Ganga Aurum Park C
Certificate SignedTathwade, Pune 411033 |Promoter: Ecostar Goel Properties LLP
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Buildings
- 1
- Unit types
- —103 units in all
- Address
- 60/3, Tathawade, TathawadePIN 411033
- Designated bank account
- 109
- Developed in phases
- No
Location
Coordinates as published by MahaRERA
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion pushed back 4 months
- Registered
- 17 Nov 2017
- Promised
- 30 Dec 2026
- Revised
- 30 Apr 2027
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100014268 | 17 Nov 2017 | 30 Dec 2026 | 30 Apr 2027 | Ecostar Goel Properties LLP | Project page |
1 building
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| C | 13 | 103 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
103 units registered
| Type | Carpet area | Units |
|---|---|---|
| — | — | 103 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Documents
1 document held by Deedo, 140 filings listed on MahaRERA's project page
Finance
Legal
Show all 141 documentsShow fewer documents
Migrated
- 1 Proforma of Allotment letterRERA AGR-GANGA AURUM PARK.pdf · uploaded 17 Oct 2017Source
- 1 Details of encumbrancesNO ENCUMBERANCE.pdf · uploaded 25 Oct 2017Source
- 1 Certificates of CA (Form 3)FORM 3 CA CERTIFICATE GANGA AURUM PARK-1.pdf · uploaded 25 Oct 2017Source
- 1 Commencement Certificates / NA Order for plotted developmentAurum Park CC BP-Tathawade-21-2016 Dt 29-11-16.pdf · uploaded 30 Oct 2017Source
- 1 Copy of Layout Approval (in case of layout)Ganga Aurum Park LAYOUT-min.pdf · uploaded 15 Nov 2017Source
- 1 Building Plan Approval (IOD)Ganga Aurum Park LAYOUT-min.pdf · uploaded 15 Nov 2017Source
- 1 OtherGanga Aurum Park.pdf · uploaded 13 Aug 2021Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)20210118_C Engineer Certificate_compressed.pdf · uploaded 22 Feb 2022Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)ganga aurum park- c bldg.pdf · uploaded 22 Feb 2022Source
- 2 Certificates of CA (Form 3)CA Certificate Ganga Aurum Park C Building_Signed - Dec 21_compressed.pdf · uploaded 22 Feb 2022Source
- 2 Details of encumbrancesEGPLLP Prachay Mortgage Deed Dt26-12-2020 Index II.pdf · uploaded 7 Mar 2022Source
- 1 PAN CardEcostar Goel Properties LLP.pdf · uploaded 23 Dec 2022Source
- 2 Copy of Layout Approval (in case of layout)ECO.pdf · uploaded 23 Dec 2022Source
- 2 Building Plan Approval (IOD)IOD Layout 2022.pdf · uploaded 23 Dec 2022Source
- 2 Commencement Certificates / NA Order for plotted developmentComplete CC (2)_compressed.pdf · uploaded 23 Dec 2022Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameECO.pdf · uploaded 23 Dec 2022Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect form 1.pdf · uploaded 6 Jan 2023Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineering certificate form 2.pdf · uploaded 6 Jan 2023Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineering certificate form 2.pdf · uploaded 6 Jan 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Quarterly- Quality Assurance form 2A (RERA).pdf · uploaded 6 Jan 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Quarterly- Quality Assurance form 2A (RERA).pdf · uploaded 6 Jan 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Quarterly- Quality Assurance form 2A (RERA).pdf · uploaded 6 Jan 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5.pdf · uploaded 9 Jan 2023Source
- 1 Declaration about Commencement CertificateFormat D.pdf · uploaded 15 Feb 2023Source
- 1 Disclosure of sold/ booked inventoryDisclosure of sold and unsold.pdf · uploaded 15 Feb 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 march.pdf · uploaded 17 Apr 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 29 Jun 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A.pdf · uploaded 25 Jul 2023Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 8 Aug 2023Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 8 Aug 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5.pdf · uploaded 8 Aug 2023Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 18 Aug 2023Source
- 3 Certificates of CA (Form 3)Form 3.pdf · uploaded 18 Aug 2023Source
- 4 Certificates of CA (Form 3)Form 3.pdf · uploaded 18 Aug 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5.pdf · uploaded 18 Aug 2023Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Ecostar goel properties form 1-compressed.pdf · uploaded 9 Nov 2023Source
- 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 c - bldg.pdf · uploaded 9 Nov 2023Source
- 5 Certificates of CA (Form 3)Ganga Aurum Park C Building Sept 23 Form 3 RERA CA Certificate_compressed.pdf · uploaded 9 Nov 2023Source
- 3 Details of encumbrancesEcostar Prachay Loan Mortgage Index II.pdf · uploaded 20 Nov 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsEcostar Annuj Sir.pdf · uploaded 7 Dec 2023Source
- 2 Disclosure of Interest in Other Real Estate OrganizationsEcostar Ankit Sir.pdf · uploaded 7 Dec 2023Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 26 Dec 2023Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 26 Dec 2023Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 26 Dec 2023Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 26 Dec 2023Source
- 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 26 Dec 2023Source
- 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 26 Dec 2023Source
- 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 17 Jan 2024Source
- 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 17 Jan 2024Source
- 2 Disclosure of sold/ booked inventoryForm D.pdf · uploaded 17 Jan 2024Source
- 3 Disclosure of sold/ booked inventoryForm D.pdf · uploaded 17 Jan 2024Source
- 6 Certificates of CA (Form 3)Form 3.pdf · uploaded 17 Jan 2024Source
- 3 Disclosure of Interest in Other Real Estate OrganizationsForm D.pdf · uploaded 17 Jan 2024Source
- 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 AURUM.pdf · uploaded 21 Apr 2024Source
- 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 AURUM.pdf · uploaded 21 Apr 2024Source
- 7 Certificates of CA (Form 3)6 Certificates of CA (Form 3).pdf · uploaded 21 Apr 2024Source
- 8 Certificates of CA (Form 3)7 form 3.pdf · uploaded 21 Apr 2024Source
- 9 Certificates of CA (Form 3)Form 3.pdf · uploaded 23 Apr 2024Source
- 13 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Aurum.pdf · uploaded 20 Jul 2024Source
- 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Aurum.pdf · uploaded 20 Jul 2024Source
- 4 Disclosure of sold/ booked inventoryForm D aurum.pdf · uploaded 20 Jul 2024Source
- 10 Certificates of CA (Form 3)Form 3 Aurum.pdf · uploaded 20 Jul 2024Source
- 1 Copy of Layout Approval (in case of layout)layout.pdf · uploaded 30 Oct 2024Source
- 2 Copy of Layout Approval (in case of layout)C building plan.pdf · uploaded 30 Oct 2024Source
- 3 Copy of Layout Approval (in case of layout)C building plan.pdf · uploaded 30 Oct 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Aurum park.pdf · uploaded 30 Oct 2024Source
- 2 Certificates of CA (Form 3)Form 3 Aurum.pdf · uploaded 30 Oct 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Aurum park.pdf · uploaded 30 Oct 2024Source
- 1 Other – FinanceSelf Declaration aurum park.pdf · uploaded 30 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 aurum park.pdf · uploaded 21 Jan 2025Source
- 1 Certificates of CA (Form 3)Form 3 aurum.pdf · uploaded 21 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Aurum park.pdf · uploaded 21 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Aurum park.pdf · uploaded 21 Apr 2025Source
- 1 Certificates of CA (Form 3)Form 3.pdf · uploaded 21 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Aurum Park.pdf · uploaded 21 Apr 2025Source
- 1 Disclosure of sold/ booked inventory4 Disclosure of sold_ booked inventory.pdf · uploaded 21 Apr 2025Source
- 2 Disclosure of sold/ booked inventory4 Disclosure of sold_ booked inventory.pdf · uploaded 21 Apr 2025Source
- 3 Disclosure of sold/ booked inventory4 Disclosure of sold_ booked inventory.pdf · uploaded 21 Apr 2025Source
- 4 Disclosure of sold/ booked inventory4 Disclosure of sold_ booked inventory.pdf · uploaded 21 Apr 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 30 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 30 Apr 2025Source
- 1 Disclosure of sold/ booked inventorySold Unsold.pdf · uploaded 30 Apr 2025Source
- 2 Disclosure of sold/ booked inventorySold inventory.pdf · uploaded 30 Apr 2025Source
- Withdrawal Update Form 1Form 1.pdf · uploaded 6 Oct 2026Source
- Withdrawal Update Form 1Form 1.pdf · uploaded 6 Oct 2026Source
- Withdrawal Update Form 1Form 1.pdf · uploaded 6 Oct 2026Source
- Withdrawal Update Form 1Form 1.pdf · uploaded 6 Oct 2026Source
- Withdrawal Update Form 1Form 1.pdf · uploaded 6 Oct 2026Source
- Withdrawal Update Form 1Form 1.pdf · uploaded 6 Oct 2026Source
- Withdrawal Update Form 1Form 1.pdf · uploaded 6 Oct 2026Source
- Withdrawal Update Form 1Form 1.pdf · uploaded 6 Oct 2026Source
- Withdrawal Update Form 1Form 1.pdf · uploaded 6 Oct 2026Source
- Withdrawal Update Form 1Form 1.pdf · uploaded 6 Oct 2026Source
- Withdrawal Update Form 1Form 1.pdf · uploaded 6 Oct 2026Source
- Withdrawal Update Form 2Form 2 Aurum.pdf · uploaded 6 Oct 2026Source
- Withdrawal Update Form 2Form 2 Aurum.pdf · uploaded 6 Oct 2026Source
- Withdrawal Update Form 2Form 2 Aurum.pdf · uploaded 6 Oct 2026Source
- Withdrawal Update Form 2Form 2.pdf · uploaded 6 Oct 2026Source
- Withdrawal Update Form 2Form 2.pdf · uploaded 6 Oct 2026Source
- Withdrawal Update Form 2Form 2.pdf · uploaded 6 Oct 2026Source
- Withdrawal Update Form 2Form 2.pdf · uploaded 6 Oct 2026Source
- Withdrawal Update Form 2Form 2.pdf · uploaded 6 Oct 2026Source
- Withdrawal Update Form 2Form 2.pdf · uploaded 6 Oct 2026Source
- Withdrawal Update Form 2Form 2.pdf · uploaded 6 Oct 2026Source
- Withdrawal Update Form 2Form 2.pdf · uploaded 6 Oct 2026Source
- Withdrawal Update Form 3Form 3.pdf · uploaded 6 Oct 2026Source
- Withdrawal Update Form 3Form 3.pdf · uploaded 6 Oct 2026Source
- Withdrawal Update Form 3Form 3.pdf · uploaded 6 Oct 2026Source
- Withdrawal Update Form 3Form 3.pdf · uploaded 6 Oct 2026Source
- Withdrawal Update Form 3Form 3.pdf · uploaded 6 Oct 2026Source
- Withdrawal Update Form 3Form 3.pdf · uploaded 6 Oct 2026Source
- Withdrawal Update Form 3Form 3.pdf · uploaded 6 Oct 2026Source
- Withdrawal Update Form 3Form 3.pdf · uploaded 6 Oct 2026Source
- Withdrawal Update Form 3Form 3.pdf · uploaded 6 Oct 2026Source
- Withdrawal Update Form 3Form 3.pdf · uploaded 6 Oct 2026Source
- Withdrawal Update Form 3Form 3.pdf · uploaded 6 Oct 2026Source
Technical
- DocumentGanga Aurum Park LAYOUT-min.pdf · uploaded 15 Nov 2017Source
- DocumentGanga Aurum Park LAYOUT-min.pdf · uploaded 15 Nov 2017Source
- DocumentECO.pdf · uploaded 23 Dec 2022Source
- DocumentIOD Layout 2022.pdf · uploaded 23 Dec 2022Source
- Documentlayout.pdf · uploaded 30 Oct 2024Source
- DocumentC building plan.pdf · uploaded 30 Oct 2024Source
- DocumentC building plan.pdf · uploaded 30 Oct 2024Source
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Tathwade, Mulshi taluka
Survey, CTS, gat or plot numbers
Boundaries
- North
- 60 Part
- South
- 59 Part
- East
- 60 Part
- West
- 60 Part
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | A and T Consultants Vikas Achlkar | — |
| Chartered accountant | DMKH & Co | — |
| Engineer | Shrikant Morajkar | — |
| Registered real estate agent | Amit Anil Kulkarni | — |
| Registered real estate agent | Bigfeet Realty Advisors LLP | — |
| Registered real estate agent | Gaurav Kumar Ramjinish Singh Singh | — |
| Registered real estate agent | Hectare Marketing LLP | — |
| Registered real estate agent | Imran Mohammed | — |
Show all 17 professionalsShow fewer professionals
| Role | Name | Registration no. |
|---|---|---|
| Registered real estate agent | Jones Lang Lasalle Property Consultants (India) Private Limited | — |
| Registered real estate agent | MDN Properties Private Limited | — |
| Registered real estate agent | Mehak Mehak | — |
| Registered real estate agent | Mitosh Subhash Navale | — |
| Registered real estate agent | Parvej Saipan Mulla | — |
| Registered real estate agent | Priyanka Nautiyal | — |
| Registered real estate agent | Propbuying Realtors Pvt Ltd | — |
| Registered real estate agent | Sahil Kathuria | — |
| Registered real estate agent | S Golakanath Patro Patro | — |
Source: MahaRERA project page. Contact details are not shown.
