Anil Hardasmal Tharwani
Deedo IDDD-K9SNOf 4 registrations whose promised date has arrived, 1 kept it (25%). The rest ran a median 18 mo late.
Delivery record
3 of 4 registrations with dates moved or missed their RERA date · months late against the original promise
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Tharwani SolitaireP51700004565 | Mharal Kh. (N.V) | Certificate Signed | 30 Apr 2019 | 29 Oct 2020 | +18 mo |
| Tharwani SolitaireP51700005135 | Mharal Kh. (N.V) | Certificate Signed | 30 Mar 2021 | 29 Sep 2022 | +68 mo* |
| Tharwani SolitaireP51700005630 | Mharal Kh. (N.V) | Certificate Signed | 30 Apr 2018 | 30 Apr 2018 | On date |
| Tharwani Solitaire Phase IVP51700030172 | Mharal | Certificate Signed | 29 Jul 2026 | 29 Nov 2026 | +4 mo |
Anil Hardasmal Tharwani, in questions
Does Anil Hardasmal Tharwani finish projects on time?
Of 4 MahaRERA registrations whose promised completion date has arrived, 1 kept it (25%). The rest ran a median 18 mo late. Across Maharashtra, 73% kept their date.
How many projects has Anil Hardasmal Tharwani registered with MahaRERA?
2 projects under 4 MahaRERA registrations; 2 completed on MahaRERA.
Does Anil Hardasmal Tharwani have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.