8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects4
Registrations4
Completion still due31 past their date
Median extension4 months50% of registrations extended
Regulatory cases1on 1 project

8 in 10 registrations run late here

4 MahaRERA registrations in Patgaon

1 not yet due2 extended, not yet due1 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Patgaon

4 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Heritage VillasMadhusudan Infrabuild Private LimitedDue Apr 2030, extended 4 mo——
Madhusudan Retreat TerracesMadhusudan Leisure HomesDue Apr 2027, extended 4 mo——
Madhusudan RetreatMadhusudan Leisure HomesDue Mar 2027——
Karniks ExoticaKarniks ExoticaCompleted——
Patgaon market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Madhusudan Leisure Homes2 projects
  2. Karniks Exotica1 project
  3. Madhusudan Infrabuild Private Limited1 project

Patgaon, in questions

How many projects in Patgaon run late?

8 in 10 MahaRERA registrations (3 of 4): their completion date was extended or has passed, data through 21 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Patgaon by Deedo. Medians on fewer than 3 deeds are not shown.

Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology