Skip to content

Ravade, Pune

2 in 10 MahaRERA registrations here have pushed their completion date back.

RERA projects5
Registrations5
Completion still due32 past their date
Median extension4 months20% of registrations extended
Regulatory cases1on 1 project
Ravade market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Projects in Ravade

5 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Rivera Residence Phase 1M/s High Yield Fortune Pvt LtdP5210007962917 Mar 202531 Dec 202931 Dec 2029Not yet due1
Aryan BrentwoodPrahlad Harishchandra KhandelwalP5210005192813 Jul 20237 Jun 20277 Oct 2027Extended 4 mo0
Foresta Phase IIHigh Yield Fortune Pvt LtdP5210004693720 Sep 202231 Aug 202631 Aug 2026Promised date passed0
Foresta Phase IMachi Suites LLPP5210003115811 Oct 202126 Oct 202626 Oct 2026Not yet due0
AmansaraSvb RealtyP5210002250125 Sep 201930 Oct 202430 Oct 2024Promised date passed0

Most active promoters

  1. High Yield Fortune Pvt Ltd1 project
  2. Machi Suites LLP1 project
  3. M/s High Yield Fortune Pvt Ltd1 project
  4. Prahlad Harishchandra Khandelwal1 project
  5. Svb Realty1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology