Completion was pushed back 1 year and 6 months, to Nov 2026; no MahaRERA orders on record; 93% of its units are booked.

Mharal, Thane 421103 · Promoter: Vinayak Associates

DeliveryExtended 1 yr 6 moPromised May 2025 · now due Nov 2026RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales93% booked153 of 164 units · as the promoter reported to MahaRERA
Precious Meadows project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

Completion was pushed back 1 year and 6 months, to Nov 2026

  • This projectRegistered 9 Feb 2022, completion promised 31 May 2025, revised to 30 Nov 2026.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700033139
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P517000331399 Feb 202231 May 202530 Nov 2026Vinayak AssociatesProject page
Documents64

2 documents held by Deedo, 62 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Finance

  • PAN Card12 Vinayak associates PAN.pdf · uploaded 17 Dec 2021Source

Legal

  • Legal Title reportLegal Title Report.pdf · uploaded 20 Jan 2022Source
  • Declaration Form BForm B_compressed.pdf · uploaded 2 Feb 2022Source
  • Legal Title reportTitle.pdf · uploaded 20 Sep 2023Source
  • Declaration Form BVinayak associates form B declaration.pdf · uploaded 24 Apr 2025Source

Migrated

  • 1 PAN Card12 Vinayak associates PAN.pdf · uploaded 17 Dec 2021Source
Show all 64 documentsShow fewer documents

Migrated

  • 1 Details of encumbrancesNo Encumbrance.pdf · uploaded 17 Dec 2021Source
  • 1 Copy of Layout Approval (in case of layout)9 Approved Plan Layout 1.PDF · uploaded 17 Dec 2021Source
  • 1 Building Plan Approval / NA Order for plotted development9 Approved Plan Layout 1.PDF · uploaded 17 Dec 2021Source
  • 1 Commencement Certificates / NA Order for plotted development8 Commencement certificarte_compressed.pdf · uploaded 17 Dec 2021Source
  • 1 Proforma of Allotment letterAllotment Letter.pdf · uploaded 17 Dec 2021Source
  • 1 CERSAI detailsCERSAI_Search_Report_200226101123.pdf · uploaded 18 Dec 2021Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate - Vinayak Associates_compressed.pdf · uploaded 18 Dec 2021Source
  • 1 Copy of the legal title reportLegal Title Report.pdf · uploaded 20 Jan 2022Source
  • 2 Proforma of Allotment letterDraft Sale Agreement.pdf · uploaded 20 Jan 2022Source
  • 1 Declaration about Commencement CertificateFormat D.pdf · uploaded 2 Feb 2022Source
  • 1 Declaration in FORM BForm B_compressed.pdf · uploaded 2 Feb 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Vinayak Asso Form 5.pdf · uploaded 23 Jan 2023Source
  • 2 Copy of the legal title reportTitle.pdf · uploaded 20 Sep 2023Source
  • 1 Proforma of Agreement for saleDraft AFS 20092023.pdf · uploaded 20 Sep 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_compressed.pdf · uploaded 19 Oct 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 19 Oct 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 30-9-23_compressed.pdf · uploaded 19 Oct 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 VA (M).pdf · uploaded 12 Dec 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Vinayak Associates Architect certificate.pdf · uploaded 20 Jan 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Rera Form 2 - Vinayak asso.pdf · uploaded 20 Jan 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Rera Form 2 - Vinayak asso.pdf · uploaded 20 Apr 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Vinayak Associates Form 1.pdf · uploaded 20 Jul 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Rera Form 2 Vinayak asso.pdf · uploaded 20 Jul 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)VA Form 1 ARC Q2.pdf · uploaded 31 Oct 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Rera Form 2 - Vinayak asso ENG Q2.pdf · uploaded 31 Oct 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Signed Form 5 VA.pdf · uploaded 2 Dec 2024Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentPart OC (Promoter Copy).pdf · uploaded 14 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 22 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)vaENGINEER CERTIFICATE FORM 2 (2).pdf · uploaded 27 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 VA_compressed.pdf · uploaded 31 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Signed Form 1 Vinayak Associates.pdf · uploaded 18 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Signed Form 3_11zon.pdf · uploaded 18 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Signed Rera Form 2 - Vinayak associates.pdf · uploaded 18 Apr 2025Source
  • 1 Declaration in FORM BVinayak associates form B declaration.pdf · uploaded 24 Apr 2025Source
  • 1 Disclosure of sold/ booked inventoryVinayak Associates Disclosure.pdf · uploaded 1 May 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Quality Assurance Certifi 21-22.pdf · uploaded 1 May 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Quality Certificate Certifi 22-23.pdf · uploaded 1 May 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Quality Assurance Certifi 23-24.pdf · uploaded 1 May 2025Source
  • Form 5 (FY 2024-2025)Vinayak Associates form 5 scanned SIGNED.pdf · uploaded 29 Sep 2025Source
  • Withdrawal Update Form 1Vinayak associates form 1(2).pdf · uploaded 14 Jan 2026Source
  • Withdrawal Update Form 2Vinayak associates Form 2.pdf · uploaded 14 Jan 2026Source
  • Withdrawal Update Form 3Signed Form 3_11zon.pdf · uploaded 14 Jan 2026Source
  • Occupational CertificateGmail.pdf · uploaded 16 Jan 2026Source
  • Occupational CertificateOC Plan.pdf · uploaded 16 Jan 2026Source
  • Occupational CertificatePRECIOUS -VINAYAK ASSOCIATES -FULL OC.pdf · uploaded 16 Jan 2026Source
  • Form 5 (FY 2025-2026)Form 5 Signed.pdf · uploaded 30 Sep 2026Source

Technical

  • Document9 Approved Plan Layout 1.PDF · uploaded 17 Dec 2021Source
  • Document9 Approved Plan Layout 1.PDF · uploaded 17 Dec 2021Source

Technical (Architect)

  • DocumentVA Form 1 ARC Q2.pdf · uploaded 31 Oct 2024Source
  • DocumentForm 1.pdf · uploaded 22 Jan 2025Source
  • DocumentSigned Form 1 Vinayak Associates.pdf · uploaded 18 Apr 2025Source
  • DocumentVinayak associates form 1(2).pdf · uploaded 14 Jan 2026Source

Technical (Engineer)

  • DocumentRera Form 2 - Vinayak asso ENG Q2.pdf · uploaded 31 Oct 2024Source
  • DocumentvaENGINEER CERTIFICATE FORM 2 (2).pdf · uploaded 27 Jan 2025Source
  • DocumentSigned Rera Form 2 - Vinayak associates.pdf · uploaded 18 Apr 2025Source
  • DocumentVinayak associates Form 2.pdf · uploaded 14 Jan 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvals2T, 4

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK, Shop164 units in all
Address
Survey No.14, Hissa No 2A and 2T, Survey No.17, Hissa No.3P, 4 and 5A, Survey No.18, Hissa No.1A, , Mharal, MharalPIN 421103
Village
mharal, Kalyan taluka
Designated bank account
76
Developed in phases
No

Survey, CTS, gat or plot numbers

2T45AHissa No.1AHissa No 2AHissa No.3PSurvey No.14Survey No.17Survey No.18

Boundaries

North
Road and S No 17 Hissa No 3 P
South
Road and S No 17 and 18
East
S No 16
West
Road and S No 17 Hissa No 3P

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking164 units

153 of 164 units booked (93%), as the promoter reported to MahaRERA

1BHK · 99 units2BHK · 56 unitsShop · 9 units
TypeCarpet areaUnitsBooked
1BHK33.91 sq m · 365 sq ft4242
1BHK33.97 sq m · 366 sq ft1414
1BHK34.16 sq m · 368 sq ft1413
1BHK34.26 sq m · 369 sq ft1414
1BHK34.84 sq m · 375 sq ft1414
1BHK44.22 sq m · 476 sq ft10
2BHK50.05 sq m · 539 sq ft1414
2BHK50.23 sq m · 541 sq ft1413
Show all 17 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
2BHK53.42 sq m · 575 sq ft1414
2BHK54.39 sq m · 585 sq ft1414
Shop7 sq m · 75 sq ft10
Shop9.06 sq m · 98 sq ft10
Shop9.17 sq m · 99 sq ft10
Shop13 sq m · 140 sq ft20
Shop30.24 sq m · 326 sq ft11
Shop36.72 sq m · 395 sq ft20
Shop38.63 sq m · 416 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectKaranjali Arch—
Chartered accountantMukesh Premchand Gurnani—
EngineerM Nandwani—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology