Neral, Raigarh
Deedo IDDL-RAI-NERAL9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects88
Registrations90some projects hold several
Completion still due3159 past their date
Median extension12 months51% of registrations extended
Regulatory cases1on 1 project
9 in 10 registrations run late here
90 MahaRERA registrations in Neral
7 not yet due24 extended, not yet due59 past even the latest date
Extended registrations moved their completion date by a median of 12 months.
Projects in Neral
88 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Abhishek Florida- DaffodilsSeema Promoters And Builders Private Limited | Completed | — | 97% |
| Abhishek Florida- LotusSeema Promoters And Builders Private Limited | Completed | — | 95% |
| Abhishek Florida- MarigoldSeema Promoters And Builders Private Limited | Completed | — | 100% |
| Abhishek Florida- OrchidSeema Promoters And Builders Private Limited | Completed | — | 100% |
| Green PalmsGreen Leaf Realty | Completed, extended 1 yr 6 mo | — | 9% |
| Pooja NagarShree Laxmi Narayan Developers | 4 yrs 11 mo late | — | 32% |
| Dwarika ValleyDwarika Real Infra LLP | Completed, extended 3 yrs | — | 75% |
| NisargIndiapride Infraspaces | Completed, extended 1 yr 6 mo | — | — |
| Niravana EnclaveJagdish Lakhmichand Mohinani | Completed | — | 36% |
| Raj BaugNehaldhara Realtors | Completed | — | 87% |
| Sai Krupa Valley- Phase 1Sai Krupa Developers | Completed | — | 68% |
| Tulsi Centre PointNavkar developers, Navkar Developers | Completed | — | 37% |
| Rucha SolitaireChintamani Projects | Completed | — | 100% |
Nearby: other villages in Karjat
Most active promoters
- Seema Promoters And Builders Private Limited6 projects
- Shibam Associates4 projects
- Dreamz Realty3 projects
- Brs Builders & Developers2 projects
- Nehaldhara Realtors2 projects
- Pankaj Prakash Sawant2 projects
- Prashant Prakash Sawant2 projects
- 5p Developers1 project
- Aaradhya Developers1 project
- Aaradhya Enterprises1 project
Neral, in questions
How many projects in Neral run late?
9 in 10 MahaRERA registrations (83 of 90): their completion date was extended or has passed, data through 5 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Neral by Deedo. Medians on fewer than 3 deeds are not shown.
Data through5 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology