Khed, Pune
Deedo IDDL-PUN-KHED7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects331
Registrations349some projects hold several
Completion still due125169 past their date
Median extension4 months51% of registrations extended
Regulatory cases8on 9 projects
7 in 10 registrations run late here
349 MahaRERA registrations in Khed and the places within it
34 not yet due91 extended, not yet due169 past even the latest date55 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Khed
331 projects registered with MahaRERA in this taluka and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Kalp HomesDwarkamai Enterprises | Completed | — | 100% |
| Vrundavan - A WingShri Laxmi Balaji Developers | Completed | — | 81% |
| Saidatta ParadiseSai Datta Enterprises | Completed | — | 44% |
| Saidatta Paradise Wing ASai Datta Enterprises | Completed, extended 1 yr 6 mo | — | 26% |
| Sara SanskrutiJagrutsara Structures LLP | Completed | — | 100% |
| Aabhas Phase IVednirmitee Realities | Completed, extended 1 yr 6 mo | — | 46% |
| Jigisha GardenKalashri Construction Group | Due Jun 2029, extended 7 yrs 3 mo | — | 46% |
| Star City B WingAmar Builder and Promoters | Completed | — | 41% |
| DnyansadhanaDattakrupa Developer | 3 yrs 3 mo late | — | 3% |
| Creative Ventures ChakanCreative Ventures Chakan | Due Dec 2027, extended 6 yrs | — | 21% |
| Morya HillsRamesh Babanrao Gavhane | Completed, extended 1 yr 5 mo | — | 95% |
| NYAS ResidencyNYAS Developers | Completed, extended 1 yr 6 mo | — | 15% |
| Sahadu Construction Co.Sahadu Construction Co | Completed | — | 35% |
| Vastu Forest NestVastushilpbuilders & Developers | Completed | — | 86% |
| Vastu Vintage Phase 1Vastushilpbuilders & Developers | Completed | — | 73% |
| Aapla Ghar Chakan Talegaon Phase IMaple Shelters Chakan 1 | Due Dec 2027, extended 4 yrs | — | 92% |
| KalpataruShree Maruti Buildcon | Completed, extended 1 yr | — | 100% |
| Kulswamini KasturiShankar Baban Gawade | Completed | — | 65% |
| SpringfieldSwami Samarth Associates | 7 yrs 11 mo late | — | 63% |
| Tiara Meadow Phase ITiara Housing | Completed | — | 97% |
| Mahalaxmi HeightsMahalaxmi Developers | Completed, extended 2 yrs | — | 93% |
| Phase II - C1, D1 and E1 BuildingsShree Sai Associates | 6 yrs 11 mo late | — | 86% |
| Phase IV - K1 and L1 BuildingsShree Sai Associates | 6 yrs 11 mo late | — | 91% |
| Prasanna I SquarePrasanna Developers | Completed, extended 3 yrs 9 mo | — | 63% |
| Rama HeightsVasturang Developers | Completed | — | 82% |
Nearby: other talukas in Pune
Most active promoters
- Jagrutsara Structures Llp21 projects
- Sara Builders & Developers7 projects
- Anand Deoram Tambe4 projects
- Naiknavare Housing Developments Pvt. Ltd4 projects
- Shivam Developers Pvt. Ltd4 projects
- Shree Sai Associates4 projects
- Intercontinental Infrastructure Limited3 projects
- Mahendra Sayaji Pacharane3 projects
- Mangesh Vasant Gundal3 projects
- Maple Estates3 projects
Khed, in questions
How many projects in Khed run late?
7 in 10 MahaRERA registrations (260 of 349): their completion date was extended or has passed, data through 6 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Khed by Deedo. Medians on fewer than 3 deeds are not shown.
Data through6 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology