It is due for completion in Dec 2027, with no extension on record; no MahaRERA orders on record; 63% of its units are booked.

Ulawe, Raigarh 410206 · by Geo Enterprises

DeliveryDue Dec 2027No extension on recordRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales63% booked52 of 83 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

It is due for completion in Dec 2027, with no extension on record

  • This projectRegistered 27 Mar 2023, completion promised 31 Dec 2027.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52000050232
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5200005023227 Mar 202331 Dec 202731 Dec 2027Geo EnterprisesProject page
Documents80

1 document held by Deedo, 79 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardGeo Enterprises- Pancard.pdf · uploaded 14 Mar 2023Source

Legal

  • Declaration Form BForm B Promoter.pdf · uploaded 6 Mar 2023Source
  • Legal Title reportTitle Bhaveshwar Feather.pdf · uploaded 15 Mar 2023Source

Migrated

  • 1 a Details of encumbrances concerned to FinanceEncumbrance - Finance.pdf · uploaded 6 Mar 2023Source
  • 2 a Details of encumbrances concerned to FinanceEncumbrance Legal.pdf · uploaded 6 Mar 2023Source
  • 1 b Details of encumbrances concerned to LegalEncumbrance - Finance.pdf · uploaded 6 Mar 2023Source
  • 2 b Details of encumbrances concerned to LegalEncumbrance Legal.pdf · uploaded 6 Mar 2023Source
Show all 80 documentsShow fewer documents

Migrated

  • 1 Copy of Layout Approval (in case of layout)1 Copy of Layout Approval (in case of layout).pdf · uploaded 6 Mar 2023Source
  • 1 Building Plan Approval / NA Order for plotted development1 Building Plan Approval _ NA Order for plotted development (1).pdf · uploaded 6 Mar 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 6 Mar 2023Source
  • 1 Declaration about Commencement CertificateFormat D.pdf · uploaded 6 Mar 2023Source
  • 1 Declaration in FORM BForm B Promoter.pdf · uploaded 6 Mar 2023Source
  • 1 CERSAI detailsCERSAI_Search_Report_200261749869_For_Asset_Based_Search_01_03_2023_17_17_01_276 (1).pdf · uploaded 6 Mar 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)First Form 3 - Bhaveshwar Feather Final.pdf · uploaded 6 Mar 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A_compressed.pdf · uploaded 6 Mar 2023Source
  • 1 Proforma of Agreement for saleAFS_BHAVESHWAR FEATHERS_GEO ENTERPRISES_04032023 (1).pdf · uploaded 6 Mar 2023Source
  • 1 Proforma of Allotment letterAlloment_Bhaveshwar Feathers_Geo Enterprises_04032023 (1).pdf · uploaded 6 Mar 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFormat A.pdf · uploaded 6 Mar 2023Source
  • 1 Deviation Report with respect to Allotment letterDeviation Allotment .pdf · uploaded 6 Mar 2023Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation AFS (1).pdf · uploaded 6 Mar 2023Source
  • 1 PAN CardGeo Enterprises- Pancard.pdf · uploaded 14 Mar 2023Source
  • 1 Copy of the legal title reportTitle Bhaveshwar Feather.pdf · uploaded 15 Mar 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 with builder sign.pdf · uploaded 24 Jun 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2-Geo enterprises.pdf · uploaded 24 Jun 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Site Supervisor Letter Form 2A.pdf · uploaded 24 Jun 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)1 Project Information.pdf · uploaded 24 Jun 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)1 Form 3.pdf · uploaded 24 Jun 2023Source
  • 2 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFormat A Geo enterprises Separate account letter.pdf · uploaded 24 Jun 2023Source
  • 3 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameANNEXURE A - Geo Ent.pdf · uploaded 24 Jun 2023Source
  • 1 Other – TechnicalDeclaration Form 5 Geo.pdf · uploaded 24 Jun 2023Source
  • 2 Other – Technicalself declaration GEO.pdf · uploaded 24 Jun 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)5 4 Declaration Form 5 Geo.pdf · uploaded 30 Jun 2023Source
  • 4 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the same1 self declaration GEO.pdf · uploaded 30 Jun 2023Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A.pdf · uploaded 30 Oct 2023Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Signed Form 5.pdf · uploaded 30 Oct 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2_compressed.pdf · uploaded 1 Nov 2023Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A.pdf · uploaded 1 Nov 2023Source
  • 1 Disclosure of sold/ booked inventoryDisclouser of Sold Inventory.pdf · uploaded 1 Nov 2023Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 1 Nov 2023Source
  • 2 Commencement Certificates / NA Order for plotted development1 New CC.pdf · uploaded 18 Dec 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 2 Feb 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 27 Feb 2024Source
  • 2 Disclosure of sold/ booked inventorysold unsold inventory.pdf · uploaded 1 Mar 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)3 Form 3 - Bhaveshwar Feathers sign.pdf · uploaded 1 Mar 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)C16-15-ULWE RERA (2024 MARCH) (1).pdf · uploaded 16 Apr 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 with sign.pdf · uploaded 20 Apr 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 20 Apr 2024Source
  • 3 Disclosure of sold/ booked inventorySold Unsold Inventory.pdf · uploaded 20 Apr 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 18 Jul 2024Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Document 22.pdf · uploaded 19 Jul 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 2 Aug 2024Source
  • 4 Disclosure of sold/ booked inventorySold unsold declaration GE.pdf · uploaded 2 Aug 2024Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 10 Aug 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)1 Form 5 202324 GE.pdf · uploaded 22 Oct 2024Source
  • 2 Disclosure of sold/ booked inventorySold unsold declaration GE.pdf · uploaded 24 Oct 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 25 Oct 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Geo Enterprises.pdf · uploaded 14 Nov 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 14 Nov 2024Source
  • 1 Disclosure of sold/ booked inventorySold unsold declaration GE.pdf · uploaded 22 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 24 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Bhaveshwar Feathers Dec 24.pdf · uploaded 25 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 25 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 14 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 17 Apr 2025Source
  • 1 Disclosure of sold/ booked inventorySold unsold declaration GE.pdf · uploaded 17 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Bhaveshwar Feathers Q4.pdf · uploaded 22 Apr 2025Source
  • Form 5 (FY 2024-2025)Form 5.pdf · uploaded 30 May 2025Source

Technical

  • Document1 Copy of Layout Approval (in case of layout).pdf · uploaded 6 Mar 2023Source
  • Document1 Building Plan Approval _ NA Order for plotted development (1).pdf · uploaded 6 Mar 2023Source
  • Other – TechnicalDeclaration Form 5 Geo.pdf · uploaded 24 Jun 2023Source
  • Other – Technicalself declaration GEO.pdf · uploaded 24 Jun 2023Source

Technical (Architect)

  • DocumentDocument 22.pdf · uploaded 19 Jul 2024Source
  • DocumentForm 1.pdf · uploaded 25 Oct 2024Source
  • DocumentForm 1.pdf · uploaded 24 Jan 2025Source
  • DocumentForm 1.pdf · uploaded 14 Apr 2025Source

Technical (Engineer)

  • DocumentForm 2.pdf · uploaded 2 Aug 2024Source
  • DocumentForm 2.pdf · uploaded 14 Nov 2024Source
  • DocumentForm 2.pdf · uploaded 25 Jan 2025Source
  • DocumentForm 2.pdf · uploaded 17 Apr 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel Plot No C16, Sector 15

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
—83 units in all
Address
Plot No- C-16, Sector- 15, Sector- 15, UlwePIN 410206
Village
Ulawe, Panvel taluka
Land area for this project
1,200 sq m (12,914 sq ft)
Permissible built-up area
3,944 sq m (42,452 sq ft)
Sanctioned built-up area
3,944 sq m (42,452 sq ft)
Designated bank account
220
Developed in phases
No

Survey, CTS, gat or plot numbers

Plot No C16Sector 15

Land as published on MahaRERA's project page

Plot No- C-16, Sector- 15

Boundaries

North
15 meter wide road
South
Plot No- C-14 and C-15
East
Plot No- C-1
West
15 meter wide road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking83 units

83 units registered

— · 83 units
TypeCarpet areaUnits
——83

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals6

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAtul Patel Architects—
Chartered accountantA. T. Upadhye & Co.—
Chartered accountantDeepesh Shah & Associates—
Chartered accountantRutuja Narsingh and Associates—
EngineerHitesh Nandlal Borad—
OtherB S Sukthankar and Associates—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Ulawe

All 697 projects in Ulawe · Compare Bhaveshwar Feather with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology