Deedo IDDL-PUN-KHED7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects331
Registrations349some projects hold several
Completion still due125169 past their date
Median extension4 months51% of registrations extended
Regulatory cases8on 9 projects
7 in 10 registrations run late here
349 MahaRERA registrations in Khed and the places within it
34 not yet due91 extended, not yet due169 past even the latest date55 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Khed
331 projects registered with MahaRERA in this taluka and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Royal ResidencyAkshay Builders & Developers | 8 yrs 8 mo late | — | 47% |
| Sejal HomesSaubhari Developers | Completed | — | 100% |
| Shivdeep AssociatesShivdeep Associates | Completed | — | 100% |
| ShivshaktiAtul Harishchandra Yelbhar | Completed, extended 4 yrs | — | 39% |
| shree hari ResidencyArchie Nova Associates | 7 yrs 11 mo late | — | 85% |
| Shree Jayganesh DarpanMahendra Sayaji Pacharane | Completed | — | 56% |
| Spine City Residency Building CSpine Developers | Completed, extended 1 yr 6 mo | — | 45% |
| sudarshan heightssudarshan properties | Completed, extended 1 yr | — | 100% |
| Suraj HomesSuraj Group Pramoters And Builders | Completed | — | 6% |
| The UrbanaIntercontinental Infrastructure Limited | 8 mo late | — | 45% |
| Unicon BlissShree Vijayalaxmi Developers | Completed | — | — |
| Phase I - Buildings A, A1, P and S, T, U Combined wingShree Sai Associates | Due Apr 2031, extended 4 mo | — | 80% |
| Shivam GreencourtShivam Developers Pvt. Ltd. | Completed | — | 100% |
| Yesai ParkSiddhivinayak Developers | Due Oct 2027 | — | 45% |
| Dnyanada City And Dnyanada Commercial CenterBhagwan Narayan Pokharkar | Due Dec 2027, extended 4 yrs | — | 64% |
| Siddhi HomesShree Ganesh Developers | Completed | — | 84% |
| Urban County A & B WingPadmalaya Properties | Due Dec 2026 | — | 91% |
| Platinum BlissPlatinum Realties | 5 yrs 5 mo late | — | 81% |
| Pradnyesh ResidencyM\s Pradnyesh Builders And Developers | Completed | — | 100% |
| Vaishnavi Builders And DevelopersVaishnavi Builders & Developers | 7 yrs 4 mo late | — | 27% |
| VrundavanShri Laxmi Balaji Developers | Completed | — | 23% |
| Aapla Ghar Chakan Phase II Amenity Bldg AMaple Estates | 3 yrs 11 mo late | — | — |
| Alteza CityS Builders & Developers | 3 yrs 11 mo late | — | 44% |
| Siddhivinayak Dream HomesRavindra Yamnaji Bhor | 7 yrs 5 mo late | — | 65% |
| Surabhi IconicaSurabhi Ventures | 2 yrs 11 mo late | — | 46% |
Nearby: other talukas in Pune
Most active promoters
- Jagrutsara Structures Llp21 projects
- Sara Builders & Developers7 projects
- Anand Deoram Tambe4 projects
- Naiknavare Housing Developments Pvt. Ltd4 projects
- Shivam Developers Pvt. Ltd4 projects
- Shree Sai Associates4 projects
- Intercontinental Infrastructure Limited3 projects
- Mahendra Sayaji Pacharane3 projects
- Mangesh Vasant Gundal3 projects
- Maple Estates3 projects
Khed, in questions
How many projects in Khed run late?
7 in 10 MahaRERA registrations (260 of 349): their completion date was extended or has passed, data through 6 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Khed by Deedo. Medians on fewer than 3 deeds are not shown.
Data through6 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology