Jupiter Royal
Deedo IDDP-RAI-6185Completion was pushed back 4 months, to Mar 2027; no MahaRERA orders on record; 50% of its units are booked.
Ulawe, Raigarh 410206 · by Arjun Ashok Tarachandani · 75% of its projects kept the RERA date
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Mar 2027
- This projectRegistered 24 Jan 2023, completion promised 30 Nov 2026, revised to 30 Mar 2027.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52000048883
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52000048883 | 24 Jan 2023 | 30 Nov 2026 | 30 Mar 2027 | Arjun Ashok Tarachandani | Project page |
Documents106
1 document held by Deedo, 105 filings listed on MahaRERA's project page
Finance
Show all 106 documentsShow fewer documents
Legal
- Declaration Form B1 Declaration in FORM B.pdf · uploaded 13 Jan 2023Source
- Declaration Form Bform b Landowners.pdf · uploaded 13 Jan 2023Source
- Legal Title reportFinal Legal Title Report Plot 125.pdf · uploaded 19 Jan 2023Source
- Other – LegalDA-1.pdf · uploaded 2 Oct 2023Source
- Other – LegalDA-2 (1).pdf · uploaded 2 Oct 2023Source
- Other – LegalDA-3 (1).pdf · uploaded 2 Oct 2023Source
Migrated
- 1 PAN CardPan Card Arjun Tarachandani.pdf · uploaded 13 Jan 2023Source
- 2 PAN CardJamil Pan aadhar.pdf · uploaded 13 Jan 2023Source
- 3 PAN CardRabana Pan aadhar.pdf · uploaded 13 Jan 2023Source
- 1 a Details of encumbrances concerned to Finance1 a Details of encumbrances concerned to Finance.pdf · uploaded 13 Jan 2023Source
- 2 a Details of encumbrances concerned to FinanceEncum to Legal LO.pdf · uploaded 13 Jan 2023Source
- 1 b Details of encumbrances concerned to Legal1 a Details of encumbrances concerned to Finance.pdf · uploaded 13 Jan 2023Source
- 2 b Details of encumbrances concerned to LegalEncum to Legal LO.pdf · uploaded 13 Jan 2023Source
- 1 Copy of Layout Approval (in case of layout)1 Copy of Layout Approval (in case of layout).pdf · uploaded 13 Jan 2023Source
- 1 Building Plan Approval / NA Order for plotted development1 Building Plan Approval _ NA Order for plotted development.pdf · uploaded 13 Jan 2023Source
- 1 Commencement Certificates / NA Order for plotted development125 24 CC.pdf · uploaded 13 Jan 2023Source
- 1 Declaration about Commencement CertificateDeclaration CC.pdf · uploaded 13 Jan 2023Source
- 1 Declaration in FORM B1 Declaration in FORM B.pdf · uploaded 13 Jan 2023Source
- 2 Declaration in FORM Bform b Landowners.pdf · uploaded 13 Jan 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect Certificate.pdf · uploaded 13 Jan 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)1 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf · uploaded 13 Jan 2023Source
- 1 CERSAI details1 CERSAI details.pdf · uploaded 13 Jan 2023Source
- 1 Disclosure of Interest in Other Real Estate Organizations1 Disclosure of Interest in Other Real Estate Organizations.pdf · uploaded 13 Jan 2023Source
- 1 Proforma of Agreement for sale1 Proforma of Agreement for sale.pdf · uploaded 13 Jan 2023Source
- 1 Proforma of Allotment letter1 Proforma of Allotment letter.pdf · uploaded 13 Jan 2023Source
- 1 Deviation Report with respect to Allotment letter1 Deviation Report with respect to Allotment letter.pdf · uploaded 13 Jan 2023Source
- 1 Deviation Report with respect to model copy of Agreement1 Deviation Report with respect to model copy of Agreement.pdf · uploaded 13 Jan 2023Source
- 1 Other – Legal1 Other – Legal.pdf · uploaded 13 Jan 2023Source
- 2 Other – Legal3 Other – Legal.pdf · uploaded 13 Jan 2023Source
- 3 Other – Legal4 Other – Legal.pdf · uploaded 13 Jan 2023Source
- 4 Other – Legal5 Other – Legal.pdf · uploaded 13 Jan 2023Source
- 3 a Details of encumbrances concerned to FinanceFinance Onwer.pdf · uploaded 16 Jan 2023Source
- 4 a Details of encumbrances concerned to FinanceFinance Promoter.pdf · uploaded 16 Jan 2023Source
- 3 b Details of encumbrances concerned to LegalFinance Onwer.pdf · uploaded 16 Jan 2023Source
- 4 b Details of encumbrances concerned to LegalFinance Promoter.pdf · uploaded 16 Jan 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA_compressed.pdf · uploaded 16 Jan 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameSeperate Acc.pdf · uploaded 16 Jan 2023Source
- 1 Copy of the legal title reportFinal Legal Title Report Plot 125.pdf · uploaded 19 Jan 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate Form 1.pdf · uploaded 19 Sep 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 CA Certificate Jupiter Royal June 2023.pdf · uploaded 19 Sep 2023Source
- 5 Other – LegalDA-1.pdf · uploaded 2 Oct 2023Source
- 6 Other – LegalDA-2 (1).pdf · uploaded 2 Oct 2023Source
- 7 Other – LegalDA-3 (1).pdf · uploaded 2 Oct 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate.pdf · uploaded 14 Oct 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate 22 23.pdf · uploaded 14 Oct 2023Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA form 3.pdf · uploaded 14 Oct 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 CA Certificate.pdf · uploaded 14 Oct 2023Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)RERA FOAM 1 ROYAL 125.pdf · uploaded 15 Oct 2023Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Jupiter Royal Form 3 RERA Q2 FY 2023-24 signed scan.pdf · uploaded 15 Oct 2023Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect 1.pdf · uploaded 16 Oct 2023Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect 2.pdf · uploaded 16 Oct 2023Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect 3.pdf · uploaded 16 Oct 2023Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engi april.pdf · uploaded 16 Oct 2023Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engg.pdf · uploaded 16 Oct 2023Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Jupiter Royal_compressed.pdf · uploaded 16 Oct 2023Source
- 2 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5.pdf · uploaded 16 Oct 2023Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 19 Oct 2023Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)125 24 Form 1 Q3.pdf · uploaded 31 Dec 2023Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Plot 125 Q3 (1).pdf · uploaded 19 Jan 2024Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Jupiter Royal Form 3 RERA Q3 FY 2023-24 signed scan.pdf · uploaded 20 Jan 2024Source
- 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)125 24 rera 1 13 april 2024.pdf · uploaded 20 Apr 2024Source
- 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)Jupiter Royal Form 2 125.pdf · uploaded 20 Apr 2024Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Jupiter Royal Form3_Q4_FY 2023-24.pdf · uploaded 20 Apr 2024Source
- 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)foam 1 3 july 2024 from architect jupiter royal.pdf · uploaded 21 Jul 2024Source
- 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)Royal July 24.pdf · uploaded 21 Jul 2024Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Jupiter Royal Form 3 Q1 FY 2024-25 SIGNED SCAN_compressed.pdf · uploaded 21 Jul 2024Source
- Form 5 (FY 2023-2024)Jupiter Royal Form 5.pdf · uploaded 20 Sep 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)ROYAL FOAM 1 125 10 SEPT 24.pdf · uploaded 19 Oct 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)F2Jupiter Royal oct24.pdf · uploaded 19 Oct 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)F3 J Royal.pdf · uploaded 22 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FOAM 1 125 24 DEC 2024.pdf · uploaded 20 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Royal Jan25.pdf · uploaded 20 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Jupiter royal form 3 Q3 fy 24-25.pdf · uploaded 23 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 royal.pdf · uploaded 19 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)F3 J Royal.pdf · uploaded 19 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Royal Apr25.pdf · uploaded 19 Apr 2025Source
- Withdrawal Update Form 1Jupiter Royal Form 1 Dec 25.pdf · uploaded 23 Jan 2026Source
- Withdrawal Update Form 2Jupiter Royal Form 2 Dec 25.pdf · uploaded 23 Jan 2026Source
- Withdrawal Update Form 3Jupiter royal q3 fy 25-26 form 3.pdf · uploaded 23 Jan 2026Source
- Withdrawal Update Form 1Jupiter Royal Form 1 Dec 25.pdf · uploaded 24 Jan 2026Source
- Withdrawal Update Form 2Jupiter Royal Form 2 Dec 25.pdf · uploaded 24 Jan 2026Source
- Withdrawal Update Form 3Jupiter royal q3 fy 25-26 form 3.pdf · uploaded 24 Jan 2026Source
- Withdrawal Update Form 1Jupiter Royal Form 1 Dec 25.pdf · uploaded 26 Apr 2026Source
- Withdrawal Update Form 2Form 2 Royal April2026.pdf · uploaded 26 Apr 2026Source
- Withdrawal Update Form 3Form 3 Royal March 2026.pdf · uploaded 26 Apr 2026Source
- Withdrawal Update Form 1ARCHITECTS CERTIFICATEjupiter royal q1-fy 26-27.pdf · uploaded 18 Jul 2026Source
- Withdrawal Update Form 2Engineer certificate jupiter royal q1 fy 26-27.pdf · uploaded 18 Jul 2026Source
- Withdrawal Update Form 3JUPITER ROYAL FORM 3 OG.pdf · uploaded 18 Jul 2026Source
Technical
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 125
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK, Shop24 units in all
- Address
- 125, Plot No 125 Sector 24 Pushpak Vahal, Pushpak VahalPIN 410206
- Village
- Ulawe, Panvel taluka
- Land area for this project
- 700 sq m (7,535 sq ft)
- Permissible built-up area
- 1,750 sq m (18,837 sq ft)
- Sanctioned built-up area
- 1,050 sq m (11,302 sq ft)
- Designated bank account
- 16
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
125
Boundaries
- North
- Plot No 126
- South
- Plot No 123 And 124
- East
- 11 Mtrs Wide Road
- West
- Plot No 146 And 147
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking24 units
12 of 24 units booked (50%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 29.87 sq m · 322 sq ft | 4 | 2 |
| 1BHK | 29.9 sq m · 322 sq ft | 4 | 3 |
| 1BHK | 29.96 sq m · 322 sq ft | 4 | 4 |
| 2BHK | 48.03 sq m · 517 sq ft | 8 | 3 |
| Shop | 21.76 sq m · 234 sq ft | 4 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals5
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Precision Architects | — |
| Chartered accountant | Bhavesh Bhanushali And Associates | — |
| Chartered accountant | Vaishnavi R Morajkar | — |
| Engineer | Ashok K Patel | — |
| Other | Law Affairs | — |
Source: MahaRERA project page. Contact details are not shown.