Badlapur (M Cl), Thane

Deedo IDDL-THN-BADLAPUR

9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects715
Registrations752some projects hold several
Completion still due209543 past their date
Median extension4 months35% of registrations extended
Regulatory cases44on 9 projects

9 in 10 registrations run late here

752 MahaRERA registrations in Badlapur (M Cl)

13 completed53 not yet due156 extended, not yet due530 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Badlapur (M Cl)

715 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Gokul HeightsSairaj DevelopersDue Dec 2029——
Saurabh SankulS K DevelopersDue Dec 2028——
Sai Chhaya Co.op. Housing SocietyPrakash Jagannath ManeDue Dec 2026——
Grand Unity ResidencesYash EnterprisesDue May 2028——
James Residency Phase 3Sudhir Damodar GhatnekarDue Jun 2027——
Om Ambika Darshan Chs LtdSharvi EnterprisesDue Dec 2028——
Varun EnclaveVarun Builders And DevelopersDue Dec 2028——
Varun VistaVarun Builders And DevelopersDue Dec 2028——
Varun HillcrestVarun Builders And DevelopersDue Dec 2027——
Panvelkar Evoke Co-op Housing Society LtdPanvelkar Group InfrastructureDue Dec 2028——
Swanand VedikaAtharv InfrastructuresDue Jun 2029——
Om Sumukh Darshan ChslPnr Group DevelopersDue Dec 2026——
Dashmesh PearlEmpire RealtyDue Dec 2026—53%
Akanksha Co. Op. Hsg. Soc. Ltd.Krishna BuildconDue Dec 2026——
Om Anant PalaceYogeshwar DevelopersDue Mar 2029——
Om Guru Krupa Co-Op. Housing Society LtdSairaj ConstructionDue Mar 2027——
Krishna Nayan Complex Phase IShreeji Builders And DevelopersDue Dec 2027——
Crystal HeightsSupreme DevelopersDue Apr 2027——
Satyam AnantamShivansh InfraDue Dec 2026—53%
Krishna Dham - 2Atree RealtorsDue Dec 2026——
Seventh AvenuePawar GroupDue Dec 2031——
Riddhi Siddhi ChsVadnere Builder & DevelopersDue Dec 2026—18%
Panvelkar Nisarg Phase II Building A2Panvelkar Realty Pvt LtdDue Dec 2026—7%
Vrundavan HeightsMaulikrupa DevelopersDue Dec 2026—40%
Prathmesh Vrindavan F WingS. P. GroupDue Dec 2026——
Badlapur (M Cl) market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Mohan Hardasmal Tharwani7 projects
  2. Raj Group6 projects
  3. Ashish Waman Gole5 projects
  4. M K Patil Developers5 projects
  5. Mohan Lifespaces Llp5 projects
  6. Panvelkar Infrastructures Private Limited5 projects
  7. Sai Shradha Developers5 projects
  8. Bhavani Enterprises4 projects
  9. Bhushan Nandkishor Patkar4 projects
  10. Sai Properties4 projects

Badlapur (M Cl), in questions

How many projects in Badlapur (M Cl) run late?

9 in 10 MahaRERA registrations (686 of 752): their completion date was extended or has passed, data through 30 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Badlapur (M Cl) by Deedo. Medians on fewer than 3 deeds are not shown.

Data through30 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology