Wardoli, Raigarh

Deedo IDDL-RAI-WARDOLI

6 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects28
Registrations35some projects hold several
Completion still due332 past their date
Median extension4 months51% of registrations extended
Regulatory cases1on 1 project

6 in 10 registrations run late here

35 MahaRERA registrations in Wardoli

15 not yet due18 extended, not yet due2 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Wardoli

28 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Wise City, South Block Phase I, Plot RZ8 Building 4 Wing F3Wadhwa Construction and Infrastructure Private LimitedCompleted—68%
Wise City, South Block Phase I, Plot RZ8 Building 4 Wing F4Wadhwa Construction and Infrastructure Private LimitedCompleted—82%
Wise City, South Block Phase I, Plot RZ8 Building 1 Wing A1Wadhwa Construction and Infrastructure Private LimitedCompleted—96%
Wardoli market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Wadhwa Construction And Infrastructure Private Limited23 projects
  2. Anant Builders2 projects
  3. Greenpath Realty Private Limited2 projects
  4. Property Pioneers1 project

Wardoli, in questions

How many projects in Wardoli run late?

6 in 10 MahaRERA registrations (20 of 35): their completion date was extended or has passed, data through 21 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Wardoli by Deedo. Medians on fewer than 3 deeds are not shown.

Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology