RERA projects in Tathwade
163 projects under 189 MahaRERA registrations, registered 2017–2026. 13% have a completion date extended beyond the one promised.
163RERA projects
189Registrationssome projects hold several
107Completion still due82 past their completion date
12 monthsMedian extension beyond promised date13% of registrations extended
1Regulatory caseson 1 project
32Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 15 |
| 2018 | 9 |
| 2019 | 21 |
| 2020 | 15 |
| 2021 | 14 |
| 2022 | 25 |
| 2023 | 34 |
| 2024 | 17 |
| 2025 | 22 |
| 2026 | 17 |
Projects in Tathwade
163 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Sky HomesMahalaxmi Enterprise | P52100030849 | 20 Sep 2021 | 31 May 2028 | — | Not yet due | 0 |
| Ashoka Commercial HubAshoka Developers | P52100030431 | 25 Aug 2021 | 31 Mar 2024 | 31 Mar 2025 | Extended 12 mo | 0 |
| One Shriaunsh Phase IIShriaunsh Erectors Pvt. Ltd. | P52100030473 | 25 Aug 2021 | 30 Jun 2022 | — | Promised date passed | 0 |
| 41cosmoKrisala Enterprises LLP | P52100029844 | 8 Jul 2021 | 31 Dec 2024 | 9 Jun 2025 | Extended 6 mo | 0 |
| Mrudang ResidencyJaydeep Shankar Khavale | P52100029708 | 26 Jun 2021 | 25 May 2023 | — | Promised date passed | 0 |
| Happinest Tathawade Phase-1Mahindra Lifespace Developers limited | P52100028049 | 27 Jan 2021 | 31 Jan 2027 | — | Not yet due | 0 |
| 41 EliteM/S Krisala Enterprises | P52100027959 | 21 Jan 2021 | 30 Jun 2024 | — | Promised date passed | 0 |
| iOS TathawadeLinux Group | P52100027952 | 21 Jan 2021 | 10 Jul 2024 | 30 Dec 2024 | Extended 5 mo | 0 |
| 41 EliteM/S Krisala Enterprises, M/S. Krisala Enterprises | P52100027929, P52100027958 | 16 Jan 2021 | 30 Jun 2024 | — | Promised date passed | 0 |
| The CentrumMansion Creators | P52100027662 | 25 Dec 2020 | 30 Jun 2023 | — | Promised date passed | 0 |
| 41 Elite Phase 3 Building CM/S Krisala Enterprises | P52100027496 | 14 Dec 2020 | 30 Jun 2023 | 30 Jun 2025 | Extended 24 mo | 0 |
| Millennium PacificMillennium Developers | P52100027204 | 24 Nov 2020 | 31 Mar 2024 | — | Promised date passed | 0 |
| Sai AasraAbhijit Prakash Borase | P52100026893 | 3 Nov 2020 | 20 Apr 2023 | — | Promised date passed | 0 |
| Kohinoor Sapphire IIRising Associates | P52100026685 | 21 Oct 2020 | 30 Sep 2024 | — | Promised date passed | 0 |
| Vision Starwest Phase - 2Vision Creative Developers | P52100026625 | 10 Oct 2020 | 30 Dec 2023 | — | Promised date passed | 0 |
| Metro Life Optima ResidencesRama Synergy Spaces | P52100026255 | 2 Sep 2020 | 31 Dec 2024 | 31 Dec 2024 | Promised date passed | 0 |
| Darekar HeightsMangaldeep Radiant Developers | P52100026195 | 29 Aug 2020 | 30 Jun 2024 | 29 Jun 2025 | Extended 12 mo | 1 |
| Vision Ace MHADAVision Ace | P52100026135 | 21 Aug 2020 | 30 Oct 2022 | 30 Oct 2023 | Extended 12 mo | 0 |
| Vision Ace Commercial Phase IVision Ace | P52100026126 | 20 Aug 2020 | 28 Sep 2026 | — | Promised date passed | 0 |
| 41 EarthKrisala Buildcon | P52100024708 | 28 Feb 2020 | 1 Feb 2024 | — | Promised date passed | 0 |
| Vision Starwest Phase - 1Vision Creative Infra | P52100024346 | 5 Feb 2020 | 31 Jul 2023 | — | Promised date passed | 0 |
| Azure Aster G and HParanjape Schemes (Construction) Ltd | P52100024186 | 24 Jan 2020 | 28 Feb 2026 | — | Promised date passed | 0 |
| Akshara ResidencyHaribhau Vaijnath Kendre | P52100023547 | 18 Dec 2019 | 30 Jun 2023 | — | Promised date passed | 0 |
| MarigoldCaratlane Landmarks LLP | P52100023395 | 12 Dec 2019 | 30 Mar 2025 | — | Promised date passed | 0 |
| Vardhaman MoonstoneVardhaman Associates | P52100023184 | 5 Dec 2019 | 1 Mar 2025 | — | Promised date passed | 0 |
| The SpectrumFuturistic Homes | P52100022934 | 5 Nov 2019 | 30 Dec 2023 | — | Promised date passed | 0 |
| Ace Almighty Delta TowerM/S. Ace Almighty | P52100022574 | 7 Oct 2019 | 30 Dec 2023 | — | Promised date passed | 0 |
| Vision Ace Phase IIVision Ace | P52100022545 | 1 Oct 2019 | 30 Oct 2024 | — | Promised date passed | 0 |
| Kohinoor SapphireRising Associates | P52100022378 | 16 Sep 2019 | 30 Dec 2024 | — | Promised date passed | 0 |
| Metro Life Bizz BayRama Synergy Spaces | P52100022156 | 4 Sep 2019 | 31 Jul 2023 | 26 Jul 2024 | Extended 12 mo | 0 |
| Sentosa SereneShanti Constructions | P52100021762 | 23 Jul 2019 | 30 Jun 2023 | — | Promised date passed | 0 |
| Austin Park NXTDivya Associates | P52100021130 | 10 Jun 2019 | 30 Dec 2022 | — | Promised date passed | 0 |
| Ace Almighty Gamma TowerM/S. Ace Almighty | P52100020514 | 18 Apr 2019 | 30 Dec 2023 | — | Promised date passed | 0 |
| Prathamesh ExcellenciaPrathamesh Developers & Builders | P52100020042 | 19 Mar 2019 | 30 Mar 2023 | 1 Dec 2023 | Extended 9 mo | 0 |
| One ShriaunshShriaunsh Erectors Pvt. Ltd. | P52100019901 | 13 Mar 2019 | 30 Dec 2020 | 30 Dec 2021 | Extended 12 mo | 0 |
| Blue mountGreenaxis Associates | P52100019709 | 22 Feb 2019 | 31 Mar 2020 | 31 Oct 2022 | Extended 31 mo | 0 |
| Rohan AnantaRohan Builders & Developers Private Limited | P52100019664, P52100019678, P52100019997 | 20 Feb 2019 | 31 Dec 2026 | — | Not yet due | 0 |
| Sai MiracleSai Datta Developers | P52100019687 | 20 Feb 2019 | 31 Dec 2019 | 30 Mar 2021 | Extended 15 mo | 0 |
| Ace Almighty CommercialM/S. Ace Almighty | P52100019488 | 6 Feb 2019 | 30 Jun 2022 | — | Promised date passed | 0 |
| Vision IndratejVision Buildcon | P52100019399 | 29 Jan 2019 | 30 Jun 2022 | — | Promised date passed | 0 |
| Pragati VrundavanPrithvi Developers | P52100019118 | 4 Jan 2019 | 31 Mar 2020 | 10 Oct 2022 | Extended 31 mo | 0 |
| Nova ResidencyAmit Jugalkishor Rathi | P52100018498, P52100026787 | 12 Nov 2018 | 30 Jun 2023 | — | Promised date passed | 0 |
| Golden CrestAdityasinh Dayanand Patil | P52100018386 | 29 Oct 2018 | 9 Mar 2021 | — | Promised date passed | 0 |
| Vision Ace Phase 1Vision Ace | P52100017748 | 11 Sep 2018 | 30 Oct 2023 | — | Promised date passed | 0 |
| Palladio Phase 2Vilas Javdekar Eco Developers Pvt. Ltd. | P52100017306 | 31 Jul 2018 | 30 Dec 2022 | — | Promised date passed | 0 |
| AtlantePyramid Infraventure LLP | P52100016663 | 5 Jun 2018 | 30 Dec 2025 | 30 Dec 2027 | Extended 24 mo | 0 |
| Narmada Blue SapphireTanaji Ramchandra Katke | P52100016661 | 5 Jun 2018 | 30 Dec 2023 | 31 Jul 2025 | Extended 19 mo | 0 |
| Avalon AvenueAvalon Associates | P52100016580 | 23 May 2018 | 30 Mar 2022 | — | Promised date passed | 0 |
| Vision One Phase TwoSs Group | P52100015755 | 22 Mar 2018 | 28 May 2021 | 31 Dec 2026 | Extended 67 mo | 0 |
| Ganga Aurum Park CEcostar Goel Properties LLP | P52100014268 | 17 Nov 2017 | 30 Dec 2026 | — | Not yet due | 0 |
| 33 MilestoneLabh Promoters And Developers | P52100013679, P52100013749 | 23 Oct 2017 | 31 Mar 2019 | — | Promised date passed | 0 |
| ShantivanTrimurti Group Promoters & Builders | P52100012989 | 11 Sep 2017 | 30 Sep 2026 | — | Promised date passed | 0 |
| Austin Park D BuildingDivya Shravani Developers | P52100009291 | 22 Aug 2017 | 6 Dec 2020 | — | Promised date passed | 0 |
| Skyscraper Phase 1Vishal Properties | P52100008605 | 19 Aug 2017 | 15 Jul 2023 | — | Promised date passed | 0 |
| Austin Park A BuildingYashada Shravni Group | P52100007500 | 17 Aug 2017 | 30 Dec 2020 | — | Promised date passed | 0 |
| Star Woods Phase IVaishnavi Space Creator | P52100007153 | 17 Aug 2017 | 1 Mar 2018 | — | Promised date passed | 0 |
| Dharti GreenDharti Developers | P52100006457 | 14 Aug 2017 | 31 Mar 2019 | 1 Jan 2027 | Extended 94 mo | 0 |
| The Nook Phase 1Pyramid Developers | P52100004015 | 7 Aug 2017 | 31 Oct 2018 | 31 Oct 2019 | Extended 12 mo | 0 |
| ElementaAkshar Land Developers Private Limited | P52100002903 | 4 Aug 2017 | 31 Dec 2018 | — | Promised date passed | 0 |
| Ganga AmberShri Siddhivinayak Developers | P52100002620, P52100026055 | 2 Aug 2017 | 30 Jun 2027 | 30 Apr 2023 | Not yet due | 0 |
| Dnv Elvira ADnv Realty | P52100001240 | 27 Jul 2017 | 31 Mar 2019 | — | Promised date passed | 0 |
| Sundaram residencyJadhav Enterprises | P52100000907 | 25 Jul 2017 | 31 Dec 2019 | 31 Dec 2019 | Promised date passed | 0 |
| AzureParanjape Schemes (Construction) Ltd | P52100000241, P52100016218 | 10 Jul 2017 | 1 Jun 2022 | — | Promised date passed | 0 |
Other localities in Mulshi
- Wakad296 projects
- Punawale183 projects
- Bavadhan Bk83 projects
- Hinjavadi (Ct)82 projects
- Sus80 projects
- Bhugaon77 projects
- Mahalunge68 projects
- Man67 projects
- Thergaon56 projects
- Pirangut49 projects
- Kasar Amboli43 projects
- Dasave27 projects
Most active promoters
By projects registered here, as named on MahaRERA.
- Vision Ace4 projects
- Linux Group3 projects
- Mahindra Lifespace Developers limited3 projects
- Mansion Creators3 projects
- Millennium Developers3 projects
- M/S. Ace Almighty3 projects
- M/S Krisala Enterprises3 projects
- Rama Synergy Spaces3 projects
- Rising Associates3 projects
- Abhijit Prakash Borase2 projects
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology