Ulawe, Raigarh
Deedo IDDL-RAI-ULAWE10 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects697
Registrations698some projects hold several
Completion still due127571 past their date
Median extension4 months27% of registrations extended
Regulatory cases10on 6 projects
10 in 10 registrations run late here
698 MahaRERA registrations in Ulawe
1 completed32 not yet due95 extended, not yet due570 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Ulawe
697 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| OrchidsSerene Lifespaces | Completed | — | 33% |
| Janki VillaShree Krishna Builders | 1 yr 8 mo late | — | — |
| Shreeji GlaciaShivparvati Infra Private Limited | 1 yr 2 mo late | — | — |
| A N FloraAbdulnayeem Fatekhan | 2 yrs 10 mo late | — | — |
| Guruji ResidencyKishan Rajpat Medesia | Due Apr 2027, extended 4 mo | — | — |
| La-CasaRishabh Rajendra Shah | 8 mo late | — | 18% |
| Shreeji Kuber CornerShreeji Realty | 1 yr 5 mo late | — | 95% |
| Bhaveshwar FeatherGeo Enterprises | Due Dec 2027 | — | — |
| Shree Ganesh ResidencyM G Construction | 1 yr 5 mo late | — | — |
| Trident CornerTrident Infra | Completed, extended 1 yr | — | 86% |
| Mithun Dhanaji MhatreMithun Dhanaji Mhatre | 1 yr 10 mo late | — | 25% |
| Om Sai ResidencyYuvraj Kisan Owalekar | 3 yrs 2 mo late | — | — |
| Ambika AuraAmbika Enterprises | Due Apr 2027, extended 4 mo | — | — |
| Rajmudra IconShivaji Narayan Koli | Completed | — | — |
| Reddys CrownThirupathi Reddy Annapu Reddy Reddy | Due Apr 2027, extended 4 mo | — | — |
| Prime SolitairePrime Builders And Developers | 1 yr 1 mo late | — | 26% |
| Arihant VillaArihant Buildcon | 11 mo late | — | 30% |
| Jg PlanetJitendra Ramnarayan Giri | 11 mo late | — | — |
| Sai Krupa ResidencyM G Construction | 11 mo late | — | — |
| A.S.OrnateTrinity Realcon LLP | Due Dec 2026 | — | 14% |
| Jayesh CallistoJayesh Infrastructure And Projects Private Limited | Completed | — | 35% |
| Jupiter ArihantArjun Ashok Tarachandani | Due Apr 2027, extended 4 mo | — | — |
| Jupiter RoyalArjun Ashok Tarachandani | Due Mar 2027, extended 4 mo | — | 50% |
| Mahavir DarshanMahavir Construction | 11 mo late | — | 100% |
| Shree Siddhivinayak ParadiseKrishna Realty | Due Apr 2028, extended 4 mo | — | 11% |
Nearby: other villages in Panvel
Most active promoters
- Mahavir Construction7 projects
- Shree Riddhi Siddhi Constructions7 projects
- Tejas Enterprises7 projects
- Serene Lifespaces5 projects
- Varniraj Group5 projects
- Hare Krishna Enterprises4 projects
- Lakhani Builders Pvt Ltd4 projects
- Manoj Kumar Singh4 projects
- Mmg Landmark Llp4 projects
- Sm Developers4 projects
Ulawe, in questions
How many projects in Ulawe run late?
10 in 10 MahaRERA registrations (665 of 698): their completion date was extended or has passed, data through 22 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Ulawe by Deedo. Medians on fewer than 3 deeds are not shown.
Data through22 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology