Kothrud, Pune 411038 |Promoter: Majestique Duropolis Private Limited

29 Apr 2024Registered with MahaRERA
31 Dec 2029Promised completion
30 Apr 2030Revised completionPushed back 4 months
7Buildings
774Units registered40 booked (5%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Buildings
7
Unit types
F and b, Office space, Rehab office space, Rehab shop, Shop, 1BHK, 2BHK, 3BHK, REHAB 1 BHK, REHAB 2BHK, REHAB 3 BHK, REHAB 3BHK, REHAB 1BHK774 units in all
Address
CTS No. 947 S.NO. 148, HISSA NO. 1+2+3, PAUD ROAD, KOTHRUDPIN 411038
Designated bank account
85
Developed in phases
Yes

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.50772, 73.80782
New Friends is at latitude 18.50772, longitude 73.80782.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
29 Apr 2024
Promised
31 Dec 2029
Revised
30 Apr 2030

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210005593529 Apr 202431 Dec 202930 Apr 2030Majestique Duropolis Private LimitedProject page

7 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Commercial Wing474
Tower 6836
Tower T127151
Tower T227116
Tower T327123
Tower T427123
Tower T527151

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

40 of 774 units booked (5%), as the promoter reported to MahaRERA

F and b · 19 unitsOffice space · 104 unitsRehab office space · 18 unitsRehab shop · 56 unitsShop · 40 units1BHK · 6 units2BHK · 174 units3BHK · 130 unitsREHAB 1 BHK · 2 unitsREHAB 2BHK · 122 unitsREHAB 3 BHK · 18 unitsREHAB 3BHK · 84 unitsREHAB 1BHK · 1 unit
BuildingTypeCarpet areaUnitsBooked
Commercial WingF and b108.69 sq m · 1,170 sq ft10
Commercial WingF and b144.94 sq m · 1,560 sq ft20
Commercial WingF and b147.88 sq m · 1,592 sq ft20
Commercial WingF and b190.95 sq m · 2,055 sq ft10
Commercial WingOffice space55.42 sq m · 597 sq ft20
Commercial WingOffice space77.18 sq m · 831 sq ft32
Commercial WingOffice space93.52 sq m · 1,007 sq ft30
Commercial WingOffice space108.69 sq m · 1,170 sq ft20
Show all 225 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
Commercial WingOffice space111.57 sq m · 1,201 sq ft30
Commercial WingOffice space144.94 sq m · 1,560 sq ft40
Commercial WingOffice space147.88 sq m · 1,592 sq ft40
Commercial WingOffice space175.39 sq m · 1,888 sq ft30
Commercial WingOffice space190.95 sq m · 2,055 sq ft20
Commercial WingRehab office space55.42 sq m · 597 sq ft10
Commercial WingRehab shop22.96 sq m · 247 sq ft10
Commercial WingRehab shop27.38 sq m · 295 sq ft10
Commercial WingRehab shop29.69 sq m · 320 sq ft10
Commercial WingRehab shop35.15 sq m · 378 sq ft10
Commercial WingRehab shop37.21 sq m · 401 sq ft10
Commercial WingRehab shop39.7 sq m · 427 sq ft10
Commercial WingRehab shop40.72 sq m · 438 sq ft20
Commercial WingRehab shop43.39 sq m · 467 sq ft10
Commercial WingRehab shop46.04 sq m · 496 sq ft10
Commercial WingRehab shop50.05 sq m · 539 sq ft10
Commercial WingRehab shop54.49 sq m · 587 sq ft10
Commercial WingRehab shop55.8 sq m · 601 sq ft10
Commercial WingRehab shop55.99 sq m · 603 sq ft20
Commercial WingRehab shop56.15 sq m · 604 sq ft10
Commercial WingRehab shop57.12 sq m · 615 sq ft10
Commercial WingRehab shop57.65 sq m · 621 sq ft10
Commercial WingRehab shop57.83 sq m · 622 sq ft10
Commercial WingRehab shop57.87 sq m · 623 sq ft10
Commercial WingRehab shop58.69 sq m · 632 sq ft10
Commercial WingRehab shop59.82 sq m · 644 sq ft10
Commercial WingRehab shop60.79 sq m · 654 sq ft10
Commercial WingRehab shop61.97 sq m · 667 sq ft10
Commercial WingRehab shop66.25 sq m · 713 sq ft10
Commercial WingRehab shop76.09 sq m · 819 sq ft10
Commercial WingRehab shop81.6 sq m · 878 sq ft10
Commercial WingRehab shop85.72 sq m · 923 sq ft10
Commercial WingRehab shop93.17 sq m · 1,003 sq ft10
Commercial WingShop16.11 sq m · 173 sq ft10
Commercial WingShop18.99 sq m · 204 sq ft10
Commercial WingShop48.62 sq m · 523 sq ft10
Commercial WingShop61.98 sq m · 667 sq ft10
Commercial WingShop62.64 sq m · 674 sq ft10
Commercial WingShop62.95 sq m · 678 sq ft10
Commercial WingShop64.35 sq m · 693 sq ft10
Commercial WingShop66.86 sq m · 720 sq ft10
Commercial WingShop67.4 sq m · 725 sq ft10
Commercial WingShop68.43 sq m · 737 sq ft10
Commercial WingShop68.51 sq m · 737 sq ft10
Commercial WingShop85.02 sq m · 915 sq ft10
Tower 6Office space32.03 sq m · 345 sq ft50
Tower 6Office space36.25 sq m · 390 sq ft50
Tower 6Office space37.44 sq m · 403 sq ft50
Tower 6Office space38.61 sq m · 416 sq ft50
Tower 6Rehab shop13.91 sq m · 150 sq ft10
Tower 6Rehab shop17.03 sq m · 183 sq ft10
Tower 6Rehab shop21.82 sq m · 235 sq ft10
Tower 6Rehab shop25.34 sq m · 273 sq ft10
Tower 6Rehab shop26.55 sq m · 286 sq ft10
Tower 6Rehab shop27.3 sq m · 294 sq ft10
Tower 6Rehab shop28.26 sq m · 304 sq ft10
Tower 6Rehab shop29.97 sq m · 323 sq ft10
Tower 6Rehab shop38.25 sq m · 412 sq ft10
Tower 6Rehab shop40.69 sq m · 438 sq ft10
Tower 6Shop15.27 sq m · 164 sq ft10
Tower 6Shop16 sq m · 172 sq ft10
Tower 6Shop16.45 sq m · 177 sq ft10
Tower 6Shop18.06 sq m · 194 sq ft10
Tower 6Shop23.05 sq m · 248 sq ft10
Tower 6Shop24.52 sq m · 264 sq ft10
Tower T11BHK50.18 sq m · 540 sq ft20
Tower T11BHK56.62 sq m · 609 sq ft10
Tower T12BHK59.96 sq m · 645 sq ft310
Tower T12BHK59.99 sq m · 646 sq ft190
Tower T13BHK85.85 sq m · 924 sq ft40
Tower T13BHK101.25 sq m · 1,090 sq ft10
Tower T13BHK107.01 sq m · 1,152 sq ft30
Tower T1Office space26.17 sq m · 282 sq ft20
Tower T1Office space27.23 sq m · 293 sq ft22
Tower T1Office space27.69 sq m · 298 sq ft22
Tower T1Office space28.36 sq m · 305 sq ft20
Tower T1Office space30.94 sq m · 333 sq ft10
Tower T1Office space102.91 sq m · 1,108 sq ft20
Tower T1Office space190.18 sq m · 2,047 sq ft20
Tower T1REHAB 1 BHK50.18 sq m · 540 sq ft20
Tower T1REHAB 2BHK59.96 sq m · 645 sq ft150
Tower T1REHAB 2BHK59.99 sq m · 646 sq ft30
Tower T1REHAB 3 BHK85.85 sq m · 924 sq ft180
Tower T1REHAB 3BHK101.25 sq m · 1,090 sq ft30
Tower T1REHAB 3BHK107.01 sq m · 1,152 sq ft190
Tower T1Rehab office space29 sq m · 312 sq ft10
Tower T1Rehab office space29.59 sq m · 319 sq ft10
Tower T1Rehab office space30.2 sq m · 325 sq ft10
Tower T1Rehab office space102.91 sq m · 1,108 sq ft10
Tower T1Rehab office space190.18 sq m · 2,047 sq ft10
Tower T1Rehab shop34.3 sq m · 369 sq ft10
Tower T1Rehab shop38.43 sq m · 414 sq ft10
Tower T1Rehab shop50.69 sq m · 546 sq ft10
Tower T1Rehab shop51.28 sq m · 552 sq ft10
Tower T1Rehab shop54.41 sq m · 586 sq ft10
Tower T1Rehab shop63.84 sq m · 687 sq ft10
Tower T1Rehab shop72.09 sq m · 776 sq ft10
Tower T1Rehab shop72.12 sq m · 776 sq ft10
Tower T1Rehab shop79.58 sq m · 857 sq ft10
Tower T1Rehab shop82.19 sq m · 885 sq ft10
Tower T1Rehab shop96.45 sq m · 1,038 sq ft10
Tower T1Rehab shop103.85 sq m · 1,118 sq ft10
Tower T22BHK59.96 sq m · 645 sq ft300
Tower T22BHK75.61 sq m · 814 sq ft40
Tower T23BHK96.88 sq m · 1,043 sq ft280
Tower T2Office space27 sq m · 291 sq ft21
Tower T2Office space27.01 sq m · 291 sq ft22
Tower T2Office space27.04 sq m · 291 sq ft21
Tower T2Office space29.52 sq m · 318 sq ft11
Tower T2Office space30.13 sq m · 324 sq ft21
Tower T2Office space33.07 sq m · 356 sq ft10
Tower T2REHAB 2BHK59.96 sq m · 645 sq ft190
Tower T2REHAB 3BHK96.88 sq m · 1,043 sq ft170
Tower T2Rehab office space25.97 sq m · 280 sq ft10
Tower T2Rehab office space29.58 sq m · 318 sq ft10
Tower T2Rehab office space29.83 sq m · 321 sq ft10
Tower T2Rehab shop63.25 sq m · 681 sq ft10
Tower T2Shop56.42 sq m · 607 sq ft10
Tower T2Shop63.49 sq m · 683 sq ft10
Tower T2Shop64.41 sq m · 693 sq ft10
Tower T2Shop71.03 sq m · 765 sq ft10
Tower T32BHK59.96 sq m · 645 sq ft70
Tower T32BHK59.96 sq m · 645 sq ft42
Tower T32BHK72.12 sq m · 776 sq ft40
Tower T33BHK90.02 sq m · 969 sq ft402
Tower T3Office space23.26 sq m · 250 sq ft20
Tower T3Office space27.15 sq m · 292 sq ft20
Tower T3Office space27.21 sq m · 293 sq ft20
Tower T3Office space27.6 sq m · 297 sq ft20
Tower T3Office space29.14 sq m · 314 sq ft20
Tower T3Office space29.73 sq m · 320 sq ft10
Tower T3Office space29.85 sq m · 321 sq ft20
Tower T3Office space30.04 sq m · 323 sq ft11
Tower T3Office space31.65 sq m · 341 sq ft10
Tower T3Office space32.42 sq m · 349 sq ft10
Tower T3REHAB 2BHK59.96 sq m · 645 sq ft200
Tower T3REHAB 2BHK59.96 sq m · 645 sq ft180
Tower T3REHAB 3BHK90.02 sq m · 969 sq ft50
Tower T3Rehab office space25.97 sq m · 280 sq ft10
Tower T3Rehab office space30.3 sq m · 326 sq ft10
Tower T3Shop56.42 sq m · 607 sq ft10
Tower T3Shop63.71 sq m · 686 sq ft10
Tower T3Shop64.73 sq m · 697 sq ft10
Tower T3Shop64.79 sq m · 697 sq ft10
Tower T3Shop65.1 sq m · 701 sq ft10
Tower T3Shop67.52 sq m · 727 sq ft10
Tower T3Shop69.16 sq m · 744 sq ft10
Tower T42BHK59.96 sq m · 645 sq ft252
Tower T42BHK75.61 sq m · 814 sq ft41
Tower T43BHK96.88 sq m · 1,043 sq ft375
Tower T4F and b23.35 sq m · 251 sq ft10
Tower T4F and b27 sq m · 291 sq ft10
Tower T4F and b27.59 sq m · 297 sq ft10
Tower T4F and b27.66 sq m · 298 sq ft10
Tower T4F and b29.14 sq m · 314 sq ft10
Tower T4F and b30.14 sq m · 324 sq ft10
Tower T4Office space23.35 sq m · 251 sq ft11
Tower T4Office space27 sq m · 291 sq ft10
Tower T4Office space27.59 sq m · 297 sq ft11
Tower T4Office space27.66 sq m · 298 sq ft10
Tower T4Office space29.14 sq m · 314 sq ft10
Tower T4Office space29.52 sq m · 318 sq ft10
Tower T4Office space29.56 sq m · 318 sq ft10
Tower T4Office space30.14 sq m · 324 sq ft11
Tower T4Office space30.48 sq m · 328 sq ft10
Tower T4Office space31.65 sq m · 341 sq ft10
Tower T4REHAB 2BHK59.96 sq m · 645 sq ft240
Tower T4REHAB 3BHK96.88 sq m · 1,043 sq ft80
Tower T4Rehab office space26.05 sq m · 280 sq ft10
Tower T4Rehab office space33.09 sq m · 356 sq ft10
Tower T4Rehab shop51.01 sq m · 549 sq ft10
Tower T4Shop49.95 sq m · 538 sq ft10
Tower T4Shop56.42 sq m · 607 sq ft10
Tower T4Shop63.25 sq m · 681 sq ft10
Tower T4Shop63.39 sq m · 682 sq ft10
Tower T4Shop67.51 sq m · 727 sq ft10
Tower T4Shop75.32 sq m · 811 sq ft10
Tower T51BHK50.18 sq m · 540 sq ft30
Tower T52BHK59.96 sq m · 645 sq ft273
Tower T52BHK59.99 sq m · 646 sq ft192
Tower T53BHK89.75 sq m · 966 sq ft73
Tower T53BHK106.32 sq m · 1,144 sq ft20
Tower T53BHK112.63 sq m · 1,212 sq ft80
Tower T5F and b24.09 sq m · 259 sq ft10
Tower T5F and b24.45 sq m · 263 sq ft10
Tower T5F and b25.8 sq m · 278 sq ft10
Tower T5F and b26.94 sq m · 290 sq ft10
Tower T5F and b30.41 sq m · 327 sq ft10
Tower T5F and b34.68 sq m · 373 sq ft11
Tower T5F and b64.72 sq m · 697 sq ft10
Tower T5Office space24.09 sq m · 259 sq ft12
Tower T5Office space24.45 sq m · 263 sq ft10
Tower T5Office space25.8 sq m · 278 sq ft10
Tower T5Office space26.94 sq m · 290 sq ft21
Tower T5Office space30.41 sq m · 327 sq ft10
Tower T5Office space34.33 sq m · 370 sq ft10
Tower T5Office space34.68 sq m · 373 sq ft10
Tower T5Office space64.72 sq m · 697 sq ft10
Tower T5REHAB 1BHK50.18 sq m · 540 sq ft10
Tower T5REHAB 2BHK59.96 sq m · 645 sq ft190
Tower T5REHAB 2BHK59.99 sq m · 646 sq ft40
Tower T5REHAB 3BHK89.75 sq m · 966 sq ft150
Tower T5REHAB 3BHK106.32 sq m · 1,144 sq ft20
Tower T5REHAB 3BHK112.63 sq m · 1,212 sq ft150
Tower T5Rehab office space24.09 sq m · 259 sq ft10
Tower T5Rehab office space24.45 sq m · 263 sq ft10
Tower T5Rehab office space25.8 sq m · 278 sq ft10
Tower T5Rehab office space40.09 sq m · 432 sq ft10
Tower T5Rehab office space64.72 sq m · 697 sq ft10
Tower T5Rehab shop25.25 sq m · 272 sq ft10
Tower T5Rehab shop47.05 sq m · 506 sq ft10
Tower T5Rehab shop89.7 sq m · 966 sq ft10
Tower T5Shop48.96 sq m · 527 sq ft10
Tower T5Shop50.05 sq m · 539 sq ft10
Tower T5Shop51.13 sq m · 550 sq ft10
Tower T5Shop69.91 sq m · 753 sq ft10
Tower T5Shop84.68 sq m · 911 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 212 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN.pdf · uploaded 15 Mar 2024Source

Legal

  • Declaration Form BForm B Promoter.pdf · uploaded 15 Mar 2024Source
  • Legal Title reportSTR.pdf · uploaded 16 Mar 2024Source
  • Legal Title reportSTRR_compressed.pdf · uploaded 16 Mar 2024Source
  • Legal Title reportSTR I NFS new.pdf · uploaded 24 Oct 2024Source
  • Legal Title reportSTR II NFS new.pdf · uploaded 24 Oct 2024Source

Migrated

  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate.pdf · uploaded 7 Mar 2024Source
Show all 213 documentsShow fewer documents

Migrated

  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineering Certificate.pdf · uploaded 7 Mar 2024Source
  • 1 PAN CardPAN.pdf · uploaded 15 Mar 2024Source
  • 1 a Details of encumbrances concerned to FinanceEncum Finance.pdf · uploaded 15 Mar 2024Source
  • 2 a Details of encumbrances concerned to FinanceEncum Legal.pdf · uploaded 15 Mar 2024Source
  • 1 b Details of encumbrances concerned to LegalEncum Finance.pdf · uploaded 15 Mar 2024Source
  • 2 b Details of encumbrances concerned to LegalEncum Legal.pdf · uploaded 15 Mar 2024Source
  • 1 Declaration about Commencement CertificateFormat D.pdf · uploaded 15 Mar 2024Source
  • 1 Declaration in FORM BForm B Promoter.pdf · uploaded 15 Mar 2024Source
  • 1 CERSAI detailsCersai.pdf · uploaded 15 Mar 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDiscloser KM.pdf · uploaded 15 Mar 2024Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFormat A.pdf · uploaded 15 Mar 2024Source
  • 1 Deviation Report with respect to Allotment letterNo Deviation Allotment.pdf · uploaded 15 Mar 2024Source
  • 1 Copy of the legal title reportSTR.pdf · uploaded 16 Mar 2024Source
  • 2 Copy of the legal title reportSTRR_compressed.pdf · uploaded 16 Mar 2024Source
  • 1 Proforma of Allotment letterAllotment_compressed.pdf · uploaded 16 Mar 2024Source
  • 1 Proforma of Agreement for saleAgreement.pdf · uploaded 22 Mar 2024Source
  • 1 Deviation Report with respect to model copy of AgreementNo Deviation Agreement.pdf · uploaded 22 Mar 2024Source
  • 1 Copy of Layout Approval (in case of layout)LAYOUT.pdf · uploaded 23 Mar 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 23 Mar 2024Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsDiscloser RM.pdf · uploaded 23 Mar 2024Source
  • 2 Copy of Layout Approval (in case of layout)01 BP layout_page-0001.pdf · uploaded 28 Mar 2024Source
  • 1 Building Plan Approval / NA Order for plotted development2.pdf · uploaded 3 Apr 2024Source
  • 2 Building Plan Approval / NA Order for plotted development3.pdf · uploaded 3 Apr 2024Source
  • 3 Building Plan Approval / NA Order for plotted development4.pdf · uploaded 3 Apr 2024Source
  • 4 Building Plan Approval / NA Order for plotted development5.pdf · uploaded 3 Apr 2024Source
  • 5 Building Plan Approval / NA Order for plotted development6.pdf · uploaded 3 Apr 2024Source
  • 6 Building Plan Approval / NA Order for plotted development7.pdf · uploaded 3 Apr 2024Source
  • 7 Building Plan Approval / NA Order for plotted development8.pdf · uploaded 3 Apr 2024Source
  • 8 Building Plan Approval / NA Order for plotted development9.pdf · uploaded 3 Apr 2024Source
  • 9 Building Plan Approval / NA Order for plotted development10.pdf · uploaded 3 Apr 2024Source
  • 10 Building Plan Approval / NA Order for plotted development11.pdf · uploaded 3 Apr 2024Source
  • 11 Building Plan Approval / NA Order for plotted development12.pdf · uploaded 3 Apr 2024Source
  • 12 Building Plan Approval / NA Order for plotted development13.pdf · uploaded 3 Apr 2024Source
  • 13 Building Plan Approval / NA Order for plotted development14.pdf · uploaded 3 Apr 2024Source
  • 14 Building Plan Approval / NA Order for plotted development15.pdf · uploaded 3 Apr 2024Source
  • 1 Other – TechnicalDecl Order 45-24.pdf · uploaded 3 Apr 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 UPDATED_compressed.pdf · uploaded 18 Apr 2024Source
  • 3 a Details of encumbrances concerned to FinanceENCUMBRANCE CERTIFICATE - MAJESTIQUE DUROPOLIS PVT LTD.pdf · uploaded 12 Jun 2024Source
  • 3 b Details of encumbrances concerned to LegalENCUMBRANCE CERTIFICATE - MAJESTIQUE DUROPOLIS PVT LTD.pdf · uploaded 12 Jun 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentc c_.pdf · uploaded 23 Oct 2024Source
  • 13 Building Plan Approval / NA Order for plotted developmentplan-14-22_.pdf · uploaded 23 Oct 2024Source
  • 10 Building Plan Approval / NA Order for plotted developmentplan-11-22_.pdf · uploaded 23 Oct 2024Source
  • 14 Building Plan Approval / NA Order for plotted developmentplan-15-22_.pdf · uploaded 23 Oct 2024Source
  • 15 Building Plan Approval / NA Order for plotted developmentplan-16-22_.pdf · uploaded 23 Oct 2024Source
  • 16 Building Plan Approval / NA Order for plotted developmentplan-17-22_c.pdf · uploaded 23 Oct 2024Source
  • 17 Building Plan Approval / NA Order for plotted developmentplan-19-22_.pdf · uploaded 23 Oct 2024Source
  • 18 Building Plan Approval / NA Order for plotted developmentplan-20-22_.pdf · uploaded 23 Oct 2024Source
  • 19 Building Plan Approval / NA Order for plotted developmentplan-21-22_.pdf · uploaded 23 Oct 2024Source
  • 20 Building Plan Approval / NA Order for plotted developmentplan-22-22_.pdf · uploaded 23 Oct 2024Source
  • 12 Building Plan Approval / NA Order for plotted developmentplan-13-22_.pdf · uploaded 23 Oct 2024Source
  • 11 Building Plan Approval / NA Order for plotted developmentplan-12-22_.pdf · uploaded 23 Oct 2024Source
  • 9 Building Plan Approval / NA Order for plotted developmentplan-10-22_.pdf · uploaded 23 Oct 2024Source
  • 8 Building Plan Approval / NA Order for plotted developmentplan-09-22_.pdf · uploaded 23 Oct 2024Source
  • 7 Building Plan Approval / NA Order for plotted developmentplan-08-22_.pdf · uploaded 23 Oct 2024Source
  • 6 Building Plan Approval / NA Order for plotted developmentplan-07-22_.pdf · uploaded 23 Oct 2024Source
  • 5 Building Plan Approval / NA Order for plotted developmentplan-06-22_.pdf · uploaded 23 Oct 2024Source
  • 4 Building Plan Approval / NA Order for plotted developmentplan-05-22_.pdf · uploaded 23 Oct 2024Source
  • 3 Building Plan Approval / NA Order for plotted developmentplan-04-22_.pdf · uploaded 23 Oct 2024Source
  • 2 Building Plan Approval / NA Order for plotted developmentplan-02-22_.pdf · uploaded 23 Oct 2024Source
  • 1 Building Plan Approval / NA Order for plotted developmentplan-01-22_.pdf · uploaded 23 Oct 2024Source
  • 2 Copy of the legal title reportSTR II NFS new.pdf · uploaded 24 Oct 2024Source
  • 1 Copy of the legal title reportSTR I NFS new.pdf · uploaded 24 Oct 2024Source
  • 21 Building Plan Approval / NA Order for plotted developmentplan-18-22_.pdf · uploaded 24 Oct 2024Source
  • 22 Building Plan Approval / NA Order for plotted developmentplan-18-22_.pdf · uploaded 24 Oct 2024Source
  • 1 Declaration about Commencement CertificateFormat D New.pdf · uploaded 24 Oct 2024Source
  • 1 CERSAI detailsCersai New.pdf · uploaded 24 Oct 2024Source
  • 1 Disclosure for secured/unsecured finance availed for the projectDiscloser Asset new.pdf · uploaded 24 Oct 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 New.pdf · uploaded 25 Oct 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 new.pdf · uploaded 25 Oct 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 New.pdf · uploaded 25 Oct 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 _compressed.pdf · uploaded 31 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)31122024 ARCH CERTIFICATE.pdf · uploaded 27 Mar 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)31122024 .pdf · uploaded 27 Mar 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)31122024 ENGINEERING CERTIFICATE.pdf · uploaded 27 Mar 2025Source
  • 1 Disclosure of sold/ booked inventoryNfs -June 24.pdf · uploaded 27 Mar 2025Source
  • 2 Disclosure of sold/ booked inventorynfs sept 24.pdf · uploaded 27 Mar 2025Source
  • 3 Disclosure of sold/ booked inventoryNFS DEC-24_compressed.pdf · uploaded 27 Mar 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A.pdf · uploaded 1 Apr 2025Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC-3991-24 DT 13-03-2025_compressed.pdf · uploaded 3 Apr 2025Source
  • 1 Building Plan Approval / NA Order for plotted developmentPLAN-01-24_Compressed.pdf · uploaded 4 Apr 2025Source
  • 25 Building Plan Approval / NA Order for plotted developmentPLAN-23-24_Compressed.pdf · uploaded 4 Apr 2025Source
  • 24 Building Plan Approval / NA Order for plotted developmentPLAN-24-24_Compressed.pdf · uploaded 4 Apr 2025Source
  • 23 Building Plan Approval / NA Order for plotted developmentPLAN-22-24_Compressed.pdf · uploaded 4 Apr 2025Source
  • 22 Building Plan Approval / NA Order for plotted developmentPLAN-21-24_Compressed.pdf · uploaded 4 Apr 2025Source
  • 21 Building Plan Approval / NA Order for plotted developmentPLAN-20-24_Compressed.pdf · uploaded 4 Apr 2025Source
  • 20 Building Plan Approval / NA Order for plotted developmentPLAN-19-24_Compressed.pdf · uploaded 4 Apr 2025Source
  • 19 Building Plan Approval / NA Order for plotted developmentPLAN-18-24_Compressed.pdf · uploaded 4 Apr 2025Source
  • 18 Building Plan Approval / NA Order for plotted developmentPLAN-17-24_Compressed.pdf · uploaded 4 Apr 2025Source
  • 17 Building Plan Approval / NA Order for plotted developmentPLAN-16-24_Compressed.pdf · uploaded 4 Apr 2025Source
  • 16 Building Plan Approval / NA Order for plotted developmentPLAN-15-24_Compressed.pdf · uploaded 4 Apr 2025Source
  • 15 Building Plan Approval / NA Order for plotted developmentPLAN-14-24_Compressed.pdf · uploaded 4 Apr 2025Source
  • 14 Building Plan Approval / NA Order for plotted developmentPLAN-13-24_Compressed.pdf · uploaded 4 Apr 2025Source
  • 13 Building Plan Approval / NA Order for plotted developmentPLAN-12-24_Compressed.pdf · uploaded 4 Apr 2025Source
  • 12 Building Plan Approval / NA Order for plotted developmentPLAN-11-24_Compressed.pdf · uploaded 4 Apr 2025Source
  • 11 Building Plan Approval / NA Order for plotted developmentPLAN-10-24_Compressed.pdf · uploaded 4 Apr 2025Source
  • 10 Building Plan Approval / NA Order for plotted developmentPLAN-09-24_Compressed.pdf · uploaded 4 Apr 2025Source
  • 9 Building Plan Approval / NA Order for plotted developmentPLAN-08-24_Compressed.pdf · uploaded 4 Apr 2025Source
  • 8 Building Plan Approval / NA Order for plotted developmentPLAN 07-24_Compressed.pdf · uploaded 4 Apr 2025Source
  • 7 Building Plan Approval / NA Order for plotted developmentPLAN-06-24_Compressed.pdf · uploaded 4 Apr 2025Source
  • 6 Building Plan Approval / NA Order for plotted developmentPLAN-05-24_Compressed.pdf · uploaded 4 Apr 2025Source
  • 5 Building Plan Approval / NA Order for plotted developmentPLAN-04-24_Compressed.pdf · uploaded 4 Apr 2025Source
  • 4 Building Plan Approval / NA Order for plotted developmentPLAN-03-24_Compressed.pdf · uploaded 4 Apr 2025Source
  • 3 Building Plan Approval / NA Order for plotted developmentPLAN-03-03_Compressed.pdf · uploaded 4 Apr 2025Source
  • 2 Building Plan Approval / NA Order for plotted developmentPLAN-02-24_Compressed.pdf · uploaded 4 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)30032025 EC.pdf · uploaded 14 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)30032025 EC.pdf · uploaded 21 Apr 2025Source
  • 1 Disclosure of sold/ booked inventoryNFS - MAR 25_compressed_compressed3.pdf · uploaded 21 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)New Friends FORM 3 _compressed.pdf · uploaded 22 Apr 2025Source
  • Form 1Form 1.pdf · uploaded 22 Aug 2025Source
  • Form 2Form 2.pdf · uploaded 22 Aug 2025Source
  • Form 3Form 3 NFS_compressed.pdf · uploaded 22 Aug 2025Source
  • Disclosure of Sold and Booked Inventorysold unsold NFS_compressed.pdf · uploaded 22 Aug 2025Source
  • Form 1Form 1.pdf · uploaded 30 Oct 2025Source
  • Form 2From - 2.pdf · uploaded 30 Oct 2025Source
  • Form 3Form 3 NFS Q2_compressed.pdf · uploaded 30 Oct 2025Source
  • Disclosure of Sold and Booked InventoryNFS - 30-09-25_compressed.pdf · uploaded 30 Oct 2025Source
  • Form 5 (FY 2024-2025)NFS FORM 5 .pdf · uploaded 10 Dec 2025Source
  • Form 1Form 1 Architect Certificate.pdf · uploaded 2 Mar 2026Source
  • Form 2Form 2 EC.pdf · uploaded 2 Mar 2026Source
  • Form 3Form 3 NFS Q3_compressed.pdf · uploaded 2 Mar 2026Source
  • Disclosure of Sold and Booked InventorySold Unsold NFS Q3 25.pdf · uploaded 2 Mar 2026Source
  • Form 1ARCHITECT CERTIFICATE.pdf · uploaded 5 May 2026Source
  • Form 231032026 EC.pdf · uploaded 5 May 2026Source
  • Form 3Form 3 NFS Q4_compressed.pdf · uploaded 5 May 2026Source
  • Disclosure of Sold and Booked InventoryNFS - sold unsold March 2026_compressed.pdf · uploaded 5 May 2026Source
  • Form 2A (FY 2024-2025)Form 2A (3).pdf · uploaded 19 Jul 2026Source
  • Form 2A (FY 2025-2026)Form 2A (3).pdf · uploaded 19 Jul 2026Source
  • Form 2A (FY 2026-2027)Form 2A (3).pdf · uploaded 19 Jul 2026Source
  • Form 1Form 1 NFS.pdf · uploaded 20 Jul 2026Source
  • Form 2Form 2 NFS.pdf · uploaded 20 Jul 2026Source
  • Form 3NFS - FY 202627 - FORM 3_compressed.pdf · uploaded 20 Jul 2026Source
  • Disclosure of Sold and Booked InventoryNFS - sold unsold 30-06_compressed.pdf · uploaded 20 Jul 2026Source

Technical

  • DocumentLAYOUT.pdf · uploaded 23 Mar 2024Source
  • Document01 BP layout_page-0001.pdf · uploaded 28 Mar 2024Source
  • Document2.pdf · uploaded 3 Apr 2024Source
  • Document3.pdf · uploaded 3 Apr 2024Source
  • Document4.pdf · uploaded 3 Apr 2024Source
  • Document5.pdf · uploaded 3 Apr 2024Source
  • Document6.pdf · uploaded 3 Apr 2024Source
  • Document7.pdf · uploaded 3 Apr 2024Source
  • Document8.pdf · uploaded 3 Apr 2024Source
  • Document9.pdf · uploaded 3 Apr 2024Source
  • Document10.pdf · uploaded 3 Apr 2024Source
  • Document11.pdf · uploaded 3 Apr 2024Source
  • Document12.pdf · uploaded 3 Apr 2024Source
  • Document13.pdf · uploaded 3 Apr 2024Source
  • Document14.pdf · uploaded 3 Apr 2024Source
  • Document15.pdf · uploaded 3 Apr 2024Source
  • Other – TechnicalDecl Order 45-24.pdf · uploaded 3 Apr 2024Source
  • Documentplan-01-22_.pdf · uploaded 23 Oct 2024Source
  • Documentplan-02-22_.pdf · uploaded 23 Oct 2024Source
  • Documentplan-04-22_.pdf · uploaded 23 Oct 2024Source
  • Documentplan-05-22_.pdf · uploaded 23 Oct 2024Source
  • Documentplan-06-22_.pdf · uploaded 23 Oct 2024Source
  • Documentplan-07-22_.pdf · uploaded 23 Oct 2024Source
  • Documentplan-08-22_.pdf · uploaded 23 Oct 2024Source
  • Documentplan-09-22_.pdf · uploaded 23 Oct 2024Source
  • Documentplan-10-22_.pdf · uploaded 23 Oct 2024Source
  • Documentplan-11-22_.pdf · uploaded 23 Oct 2024Source
  • Documentplan-12-22_.pdf · uploaded 23 Oct 2024Source
  • Documentplan-13-22_.pdf · uploaded 23 Oct 2024Source
  • Documentplan-14-22_.pdf · uploaded 23 Oct 2024Source
  • Documentplan-15-22_.pdf · uploaded 23 Oct 2024Source
  • Documentplan-16-22_.pdf · uploaded 23 Oct 2024Source
  • Documentplan-17-22_c.pdf · uploaded 23 Oct 2024Source
  • Documentplan-19-22_.pdf · uploaded 23 Oct 2024Source
  • Documentplan-20-22_.pdf · uploaded 23 Oct 2024Source
  • Documentplan-21-22_.pdf · uploaded 23 Oct 2024Source
  • Documentplan-22-22_.pdf · uploaded 23 Oct 2024Source
  • Documentplan-18-22_.pdf · uploaded 24 Oct 2024Source
  • Documentplan-18-22_.pdf · uploaded 24 Oct 2024Source
  • DocumentPLAN-01-24_Compressed.pdf · uploaded 4 Apr 2025Source
  • DocumentPLAN-02-24_Compressed.pdf · uploaded 4 Apr 2025Source
  • DocumentPLAN-03-03_Compressed.pdf · uploaded 4 Apr 2025Source
  • DocumentPLAN-03-24_Compressed.pdf · uploaded 4 Apr 2025Source
  • DocumentPLAN-04-24_Compressed.pdf · uploaded 4 Apr 2025Source
  • DocumentPLAN-05-24_Compressed.pdf · uploaded 4 Apr 2025Source
  • DocumentPLAN-06-24_Compressed.pdf · uploaded 4 Apr 2025Source
  • DocumentPLAN 07-24_Compressed.pdf · uploaded 4 Apr 2025Source
  • DocumentPLAN-08-24_Compressed.pdf · uploaded 4 Apr 2025Source
  • DocumentPLAN-09-24_Compressed.pdf · uploaded 4 Apr 2025Source
  • DocumentPLAN-10-24_Compressed.pdf · uploaded 4 Apr 2025Source
  • DocumentPLAN-11-24_Compressed.pdf · uploaded 4 Apr 2025Source
  • DocumentPLAN-12-24_Compressed.pdf · uploaded 4 Apr 2025Source
  • DocumentPLAN-13-24_Compressed.pdf · uploaded 4 Apr 2025Source
  • DocumentPLAN-14-24_Compressed.pdf · uploaded 4 Apr 2025Source
  • DocumentPLAN-15-24_Compressed.pdf · uploaded 4 Apr 2025Source
  • DocumentPLAN-16-24_Compressed.pdf · uploaded 4 Apr 2025Source
  • DocumentPLAN-17-24_Compressed.pdf · uploaded 4 Apr 2025Source
  • DocumentPLAN-18-24_Compressed.pdf · uploaded 4 Apr 2025Source
  • DocumentPLAN-19-24_Compressed.pdf · uploaded 4 Apr 2025Source
  • DocumentPLAN-20-24_Compressed.pdf · uploaded 4 Apr 2025Source
  • DocumentPLAN-21-24_Compressed.pdf · uploaded 4 Apr 2025Source
  • DocumentPLAN-22-24_Compressed.pdf · uploaded 4 Apr 2025Source
  • DocumentPLAN-24-24_Compressed.pdf · uploaded 4 Apr 2025Source
  • DocumentPLAN-23-24_Compressed.pdf · uploaded 4 Apr 2025Source

Technical (Architect)

  • DocumentArchitect Certificate.pdf · uploaded 7 Mar 2024Source
  • DocumentForm 1 New.pdf · uploaded 25 Oct 2024Source
  • Document31122024 ARCH CERTIFICATE.pdf · uploaded 27 Mar 2025Source
  • Document31122024 .pdf · uploaded 27 Mar 2025Source

Technical (Engineer)

  • DocumentEngineering Certificate.pdf · uploaded 7 Mar 2024Source
  • DocumentForm 2 New.pdf · uploaded 25 Oct 2024Source
  • Document31122024 ENGINEERING CERTIFICATE.pdf · uploaded 27 Mar 2025Source
  • Document30032025 EC.pdf · uploaded 14 Apr 2025Source
  • Document30032025 EC.pdf · uploaded 21 Apr 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Kothrud, Haveli taluka

Survey, CTS, gat or plot numbers

CTS No. 947 S.NO. 148HISSA NO. 1+2+3

Boundaries

North
S No 148 Part
South
42m Wide Dp Road
East
S No 148 Part Nalla
West
S No 148 Hissa No 4

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectJay Aeram—
Chartered accountantVinod Kumar Jindal—
EngineerChetan Pagariya—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology