Nande, Pune
Deedo IDDL-PUN-NANDE3 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects5
Registrations6some projects hold several
Completion still due51 past their date
Median extension4 months17% of registrations extended
Regulatory cases0none on MahaRERA's lists
3 in 10 registrations run late here
6 MahaRERA registrations in Nande
4 not yet due1 extended, not yet due1 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Nande
5 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| ROHAN NITARA – Phase BUrban Life Ventures | Due Sep 2030 | — | — |
| Mahindra RivenzaMahindra Lifespace Developers limited | Due Dec 2031 | — | — |
| Grand RivieraM. R. Associates | Due Dec 2028 | — | — |
| PinakinAmruta Realties | Due Apr 2028, extended 4 mo | — | — |
| GrandezaPadale Construction Pvt. Ltd. | 2 yrs 1 mo late | — | 45% |
Nearby: other villages in Mulshi
Most active promoters
- Amruta Realties1 project
- Mahindra Lifespace Developers Limited1 project
- M. R. Associates1 project
- Padale Construction Pvt. Ltd1 project
- Urban Life Ventures1 project
Nande, in questions
How many projects in Nande run late?
3 in 10 MahaRERA registrations (2 of 6): their completion date was extended or has passed, data through 21 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nande by Deedo. Medians on fewer than 3 deeds are not shown.
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology