RERA projects in Tathwade

163 projects under 189 MahaRERA registrations, registered 2017–2026. 13% have a completion date extended beyond the one promised.

163RERA projects
189Registrationssome projects hold several
107Completion still due82 past their completion date
12 monthsMedian extension beyond promised date13% of registrations extended
1Regulatory caseson 1 project
32Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
201715
20189
201921
202015
202114
202225
202334
202417
202522
202617

Projects in Tathwade

163 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Sky HomesMahalaxmi EnterpriseP5210003084920 Sep 202131 May 2028—Not yet due0
Ashoka Commercial HubAshoka DevelopersP5210003043125 Aug 202131 Mar 202431 Mar 2025Extended 12 mo0
One Shriaunsh Phase IIShriaunsh Erectors Pvt. Ltd.P5210003047325 Aug 202130 Jun 2022—Promised date passed0
41cosmoKrisala Enterprises LLPP521000298448 Jul 202131 Dec 20249 Jun 2025Extended 6 mo0
Mrudang ResidencyJaydeep Shankar KhavaleP5210002970826 Jun 202125 May 2023—Promised date passed0
Happinest Tathawade Phase-1Mahindra Lifespace Developers limitedP5210002804927 Jan 202131 Jan 2027—Not yet due0
41 EliteM/S Krisala EnterprisesP5210002795921 Jan 202130 Jun 2024—Promised date passed0
iOS TathawadeLinux GroupP5210002795221 Jan 202110 Jul 202430 Dec 2024Extended 5 mo0
41 EliteM/S Krisala Enterprises, M/S. Krisala EnterprisesP52100027929, P5210002795816 Jan 202130 Jun 2024—Promised date passed0
The CentrumMansion CreatorsP5210002766225 Dec 202030 Jun 2023—Promised date passed0
41 Elite Phase 3 Building CM/S Krisala EnterprisesP5210002749614 Dec 202030 Jun 202330 Jun 2025Extended 24 mo0
Millennium PacificMillennium DevelopersP5210002720424 Nov 202031 Mar 2024—Promised date passed0
Sai AasraAbhijit Prakash BoraseP521000268933 Nov 202020 Apr 2023—Promised date passed0
Kohinoor Sapphire IIRising AssociatesP5210002668521 Oct 202030 Sep 2024—Promised date passed0
Vision Starwest Phase - 2Vision Creative DevelopersP5210002662510 Oct 202030 Dec 2023—Promised date passed0
Metro Life Optima ResidencesRama Synergy SpacesP521000262552 Sep 202031 Dec 202431 Dec 2024Promised date passed0
Darekar HeightsMangaldeep Radiant DevelopersP5210002619529 Aug 202030 Jun 202429 Jun 2025Extended 12 mo1
Vision Ace MHADAVision AceP5210002613521 Aug 202030 Oct 202230 Oct 2023Extended 12 mo0
Vision Ace Commercial Phase IVision AceP5210002612620 Aug 202028 Sep 2026—Promised date passed0
41 EarthKrisala BuildconP5210002470828 Feb 20201 Feb 2024—Promised date passed0
Vision Starwest Phase - 1Vision Creative InfraP521000243465 Feb 202031 Jul 2023—Promised date passed0
Azure Aster G and HParanjape Schemes (Construction) LtdP5210002418624 Jan 202028 Feb 2026—Promised date passed0
Akshara ResidencyHaribhau Vaijnath KendreP5210002354718 Dec 201930 Jun 2023—Promised date passed0
MarigoldCaratlane Landmarks LLPP5210002339512 Dec 201930 Mar 2025—Promised date passed0
Vardhaman MoonstoneVardhaman AssociatesP521000231845 Dec 20191 Mar 2025—Promised date passed0
The SpectrumFuturistic HomesP521000229345 Nov 201930 Dec 2023—Promised date passed0
Ace Almighty Delta TowerM/S. Ace AlmightyP521000225747 Oct 201930 Dec 2023—Promised date passed0
Vision Ace Phase IIVision AceP521000225451 Oct 201930 Oct 2024—Promised date passed0
Kohinoor SapphireRising AssociatesP5210002237816 Sep 201930 Dec 2024—Promised date passed0
Metro Life Bizz BayRama Synergy SpacesP521000221564 Sep 201931 Jul 202326 Jul 2024Extended 12 mo0
Sentosa SereneShanti ConstructionsP5210002176223 Jul 201930 Jun 2023—Promised date passed0
Austin Park NXTDivya AssociatesP5210002113010 Jun 201930 Dec 2022—Promised date passed0
Ace Almighty Gamma TowerM/S. Ace AlmightyP5210002051418 Apr 201930 Dec 2023—Promised date passed0
Prathamesh ExcellenciaPrathamesh Developers & BuildersP5210002004219 Mar 201930 Mar 20231 Dec 2023Extended 9 mo0
One ShriaunshShriaunsh Erectors Pvt. Ltd.P5210001990113 Mar 201930 Dec 202030 Dec 2021Extended 12 mo0
Blue mountGreenaxis AssociatesP5210001970922 Feb 201931 Mar 202031 Oct 2022Extended 31 mo0
Rohan AnantaRohan Builders & Developers Private LimitedP52100019664, P52100019678, P5210001999720 Feb 201931 Dec 2026—Not yet due0
Sai MiracleSai Datta DevelopersP5210001968720 Feb 201931 Dec 201930 Mar 2021Extended 15 mo0
Ace Almighty CommercialM/S. Ace AlmightyP521000194886 Feb 201930 Jun 2022—Promised date passed0
Vision IndratejVision BuildconP5210001939929 Jan 201930 Jun 2022—Promised date passed0
Pragati VrundavanPrithvi DevelopersP521000191184 Jan 201931 Mar 202010 Oct 2022Extended 31 mo0
Nova ResidencyAmit Jugalkishor RathiP52100018498, P5210002678712 Nov 201830 Jun 2023—Promised date passed0
Golden CrestAdityasinh Dayanand PatilP5210001838629 Oct 20189 Mar 2021—Promised date passed0
Vision Ace Phase 1Vision AceP5210001774811 Sep 201830 Oct 2023—Promised date passed0
Palladio Phase 2Vilas Javdekar Eco Developers Pvt. Ltd.P5210001730631 Jul 201830 Dec 2022—Promised date passed0
AtlantePyramid Infraventure LLPP521000166635 Jun 201830 Dec 202530 Dec 2027Extended 24 mo0
Narmada Blue SapphireTanaji Ramchandra KatkeP521000166615 Jun 201830 Dec 202331 Jul 2025Extended 19 mo0
Avalon AvenueAvalon AssociatesP5210001658023 May 201830 Mar 2022—Promised date passed0
Vision One Phase TwoSs GroupP5210001575522 Mar 201828 May 202131 Dec 2026Extended 67 mo0
Ganga Aurum Park CEcostar Goel Properties LLPP5210001426817 Nov 201730 Dec 2026—Not yet due0
33 MilestoneLabh Promoters And DevelopersP52100013679, P5210001374923 Oct 201731 Mar 2019—Promised date passed0
ShantivanTrimurti Group Promoters & BuildersP5210001298911 Sep 201730 Sep 2026—Promised date passed0
Austin Park D BuildingDivya Shravani DevelopersP5210000929122 Aug 20176 Dec 2020—Promised date passed0
Skyscraper Phase 1Vishal PropertiesP5210000860519 Aug 201715 Jul 2023—Promised date passed0
Austin Park A BuildingYashada Shravni GroupP5210000750017 Aug 201730 Dec 2020—Promised date passed0
Star Woods Phase IVaishnavi Space CreatorP5210000715317 Aug 20171 Mar 2018—Promised date passed0
Dharti GreenDharti DevelopersP5210000645714 Aug 201731 Mar 20191 Jan 2027Extended 94 mo0
The Nook Phase 1Pyramid DevelopersP521000040157 Aug 201731 Oct 201831 Oct 2019Extended 12 mo0
ElementaAkshar Land Developers Private LimitedP521000029034 Aug 201731 Dec 2018—Promised date passed0
Ganga AmberShri Siddhivinayak DevelopersP52100002620, P521000260552 Aug 201730 Jun 202730 Apr 2023Not yet due0
Dnv Elvira ADnv RealtyP5210000124027 Jul 201731 Mar 2019—Promised date passed0
Sundaram residencyJadhav EnterprisesP5210000090725 Jul 201731 Dec 201931 Dec 2019Promised date passed0
AzureParanjape Schemes (Construction) LtdP52100000241, P5210001621810 Jul 20171 Jun 2022—Promised date passed0

Other localities in Mulshi

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Vision Ace4 projects
  2. Linux Group3 projects
  3. Mahindra Lifespace Developers limited3 projects
  4. Mansion Creators3 projects
  5. Millennium Developers3 projects
  6. M/S. Ace Almighty3 projects
  7. M/S Krisala Enterprises3 projects
  8. Rama Synergy Spaces3 projects
  9. Rising Associates3 projects
  10. Abhijit Prakash Borase2 projects
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology