Vrundavan Heights
Certificate SignedBadlapur (M Cl), Thane 421503 |Promoter: Maulikrupa Developers
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Buildings
- 3
- Unit types
- 1BHK, 2BHK, Shop45 units in all
- Address
- Survey No 39/6/A, Shrigaon, ShrigaonPIN 421503
- Designated bank account
- 66
- Developed in phases
- Yes
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 31 Dec 2026
- Registered
- 23 Oct 2023
- Promised
- 31 Dec 2026
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700053292 | 23 Oct 2023 | 31 Dec 2026 | 31 Dec 2026 | Maulikrupa Developers | Project page |
3 buildings
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| Vrundavan Heights Wing A | 7 | 20 |
| Vrundavan Heights Wing B | 4 | 17 |
| Vrundavan Heights Wing C | 3 | 8 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
18 of 45 units booked (40%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Vrundavan Heights Wing A | 1BHK | 441.75 sq m · 4,755 sq ft | 13 | 0 |
| Vrundavan Heights Wing A | 2BHK | 320.53 sq m · 3,450 sq ft | 7 | 1 |
| Vrundavan Heights Wing B | 1BHK | 342.36 sq m · 3,685 sq ft | 12 | 12 |
| Vrundavan Heights Wing B | Shop | 52.05 sq m · 560 sq ft | 5 | 5 |
| Vrundavan Heights Wing C | 1BHK | 130.16 sq m · 1,401 sq ft | 4 | 0 |
| Vrundavan Heights Wing C | Shop | 51.24 sq m · 552 sq ft | 4 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Documents
1 document held by Deedo, 86 filings listed on MahaRERA's project page
Finance
- PAN CardAll PAN.pdf · uploaded 28 Aug 2023Source
Legal
Show all 87 documentsShow fewer documents
Migrated
- 1 Commencement Certificates / NA Order for plotted developmentAppendix D-1.pdf · uploaded 28 Aug 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect certificate.pdf · uploaded 28 Aug 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engg certificate.pdf · uploaded 28 Aug 2023Source
- 1 Proforma of Allotment letterAllotment format.pdf · uploaded 28 Aug 2023Source
- 1 Declaration about Commencement CertificateDecleration o commencement certificate.pdf · uploaded 1 Sep 2023Source
- 1 CERSAI detailsDecleration of Cersai.pdf · uploaded 2 Sep 2023Source
- 1 Proforma of Agreement for salemauli krupa shirgaon rera agreement for sale.pdf · uploaded 2 Sep 2023Source
- 1 Deviation Report with respect to Allotment letterDeviation report of allotment letter.pdf · uploaded 2 Sep 2023Source
- 1 a Details of encumbrances concerned to FinanceTo finance and legal.pdf · uploaded 4 Sep 2023Source
- 1 b Details of encumbrances concerned to LegalTo finance and legal.pdf · uploaded 4 Sep 2023Source
- 1 Deviation Report with respect to model copy of AgreementDeviation of Model sale Agreement.pdf · uploaded 4 Sep 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Latest CA FORM fOR rera.pdf · uploaded 8 Sep 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBank decleration A.pdf · uploaded 8 Sep 2023Source
- 1 Copy of Layout Approval (in case of layout)Layout Plan_compressed.pdf · uploaded 9 Sep 2023Source
- 1 Building Plan Approval / NA Order for plotted developmentBuilding Plan_compressed.pdf · uploaded 9 Sep 2023Source
- 1 Other – LegalSale Deed.pdf · uploaded 12 Sep 2023Source
- 2 Other – LegalsALE DEED 2_compressed (1).pdf · uploaded 13 Sep 2023Source
- 1 Declaration in FORM BB Affidavit.pdf · uploaded 9 Oct 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsA Mauli Krupa Developers_11zon.pdf · uploaded 9 Oct 2023Source
- 1 Other – TechnicalCC Verification.pdf · uploaded 9 Oct 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Vrundavan Heights Form 1.pdf · uploaded 19 Jan 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Vrundavan Heights.pdf · uploaded 19 Jan 2024Source
- 1 Disclosure of sold/ booked inventoryINVENTORY_F.pdf · uploaded 31 Jan 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 F.pdf · uploaded 8 May 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 F.pdf · uploaded 8 May 2024Source
- 2 Disclosure of sold/ booked inventoryINVENTROY DISCLOSURE F.pdf · uploaded 8 May 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 MAULI KRUPA DEV_compressed.pdf · uploaded 8 Aug 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 MAULI KRUPA DEV_1.pdf · uploaded 8 Aug 2024Source
- 3 Disclosure of sold/ booked inventoryINVENTORY_MAULIKRUPA.pdf · uploaded 13 Aug 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 MAULIKRUPA DEV_Q2.pdf · uploaded 12 Dec 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 MAULIKRUPA DEV_Q2.pdf · uploaded 12 Dec 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 3 Feb 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 3 Feb 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM 5 MAULIKRUPA.pdf · uploaded 12 Feb 2025Source
- Form 1FORM 1 Q3 23-24.pdf · uploaded 31 Jan 2026Source
- Form 2FORM 2 Q3 23-24.pdf · uploaded 31 Jan 2026Source
- Disclosure of Sold and Booked InventoryINVENTORY Q3 23-24.pdf · uploaded 31 Jan 2026Source
- Form 3FORM 3 REG.pdf · uploaded 31 Jan 2026Source
- Form 1FORM 1 Q4 23-24.pdf · uploaded 31 Jan 2026Source
- Form 2FORM 2 Q4 23-24.pdf · uploaded 31 Jan 2026Source
- Disclosure of Sold and Booked InventoryINVENTROY Q4 23-24.pdf · uploaded 31 Jan 2026Source
- Form 3FORM 3 REG.pdf · uploaded 31 Jan 2026Source
- Form 1FORM 1 Q1 24-25.pdf · uploaded 31 Jan 2026Source
- Form 2FORM 2 Q1 24-25.pdf · uploaded 31 Jan 2026Source
- Form 3FORM 3 REG.pdf · uploaded 31 Jan 2026Source
- Disclosure of Sold and Booked InventoryINVENTORY Q1 24-25.pdf · uploaded 31 Jan 2026Source
- Withdrawal Update Form 1FORM 1 Q1 25-26 F.pdf · uploaded 10 Feb 2026Source
- Withdrawal Update Form 1FORM 1 Architect Certificate .pdf · uploaded 10 Feb 2026Source
- Withdrawal Update Form 2FORM 2 Q1 25-26 F.pdf · uploaded 10 Feb 2026Source
- Withdrawal Update Form 2FORM 2 ENGINEERS CERTIFICATE.pdf · uploaded 10 Feb 2026Source
- Withdrawal Update Form 3FORM 3 Q1.pdf · uploaded 10 Feb 2026Source
- Withdrawal Update Form 3FORM 3 Q1.pdf · uploaded 10 Feb 2026Source
- Withdrawal Update Form 1Form 1 ARCHITECH.pdf · uploaded 13 Feb 2026Source
- Withdrawal Update Form 2Form 2 Final Engineer.pdf · uploaded 13 Feb 2026Source
- Withdrawal Update Form 3FORM 3.pdf · uploaded 13 Feb 2026Source
- Withdrawal Update Form 1Form 1 ARCHITECH.pdf · uploaded 20 Mar 2026Source
- Withdrawal Update Form 2Form 2 Final Engineer.pdf · uploaded 20 Mar 2026Source
- Withdrawal Update Form 3FORM 3 FINAL 2032026.pdf · uploaded 20 Mar 2026Source
- Withdrawal Update Form 1FORM 1_Q4 2526.pdf · uploaded 29 Apr 2026Source
- Withdrawal Update Form 2FORM 2_Q4 2526.pdf · uploaded 29 Apr 2026Source
- Withdrawal Update Form 3FORM 3 Q4 25-26.pdf · uploaded 29 Apr 2026Source
- Form 5 (FY 2023-2024)FORM 5 MAULIKRUPA.pdf · uploaded 22 May 2026Source
- Form 5 (FY 2024-2025)FORM 5.pdf · uploaded 22 May 2026Source
- Form 2A (FY 2023-2024)FORM 2A.pdf · uploaded 30 May 2026Source
- Form 2A (FY 2024-2025)Form 2A SCAN.pdf · uploaded 30 May 2026Source
- Form 2A (FY 2025-2026)Form 2A 25-26.pdf · uploaded 3 Jun 2026Source
- Form 5 (FY 2025-2026)FORM 5.pdf · uploaded 25 Jun 2026Source
- Withdrawal Update Form 1FORM 1 Q1 2627.pdf · uploaded 22 Jul 2026Source
- Withdrawal Update Form 2FORM 2 Q1 2627.pdf · uploaded 22 Jul 2026Source
- Withdrawal Update Form 3FORM 3 Q1 2627 FINAL.pdf · uploaded 22 Jul 2026Source
Technical
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Badlapur (M Cl), Ambarnath taluka
Survey, CTS, gat or plot numbers
Boundaries
- North
- Survey No39 Hissa No 11
- South
- Survey No 39 Hissa No7
- East
- Survey No 38 Hisaa No 11
- West
- Survey number 40
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Raj Associates | — |
| Chartered accountant | Anil Motwani | — |
| Chartered accountant | Naresh Patel and Company | — |
| Chartered accountant | Shrinath Aswinkumar Patel | — |
| Engineer | Atul Kudtarkar and Associates Pvt Ltd | — |
| Engineer | Suraj Vishwakarma | — |
Source: MahaRERA project page. Contact details are not shown.