Blue mount
Certificate SignedTathwade, Pune 411033 |Promoter: Greenaxis Associates
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Buildings
- 1
- Unit types
- 1BHK, 2BHK16 units in all
- Address
- 95/1/6, Near Akshara School, Near Akshara SchoolPIN 411033
- Designated bank account
- 20
- Developed in phases
- No
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion pushed back 2 years and 7 months
The latest completion date on record passed 4 years ago.
- Registered
- 22 Feb 2019
- Promised
- 31 Mar 2020
- Revised
- 31 Oct 2022
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100019709 | 22 Feb 2019 | 31 Mar 2020 | 31 Oct 2022 | Greenaxis Associates | Project page |
1 building
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| Blue Mount | 3 | 16 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
10 of 16 units booked (63%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 40.88 sq m · 440 sq ft | 8 | 5 |
| 2BHK | 57.59 sq m · 620 sq ft | 8 | 5 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Documents
2 documents held by Deedo, 34 filings listed on MahaRERA's project page
Legal
Migrated
- 1 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERTIFICATE.pdf · uploaded 23 Aug 2018Source
- 1 Details of encumbrancesENCUBRANCES.pdf · uploaded 1 Oct 2018Source
- 1 Declaration in FORM BFORM B-.pdf · uploaded 1 Oct 2018Source
- 1 Proforma of Allotment letterALLOTMENT LETTER 1.pdf · uploaded 1 Oct 2018Source
Show all 36 documentsShow fewer documents
Migrated
- 1 Copy of Layout Approval (in case of layout)LAYOUT.pdf · uploaded 8 Oct 2018Source
- 2 Proforma of Allotment letterAGREEMENT DRAFT.pdf · uploaded 8 Oct 2018Source
- 1 Certificates of CA (Form 3)CA CERTIFICATE.pdf · uploaded 19 Oct 2018Source
- 1 Building Plan Approval (IOD)BUILDING IOD.pdf · uploaded 29 Oct 2018Source
- 1 Copy of the legal title reportSKMBT_C22419021616350.pdf · uploaded 18 Feb 2019Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECTS CERTIFICATE.pdf · uploaded 18 Feb 2019Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)BLUE MOUNT.pdf · uploaded 18 Feb 2019Source
- 1 Declaration about Commencement Certificateformat D (1).pdf · uploaded 6 Apr 2022Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2A- Blue Mount.pdf · uploaded 6 Apr 2022Source
- 1 CERSAI detailsCERSAI_Search_Report_200234425341_For_Asset_Based_Search_06_04_2022_10_43_27_952.pdf · uploaded 6 Apr 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)greenaxis 3 from 5.pdf · uploaded 6 Apr 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)greenaxis form 5.pdf · uploaded 6 Apr 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)greenaxis2 form 5 .pdf · uploaded 6 Apr 2022Source
- 2 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERTIFICATE_compressed (2).pdf · uploaded 8 Apr 2022Source
- 1 Disclosure of sold/ booked inventoryBuildtng Wise.pdf · uploaded 8 Apr 2022Source
- 2 Copy of Layout Approval (in case of layout)Layout_compressed.pdf · uploaded 10 Jan 2023Source
- 2 Building Plan Approval (IOD)Floor Plan 1_compressed.pdf · uploaded 10 Jan 2023Source
- 3 Building Plan Approval (IOD)Floor plan 2_compressed.pdf · uploaded 10 Jan 2023Source
- 3 Commencement Certificates / NA Order for plotted developmentCommencement Certificate_compressed.pdf · uploaded 10 Jan 2023Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentPart Completion.pdf · uploaded 10 Jan 2023Source
- 1 Architect’s Certificate on Completion of Project (Form 4)Form 4.pdf · uploaded 10 Jan 2023Source
Technical
Technical (Architect)
- DocumentARCHITECTS CERTIFICATE.pdf · uploaded 18 Feb 2019Source
Technical (Engineer)
- DocumentBLUE MOUNT.pdf · uploaded 18 Feb 2019Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Tathwade, Mulshi taluka
Survey, CTS, gat or plot numbers
Boundaries
- North
- By Property of Mr Chavan and Mr Sonvane
- South
- Property of Tulip Builders
- East
- By Survey No 95 2
- West
- By Road and Property of Survey No 96
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Mr Nandkishor Nikumbh | — |
| Registered real estate agent | Mayur Suryakant Dhamdhere | — |
Source: MahaRERA project page. Contact details are not shown.