RERA projects in Malthan

1 project under 1 MahaRERA registration, registered 2019–2019. 100% have a completion date extended beyond the one promised.

1RERA projects
1Registrations
1Completion still due0 past their completion date
24 monthsMedian extension beyond promised date100% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20191

Projects in Malthan

1 project registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
EarthCountyVtp Projects LLPP521000229355 Nov 201930 Dec 202431 Dec 2026Extended 24 mo0

Other localities in Shirur

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Vtp Projects LLP1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology