Skip to content
Deedo home
Menu

RERA projects in Pimpri

2 projects under 2 MahaRERA registrations, registered 2017–2025. 50% have a completion date extended beyond the one promised.

2RERA projects
2Registrations
0Completion still due2 past their completion date
12 monthsMedian extension beyond promised date50% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20171
20180
20190
20200
20210
20220
20230
20240
20251

Projects in Pimpri

2 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Tulsidas City CenterRythm PropertiesP5210007876013 Jan 202531 Dec 2025—Promised date passed0
Eden SolitiareElement Infracon Pvt LtdP5210000548911 Aug 201731 Dec 201831 Dec 2019Extended 12 mo0

Other localities in Mulshi

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Element Infracon Pvt Ltd1 project
  2. Rythm Properties1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology