RERA projects in Ambeshiv Bk

2 projects under 2 MahaRERA registrations, registered 2021–2023. None has an extended completion date on record.

Locality
2RERA projects
2Registrations
1Completion still due1 past their completion date
—Median extension beyond promised date0% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20211
20220
20231

Projects in Ambeshiv Bk

2 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Ananta Pride Phase IIPatkar RealtyP5170005337627 Oct 202331 Jul 2029—Not yet due0
Ananta Pride Phase IPatkar RealtyP5170002997720 Jul 202131 Dec 2025—Promised date passed0

Other localities in Ambarnath

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Patkar Realty2 projects
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology