Khed, Pune
Deedo IDDL-PUN-KHED7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects331
Registrations349some projects hold several
Completion still due125169 past their date
Median extension4 months51% of registrations extended
Regulatory cases8on 9 projects
7 in 10 registrations run late here
349 MahaRERA registrations in Khed and the places within it
34 not yet due91 extended, not yet due169 past even the latest date55 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Khed
331 projects registered with MahaRERA in this taluka and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Dnyaneshwari Nisarg Phase 1Dnyaneshwari Developers | Due Apr 2028, extended 4 mo | — | 73% |
| Krishnakamal ResidencyBsk Group | Completed, extended 1 yr | — | 96% |
| Varadh Residency - Phase 1Radiants Properties | Completed | — | — |
| Varadh Residency - Phase 2Radiants Properties | Due Dec 2026, extended 3 yrs 9 mo | — | 45% |
| Anand ResidencyMedankar Shevkari Associates | Completed | — | 60% |
| Rhythm ParkOm Ventures | Completed | — | — |
| AlankapuriPralhad Laxman Arude | 3 yrs 11 mo late | — | — |
| Kushal Swarnali C1Kushal Adiraj Associates | 4 yrs 11 mo late | — | — |
| Raj ApoorvamCrystal Landmark | Due Apr 2028, extended 4 mo | — | — |
| Shiv ViharRoyal Construction | Completed | — | — |
| Sara City C10Jagrutsara Structures LLP | Completed | — | 89% |
| Sara City C8Jagrutsara Structures LLP | Completed | — | 94% |
| Sara City C9Jagrutsara Structures LLP | Completed | — | 93% |
| RichmondCoral Shubh Builders | Due Feb 2027, extended 4 mo | — | 63% |
| Sara City C11Jagrutsara Structures LLP | Completed | — | 77% |
| Kumar Paksha-BKumar Properties Lifespaces Private Limited | Due Oct 2027, extended 4 mo | — | 19% |
| Sadashiv Apartments B and C BuildingVasant Shriram Khedkar | 6 yrs 2 mo late | — | — |
| Padma VillaGururaj Developers | Completed | — | — |
| Signature 28Jagrutsara Structures LLP | Completed, extended 2 yrs 5 mo | — | 100% |
| DnyanvishwaDattakrupa Associates | Due Apr 2031, extended 4 mo | — | 58% |
| Saiyog ResidencyYogita Jitendra Rakshe | 5 yrs 5 mo late | — | 94% |
| Dnyanai ResidencyBharat Badshah Satpute | Completed, extended 2 yrs 3 mo | — | 50% |
| Anand Sagar ResidencyShripad Builders & Developers | Due Jul 2028, extended 4 mo | — | 39% |
| Swami Krupa ResidencyVishwa Developers | Completed, extended 1 yr | — | 21% |
| Gulmohar ParkG G Builders And Developers | Completed | — | 100% |
Nearby: other talukas in Pune
Most active promoters
- Jagrutsara Structures Llp21 projects
- Sara Builders & Developers7 projects
- Anand Deoram Tambe4 projects
- Naiknavare Housing Developments Pvt. Ltd4 projects
- Shivam Developers Pvt. Ltd4 projects
- Shree Sai Associates4 projects
- Intercontinental Infrastructure Limited3 projects
- Mahendra Sayaji Pacharane3 projects
- Mangesh Vasant Gundal3 projects
- Maple Estates3 projects
Khed, in questions
How many projects in Khed run late?
7 in 10 MahaRERA registrations (260 of 349): their completion date was extended or has passed, data through 6 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Khed by Deedo. Medians on fewer than 3 deeds are not shown.
Data through6 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology