Deedo IDDL-PUN-KHED7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects331
Registrations349some projects hold several
Completion still due125169 past their date
Median extension4 months51% of registrations extended
Regulatory cases8on 9 projects
7 in 10 registrations run late here
349 MahaRERA registrations in Khed and the places within it
34 not yet due91 extended, not yet due169 past even the latest date55 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Khed
331 projects registered with MahaRERA in this taluka and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Cloud 11Sainath Developers | Completed | — | 100% |
| Kohinoor BlissparkKohinoor Properties | Completed, extended 6 mo | — | 53% |
| Sanvi Majesty A-D-CMilestone Developers | Completed, extended 1 yr 6 mo | — | 60% |
| Sanvi MarvelMeghraj Spaces Private Limited | Completed, extended 1 yr 6 mo | — | 65% |
| Ashanand Residency C buildingAnand Deoram Tambe | Completed | — | 91% |
| Atharva Patson Phinix PH IISamrat Atharva Patson Builders And Developers | Completed | — | 54% |
| Roshan One Wing CRahul Bhagwandas Sankla | Completed, extended 3 mo | — | 47% |
| Shriram RealityShriram Reality | Completed | — | — |
| Suvarna AlayMaheshwari Developers | Due Dec 2026, extended 8 yrs | — | 100% |
| Gobind RegencySukhmani Constructions | Completed | — | 450% |
| Playtor Rajgurunagar- Phase 2Playtor Rajgurunagar Developers Private Limited | Completed, extended 3 yrs 6 mo | — | 24% |
| Vrundavan Homes Wing APrapti Spaces | Completed | — | 40% |
| Construction Of 648 Nos EWS Ts, 620 LIG Ts Under Ph2 At Mahalunge Tal Khed Dist PunePune Housing & Area Development Board | Completed, extended 1 yr 6 mo | — | — |
| First CityXrbia Developers Ltd | 3 yrs 3 mo late | — | — |
| Gods CountyGaneshconstruction | Due Dec 2026 | — | 34% |
| Vaishnavi ParkKundnani Associates | Completed, extended 2 yrs | — | 30% |
| Aapla Ghar Chakan Phase I Amentiy A BldgMaple Estates | 5 yrs 5 mo late | — | 80% |
| Swagatpsassociates | 6 yrs 11 mo late | — | 100% |
| Aapla Ghar Chakan Phase IIMaple Estates | Completed | — | 85% |
| California HeightsSudhir Ashok Mandale | Completed | — | 24% |
| Capital CityGDS Buildcon Private Limited | Completed | — | 55% |
| Ekaakshara HeightsShiv Construction And Developers | Completed, extended 2 yrs 6 mo | — | 56% |
| Krishna IconKrishna Construction Company | Completed | — | 57% |
| Kushal Swarnali C4Kushal Adiraj Associates | Completed, extended 2 yrs 6 mo | — | 71% |
| Roshan One Wing BRahul Bhagwandas Sankla | Completed | — | 31% |
Nearby: other talukas in Pune
Most active promoters
- Jagrutsara Structures Llp21 projects
- Sara Builders & Developers7 projects
- Anand Deoram Tambe4 projects
- Naiknavare Housing Developments Pvt. Ltd4 projects
- Shivam Developers Pvt. Ltd4 projects
- Shree Sai Associates4 projects
- Intercontinental Infrastructure Limited3 projects
- Mahendra Sayaji Pacharane3 projects
- Mangesh Vasant Gundal3 projects
- Maple Estates3 projects
Khed, in questions
How many projects in Khed run late?
7 in 10 MahaRERA registrations (260 of 349): their completion date was extended or has passed, data through 6 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Khed by Deedo. Medians on fewer than 3 deeds are not shown.
Data through6 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology