Skip to content

Blue mount

Certificate Signed

Tathwade, Pune 411033 |Promoter: Greenaxis Associates

Residential / Group HousingRERAP52100019709
22 Feb 2019Registered with MahaRERA
31 Mar 2020Promised completion
31 Oct 2022Revised completionPushed back 2 years and 7 months
1Building
16Units registered10 booked (63%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
1BHK, 2BHK16 units in all
Address
95/1/6, Near Akshara School, Near Akshara SchoolPIN 411033
Designated bank account
20
Developed in phases
No

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 2 years and 7 months

The latest completion date on record passed 4 years ago.

Registered
22 Feb 2019
Promised
31 Mar 2020
Revised
31 Oct 2022

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210001970922 Feb 201931 Mar 202031 Oct 2022Greenaxis AssociatesProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Blue Mount316

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

10 of 16 units booked (63%), as the promoter reported to MahaRERA

1BHK · 8 units2BHK · 8 units
TypeCarpet areaUnitsBooked
1BHK40.88 sq m · 440 sq ft85
2BHK57.59 sq m · 620 sq ft85

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

2 documents held by Deedo, 34 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Legal

  • Declaration Form BFORM B-.pdf · uploaded 1 Oct 2018Source
  • Legal Title reportSKMBT_C22419021616350.pdf · uploaded 18 Feb 2019Source

Migrated

  • 1 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERTIFICATE.pdf · uploaded 23 Aug 2018Source
  • 1 Details of encumbrancesENCUBRANCES.pdf · uploaded 1 Oct 2018Source
  • 1 Declaration in FORM BFORM B-.pdf · uploaded 1 Oct 2018Source
  • 1 Proforma of Allotment letterALLOTMENT LETTER 1.pdf · uploaded 1 Oct 2018Source
Show all 36 documentsShow fewer documents

Migrated

  • 1 Copy of Layout Approval (in case of layout)LAYOUT.pdf · uploaded 8 Oct 2018Source
  • 2 Proforma of Allotment letterAGREEMENT DRAFT.pdf · uploaded 8 Oct 2018Source
  • 1 Certificates of CA (Form 3)CA CERTIFICATE.pdf · uploaded 19 Oct 2018Source
  • 1 Building Plan Approval (IOD)BUILDING IOD.pdf · uploaded 29 Oct 2018Source
  • 1 Copy of the legal title reportSKMBT_C22419021616350.pdf · uploaded 18 Feb 2019Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECTS CERTIFICATE.pdf · uploaded 18 Feb 2019Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)BLUE MOUNT.pdf · uploaded 18 Feb 2019Source
  • 1 Declaration about Commencement Certificateformat D (1).pdf · uploaded 6 Apr 2022Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2A- Blue Mount.pdf · uploaded 6 Apr 2022Source
  • 1 CERSAI detailsCERSAI_Search_Report_200234425341_For_Asset_Based_Search_06_04_2022_10_43_27_952.pdf · uploaded 6 Apr 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)greenaxis 3 from 5.pdf · uploaded 6 Apr 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)greenaxis form 5.pdf · uploaded 6 Apr 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)greenaxis2 form 5 .pdf · uploaded 6 Apr 2022Source
  • 2 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERTIFICATE_compressed (2).pdf · uploaded 8 Apr 2022Source
  • 1 Disclosure of sold/ booked inventoryBuildtng Wise.pdf · uploaded 8 Apr 2022Source
  • 2 Copy of Layout Approval (in case of layout)Layout_compressed.pdf · uploaded 10 Jan 2023Source
  • 2 Building Plan Approval (IOD)Floor Plan 1_compressed.pdf · uploaded 10 Jan 2023Source
  • 3 Building Plan Approval (IOD)Floor plan 2_compressed.pdf · uploaded 10 Jan 2023Source
  • 3 Commencement Certificates / NA Order for plotted developmentCommencement Certificate_compressed.pdf · uploaded 10 Jan 2023Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentPart Completion.pdf · uploaded 10 Jan 2023Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)Form 4.pdf · uploaded 10 Jan 2023Source

Technical

  • DocumentLAYOUT.pdf · uploaded 8 Oct 2018Source
  • DocumentBUILDING IOD.pdf · uploaded 29 Oct 2018Source
  • DocumentLayout_compressed.pdf · uploaded 10 Jan 2023Source
  • DocumentFloor Plan 1_compressed.pdf · uploaded 10 Jan 2023Source
  • DocumentFloor plan 2_compressed.pdf · uploaded 10 Jan 2023Source

Technical (Architect)

  • DocumentARCHITECTS CERTIFICATE.pdf · uploaded 18 Feb 2019Source

Technical (Engineer)

  • DocumentBLUE MOUNT.pdf · uploaded 18 Feb 2019Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Tathwade, Mulshi taluka

Survey, CTS, gat or plot numbers

95/1/6

Boundaries

North
By Property of Mr Chavan and Mr Sonvane
South
Property of Tulip Builders
East
By Survey No 95 2
West
By Road and Property of Survey No 96

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectMr Nandkishor Nikumbh—
Registered real estate agentMayur Suryakant Dhamdhere—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology