERA registrations (27 of 33): their completion date was extended or has passed, data through 21 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Murbad by Deedo. Medians on fewer than 3 deeds are not shown.
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology