Chendani, Thane
Deedo IDDL-THN-CHENDANI8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects9
Registrations9
Completion still due72 past their date
Median extension4 months56% of registrations extended
Regulatory cases0none on MahaRERA's lists
8 in 10 registrations run late here
9 MahaRERA registrations in Chendani
2 not yet due5 extended, not yet due2 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Chendani
9 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Dinesh Co Op Hsg SocietySamarth Vardhaman Developers | Due Jul 2030 | — | — |
| Veer DevikaYash Infra | Due Jul 2029, extended 4 mo | — | — |
| Chamunda MayfairChamunda Infrastructure Limited | Due Apr 2029, extended 4 mo | — | — |
| Umanand Co Operative Housing Society LimitedRushabh Developers | Due Apr 2029, extended 4 mo | — | — |
| Shree Darshan Co-operative Housing Society LimitedOjass Govind Infra LLP | Due Sep 2028, extended 4 mo | — | — |
| Sujan Co-Op. Hsg. Soc. Ltd.Joshi And Vishwas Realtors LLP | Due Dec 2026, extended 4 mo | — | — |
| Pramila HeightsPrime Developers | Completed | — | 70% |
| Viraj HeightsV-Raj Buildcon | Due Jun 2028 | — | — |
| MangalamDeepa Suresh Gada | Completed | — | — |
Nearby: other villages in Thane
Thane (M Corp.) · 898 projectsNavi Mumbai (M Corp.) · 271 projectsMirabhayandar (M Corp.) · 225 projectsBhayandar · 118 projectsMira Bhayandar (M Corp.) · 106 projectsNaupada · 72 projectsPanchpakhadi · 65 projectsNerul · 58 projectsGhansoli · 57 projectsMajiwade · 43 projectsMumbra · 28 projectsOwale · 28 projects
Most active promoters
- Chamunda Infrastructure Ltd1 project
- Deepa Suresh Gada1 project
- Joshi And Vishwas Realtors Llp1 project
- Ojass Govind Infra Llp1 project
- Prime Developers1 project
- Rushabh Developers1 project
- Samarth Vardhaman Developers1 project
- VRaj Buildcon1 project
- V-Raj Buildcon1 project
- Yash Infra1 project
Chendani, in questions
How many projects in Chendani run late?
8 in 10 MahaRERA registrations (7 of 9): their completion date was extended or has passed, data through 3 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Chendani by Deedo. Medians on fewer than 3 deeds are not shown.
Data through3 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology