Skip to content

Marunji, Pune

Deedo IDDL-PUN-MARUNJI

10 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects31
Registrations34some projects hold several
Completion still due1519 past their date
Median extension4 months62% of registrations extended
Regulatory cases0none on MahaRERA's lists

10 in 10 registrations run late here

34 MahaRERA registrations in Marunji

15 extended, not yet due19 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Marunji

31 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Candy FloorsAnuradha Anil Saigal1 yr 11 mo late—80%
ElysiumAnand Yashwant Buchade5 yrs 11 mo late—96%
Life Republic Sector R1 - 1st AvenueKolte-Patil Developers LimitedDue Apr 2028, extended 4 mo——
Life Republic Sector R2 - 2nd AvenueKolte-Patil Integrated Townships LimitedCompleted, extended 1 yr 6 mo—85%
CitrineAchalare Welworth AssociatesCompleted—72%
Vision EternityVision DevelopersCompleted, extended 1 yr 6 mo—72%
Marunji market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Pride Purple Infrastructure10 projects
  2. Ashiana Housing Limited2 projects
  3. Achalare Welworth Associates1 project
  4. Anand Yashwant Buchade1 project
  5. Anuradha Anil Saigal1 project
  6. Apple Builders And Developers1 project
  7. Ashiana Housing Limited1 project
  8. Buchade Patil Developers1 project
  9. Darrvesh Associates1 project
  10. Garvedevelopers1 project

Marunji, in questions

How many projects in Marunji run late?

10 in 10 MahaRERA registrations (34 of 34): their completion date was extended or has passed, data through 31 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Marunji by Deedo. Medians on fewer than 3 deeds are not shown.

Data through31 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology