Skip to content
Residential / Group Housing · 3 buildings · 208 unitsRERA P51700030172

Tharwani Solitaire Phase IV

Deedo IDDP-THN-5C1S

Completion was pushed back 4 months, to Nov 2026; no MahaRERA orders on record; 19% of its units are booked.

Mharal, Thane 421301 · by Anil Hardasmal Tharwani · 25% of its projects kept the RERA date

DeliveryExtended 4 moPromised Jul 2026 · now due Nov 2026RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales19% booked40 of 208 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Nov 2026

  • This projectRegistered 5 Aug 2021, completion promised 29 Jul 2026, revised to 29 Nov 2026.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

3 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700030172
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P517000301725 Aug 202129 Jul 202629 Nov 2026Anil Hardasmal TharwaniProject page
Documents122

1 document held by Deedo, 121 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN Cardanil tharwani pan card (1).pdf · uploaded 17 Jul 2021Source

Legal

  • Declaration Form B23.pdf · uploaded 17 Jul 2021Source
  • Legal Title reportupdated title report.pdf · uploaded 3 Aug 2021Source
  • Declaration Form BAffidavit Cum Declaration.pdf · uploaded 9 May 2024Source

Migrated

  • 1 PAN Cardanil tharwani pan card (1).pdf · uploaded 17 Jul 2021Source
  • 1 Details of encumbrancesNON ENCUMRANCE CERTIFICATE.pdf · uploaded 17 Jul 2021Source
  • 1 Copy of Layout Approval (in case of layout)MYSCAN_20210715_0001.pdf · uploaded 17 Jul 2021Source
Show all 122 documentsShow fewer documents

Migrated

  • 1 Building Plan Approval / NA Order for plotted developmentNP 14.pdf · uploaded 17 Jul 2021Source
  • 1 Declaration in FORM B23.pdf · uploaded 17 Jul 2021Source
  • 1 Declaration about Commencement CertificateDeclaration about CC.pdf · uploaded 19 Jul 2021Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE_compressed.pdf · uploaded 19 Jul 2021Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 - ENGG CERTIFICATE_compressed.pdf · uploaded 19 Jul 2021Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Solitaire Ph IV_compressed.pdf · uploaded 19 Jul 2021Source
  • 1 Proforma of Allotment letterallottment letter format Ph III-Converted.pdf · uploaded 19 Jul 2021Source
  • 2 Proforma of Allotment letterSolitaire Ph IV - Agg- FINAL.pdf · uploaded 19 Jul 2021Source
  • 2 Building Plan Approval / NA Order for plotted developmentNP 16.pdf · uploaded 27 Jul 2021Source
  • 1 Commencement Certificates / NA Order for plotted development20210715193037.pdf · uploaded 27 Jul 2021Source
  • 1 Copy of the legal title reportupdated title report.pdf · uploaded 3 Aug 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 5 Solitaire Ph IV - FY 2021-22.pdf · uploaded 27 Jan 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form III Solitaire Phase IV till March 2022 Signed.pdf · uploaded 3 Feb 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)30 June 22 solitaire ph 4 form 1.pdf · uploaded 14 Feb 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)30 September 22 solitaire ph 4 form 1.pdf · uploaded 14 Feb 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1-solitaire phase 4 .pdf · uploaded 14 Feb 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Sol Phase IV.pdf · uploaded 14 Feb 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)DocScanner 14 Feb 2023 6-50 pm.pdf · uploaded 14 Feb 2023Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)DocScanner 14 Feb 2023 6-50 pm-1.pdf · uploaded 14 Feb 2023Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)form2solitire phase 4_compressed.pdf · uploaded 14 Feb 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Q1 2022-2023 Solitaire IV.pdf · uploaded 14 Feb 2023Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Q2 2022-2023 Solitaire IV.pdf · uploaded 14 Feb 2023Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Q3 2022-2023 Solitaire IV.pdf · uploaded 14 Feb 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDocScanner 14 Feb 2023 11-53 am.pdf · uploaded 14 Feb 2023Source
  • 2 a Details of encumbrances concerned to FinanceDocScanner 9 Mar 2023 5-44 pm.pdf · uploaded 9 Mar 2023Source
  • 1 b Details of encumbrances concerned to LegalDocScanner 9 Mar 2023 5-44 pm.pdf · uploaded 9 Mar 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2A solitaire phase 4 2020 -2021.pdf · uploaded 29 Apr 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A Solitaire Phase IV 2021-2022.pdf · uploaded 29 Apr 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form2A_SOLITAIRE phase 4_FY2223.pdf · uploaded 13 Jul 2023Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_Q4_FY2022-2023_Solitaire Phase IV.pdf · uploaded 20 Aug 2023Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_Q4_FY2022-2023_Solitaire Phase IV.pdf · uploaded 20 Aug 2023Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Q4 2022-2023_Final_Signed_22062023_compressed.pdf · uploaded 20 Aug 2023Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Phase IV.pdf · uploaded 23 Aug 2023Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Solitaire phase 4 FORM 1.pdf · uploaded 27 Nov 2023Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)SOLITAIRE PHASE 4 FORM 2.pdf · uploaded 27 Nov 2023Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final Form 3- Signed_compressed.pdf · uploaded 27 Nov 2023Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Final Form 5- Signed with UDIN.pdf · uploaded 29 Nov 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Final Form 5- Signed with UDIN.pdf · uploaded 29 Nov 2023Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)SOLITAIRE PHASE 4 form 1.pdf · uploaded 13 Dec 2023Source
  • 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final Form 3 Solitaire Ph IV- Sep 2023 with UDIN.pdf · uploaded 10 Jan 2024Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)Solitaire Ph IV Form 2.pdf · uploaded 18 Jan 2024Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Tharwani solitaire phase 4(2).pdf · uploaded 25 Jan 2024Source
  • 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Q3 2023-2024_Final with UDIN.pdf · uploaded 17 Feb 2024Source
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Tharwani Solitaire Phase IV.pdf · uploaded 26 Feb 2024Source
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_Solitaire Ph IV.pdf · uploaded 7 May 2024Source
  • 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final Form 3 Solitaire Ph IV_March 2024.pdf · uploaded 8 May 2024Source
  • 2 Declaration in FORM BAffidavit Cum Declaration.pdf · uploaded 9 May 2024Source
  • 1 Disclosure of sold/ booked inventoryDisclosure of Sold-Booked Inventory.pdf · uploaded 9 May 2024Source
  • 2 Declaration about Commencement CertificateDECLARATION ABOUT COMMENCEMENT CERTIFICATE.pdf · uploaded 10 May 2024Source
  • 1 CERSAI detailsNO SECURITY INTEREST.pdf · uploaded 10 May 2024Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsANNEXURE A-Dislcosure in Other Real Estate Organisation.pdf · uploaded 10 May 2024Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFORMAT A-Declaration about Seperate Bank Account details.pdf · uploaded 10 May 2024Source
  • 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM -2 THARAWANI SOLITAIRE - IV_compressed.pdf · uploaded 27 May 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)THARAWANI SOLITAIRE PHASE -IV.pdf · uploaded 27 May 2024Source
  • 1 Proforma of Agreement for saleTharwani solitaire phase IV- AFS.pdf · uploaded 27 May 2024Source
  • 2 Copy of Layout Approval (in case of layout)01 Revised Approved Plan with Phase IV highlighted.pdf · uploaded 4 Jul 2024Source
  • 3 Building Plan Approval / NA Order for plotted development02 H Wing Layout Plan_Part 1.pdf · uploaded 4 Jul 2024Source
  • 4 Building Plan Approval / NA Order for plotted development03 H Wing Layout Plan_Part 2.pdf · uploaded 4 Jul 2024Source
  • 5 Building Plan Approval / NA Order for plotted development04 I Wing Layout Plan.pdf · uploaded 4 Jul 2024Source
  • 6 Building Plan Approval / NA Order for plotted development05 J Wing Layout Plan.pdf · uploaded 4 Jul 2024Source
  • 2 Commencement Certificates / NA Order for plotted development06 Revised Commencement Certificate.pdf · uploaded 4 Jul 2024Source
  • 3 Declaration about Commencement Certificate07 Declaration about Commencement Certificate_Form D.pdf · uploaded 4 Jul 2024Source
  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Solitaire Phase IV.pdf · uploaded 29 Jul 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_Solitaire Ph IV_Sep 2024.pdf · uploaded 4 Nov 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)scan- solitaire phase-IV.pdf · uploaded 9 Nov 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Final Form 5_Solitaire Ph IV on Letterhead.pdf · uploaded 28 Nov 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Scanned Form 3 Solitaire Ph IV June 2024_compressed.pdf · uploaded 17 Dec 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_Solitaire IV_June 2024.pdf · uploaded 31 Dec 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Scanned Form 3_Solitaire Ph IV_Sep 2024_compressed.pdf · uploaded 6 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 _Solitaire Ph IV_Sept 24.pdf · uploaded 20 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_Solitaire Ph IV Dec 2024.pdf · uploaded 25 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Scanned Form 3_Solitaire Ph IV Dec 2024_compressed.pdf · uploaded 11 Mar 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Solitaire-Form1.pdf · uploaded 26 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 _Solitaire_31-12-2024.pdf · uploaded 12 May 2025Source
  • Form 1Solitaire-Form1.pdf · uploaded 10 Jun 2025Source
  • Form 2Form 2_Solitaire Ph IV 25032025.pdf · uploaded 10 Jun 2025Source
  • Form 3Final Form 3_Solitaire Ph IV March 2025.pdf · uploaded 10 Jun 2025Source
  • Disclosure of Sold and Booked InventoryDisclosure of Sold Booked Inventory.pdf · uploaded 10 Jun 2025Source
  • Self-declaration of Quarterly ProgressSelf Declaration for Quaterly Progress.pdf · uploaded 10 Jun 2025Source
  • Form 2A (FY 2024-2025)Form 2A_Solitaire Ph IV_2024-25.pdf · uploaded 4 Aug 2025Source
  • Form 5 (FY 2024-2025)FORM 5 _ THARWANI REALTY - SOLITAIRE PHASE IV.pdf · uploaded 11 Oct 2025Source
  • Withdrawal Update Form 1Form 1_Soltaire Ph IV 30062025.pdf · uploaded 5 Dec 2025Source
  • Withdrawal Update Form 2Form 2_Solitaire Ph IV 30062025.pdf · uploaded 5 Dec 2025Source
  • Withdrawal Update Form 3Scanned Form 3_Solitaire Ph IV June 2025_compressed.pdf · uploaded 5 Dec 2025Source
  • Withdrawal Update Form 1Form 1_Solitaire Ph IV Sept 25.pdf · uploaded 20 Feb 2026Source
  • Withdrawal Update Form 2Form 2_Solitaire Phase IV Sep 2025.pdf · uploaded 20 Feb 2026Source
  • Withdrawal Update Form 3Final Form 3-Solitaire Phase IV Sep 2025.pdf · uploaded 20 Feb 2026Source
  • Withdrawal Update Form 1Form 1 Solitaire Ph IV_Dec 2025.pdf · uploaded 21 Feb 2026Source
  • Withdrawal Update Form 2Form 2_Solitaire Phase IV Dec 2025.pdf · uploaded 21 Feb 2026Source
  • Withdrawal Update Form 3Final Form 3-Solitaire Phase IV Dec 2025.pdf · uploaded 21 Feb 2026Source
  • Form 2A (FY 2021-2022)Form 2A Solitaire Phase IV 2021-2022.pdf · uploaded 21 Mar 2026Source
  • Form 2A (FY 2022-2023)Form2A_SOLITAIRE phase 4_FY2223.pdf · uploaded 21 Mar 2026Source
  • Form 2A (FY 2023-2024)THARAWANI SOLITAIRE PHASE -IV.pdf · uploaded 21 Mar 2026Source
  • Form 2A (FY 2025-2026)SOLITAIRE PHASE IV_SIGNED FORM 2A_compressed.pdf · uploaded 23 Apr 2026Source
  • Withdrawal Update Form 1Signed_Form 1_Tharwani Solitaire Phase IV_Mar 26.pdf · uploaded 8 Jul 2026Source
  • Withdrawal Update Form 2Signed_Form - 2 - Certificates of Engineer-Solitaire phase IV March 2026 Final.pdf · uploaded 8 Jul 2026Source
  • Withdrawal Update Form 3Final Form 3 Solitaire Ph IV_20032026.pdf · uploaded 8 Jul 2026Source

Technical

  • DocumentMYSCAN_20210715_0001.pdf · uploaded 17 Jul 2021Source
  • DocumentNP 14.pdf · uploaded 17 Jul 2021Source
  • DocumentNP 16.pdf · uploaded 27 Jul 2021Source
  • Document01 Revised Approved Plan with Phase IV highlighted.pdf · uploaded 4 Jul 2024Source
  • Document02 H Wing Layout Plan_Part 1.pdf · uploaded 4 Jul 2024Source
  • Document03 H Wing Layout Plan_Part 2.pdf · uploaded 4 Jul 2024Source
  • Document04 I Wing Layout Plan.pdf · uploaded 4 Jul 2024Source
  • Document05 J Wing Layout Plan.pdf · uploaded 4 Jul 2024Source
  • OthersOC_Tharwani Solitaire_WIng H_Topaz.pdf · uploaded 17 Sep 2025Source

Technical (Architect)

  • DocumentForm 1_Solitaire Ph IV_Sep 2024.pdf · uploaded 4 Nov 2024Source
  • DocumentForm 1_Solitaire Ph IV Dec 2024.pdf · uploaded 25 Feb 2025Source
  • DocumentSolitaire-Form1.pdf · uploaded 26 Apr 2025Source
  • DocumentSigned_Form 1_Tharwani Solitaire Phase IV_Mar 26.pdf · uploaded 8 Jul 2026Source

Technical (Engineer)

  • DocumentForm 2_Solitaire IV_June 2024.pdf · uploaded 31 Dec 2024Source
  • DocumentForm 2 _Solitaire Ph IV_Sept 24.pdf · uploaded 20 Jan 2025Source
  • DocumentForm 2 _Solitaire_31-12-2024.pdf · uploaded 12 May 2025Source
  • DocumentSigned_Form - 2 - Certificates of Engineer-Solitaire phase IV March 2026 Final.pdf · uploaded 8 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 12/1 -12/7, 13/1

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
2BHK, 3BHK, 4BHK208 units in all
Address
8/1, 8/2, 12/1 -12/7, 13/1, 13/2, 14/1-14/4, Kalyan Murbad Road, ShahadPIN 421301
Village
mharal, Kalyan taluka
Land area for this project
24,163 sq m (2,60,086 sq ft)
Permissible built-up area
24,163 sq m (2,60,086 sq ft)
Sanctioned built-up area
24,163 sq m (2,60,086 sq ft)
Recreational open space
11,174 sq m (1,20,276 sq ft)
Designated bank account
21
Developed in phases
Yes

Survey, CTS, gat or plot numbers

12/1 -12/713/113/214/1-14/48/18/2

Land as published on MahaRERA's project page

8/1,8/2,12/1 -12/7, 13/1,13/2,14/1-14/4

Boundaries

North
Survey No 61
South
30 Mtr Wide Road National Highway 222
East
Survey No 61
West
Ulhasnagar Municipal Corporation Boundry

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking208 units

40 of 208 units booked (19%), as the promoter reported to MahaRERA

2BHK · 116 units3BHK · 90 units4BHK · 2 units
BuildingTypeCarpet areaUnitsBooked
Spinel2BHK61.73 sq m · 664 sq ft150
Spinel3BHK88.8 sq m · 956 sq ft150
Spinel3BHK91.42 sq m · 984 sq ft150
Spinel3BHK94.84 sq m · 1,021 sq ft150
Topaz2BHK66.6 sq m · 717 sq ft137
Topaz2BHK69.11 sq m · 744 sq ft158
Topaz2BHK72.91 sq m · 785 sq ft138
Topaz3BHK82.85 sq m · 892 sq ft20
Show all 13 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
Topaz3BHK93.97 sq m · 1,011 sq ft305
Topaz3BHK106.47 sq m · 1,146 sq ft1311
Topaz4BHK128.78 sq m · 1,386 sq ft20
Vivianite2BHK66.6 sq m · 717 sq ft300
Vivianite2BHK70.12 sq m · 755 sq ft301

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals5

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectDinesh Bajaj—
Chartered accountantSunny Bhagia & Associates—
Chartered accountantVinod Santoshkumar Dhankani—
EngineerKiran Sharad Surve—
OtherMondal Enterprises—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Mharal

All 10 projects in Mharal · Compare Tharwani Solitaire Phase IV with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology