Deedo IDDL-PUN-MUGAVADE4 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects3
Registrations5some projects hold several
Completion still due50 past their date
Median extension4 months40% of registrations extended
Regulatory cases0none on MahaRERA's lists
4 in 10 registrations run late here
5 MahaRERA registrations in Mugavade
3 not yet due2 extended, not yet due
Extended registrations moved their completion date by a median of 4 months.
Projects in Mugavade
3 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Essentia Phase IMr. Jaydeep Anandrao Thakar and Mr. Dattatray Maruti More | Due Apr 2028 | — | — |
| Golden PalmsSuvarnbhumi Realtors | Due Apr 2030, extended 4 mo | — | — |
| GoodlandGoodland Realty Private Limited | Due Apr 2029, extended 4 mo | — | — |
Nearby: other villages in Mulshi
Most active promoters
- Goodland Realty Private Limited1 project
- Mr. Jaydeep Anandrao Thakar and Mr. Dattatray Maruti More1 project
- Suvarnbhumi Realtors1 project
Mugavade, in questions
How many projects in Mugavade run late?
4 in 10 MahaRERA registrations (2 of 5): their completion date was extended or has passed, data through 22 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Mugavade by Deedo. Medians on fewer than 3 deeds are not shown.
Data through22 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology