Skip to content
Residential / Group Housing · 4 buildings · 184 unitsRERA P52100013811

Aabhas Phase I

Deedo IDDP-PUN-8HT4

MahaRERA shows it completed, after its date was pushed back 1 year and 6 months; no MahaRERA orders on record; 46% of its units are booked.

Medankarwadi, Pune 410501 · by Vednirmitee Realities

DeliveryCompletedCompletion / occupancy certificate on MahaRERA · after a 1 yr 6 mo extensionRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales46% booked84 of 184 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed, after its date was pushed back 1 year and 6 months

  • This projectRegistered 25 Oct 2017, completion promised 15 Feb 2021, revised to 15 Aug 2022.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

4 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100013811
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210001381125 Oct 201715 Feb 202115 Aug 2022Vednirmitee RealitiesProject page
Documents39

3 documents held by Deedo, 36 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Other

  • OtherDate not statedView

Finance

  • PAN CardVednirmitee Pan Card.pdf · uploaded 9 Jun 2018Source

Legal

  • Declaration Form BForm B.pdf · uploaded 29 Sep 2017Source
  • Legal Title reportSearch and Title Report Medankarwadi.pdf · uploaded 29 Sep 2017Source

Migrated

  • 1 Details of encumbrancesEncumbrance Vednirmitee Realities.pdf · uploaded 31 Jul 2017Source
  • 1 Copy of Layout Approval (in case of layout)Layout Plan.PDF · uploaded 31 Jul 2017Source
Show all 39 documentsShow fewer documents

Migrated

  • 1 Building Plan Approval (IOD)Floor Plan.PDF · uploaded 31 Jul 2017Source
  • 1 Proforma of Allotment letterAllotment Letter.pdf · uploaded 31 Jul 2017Source
  • 1 Copy of the legal title reportSearch and Title Report Medankarwadi.pdf · uploaded 29 Sep 2017Source
  • 1 Declaration in FORM BForm B.pdf · uploaded 29 Sep 2017Source
  • 1 Certificates of CA (Form 3)CA Certificate medankarwadi.pdf · uploaded 29 Sep 2017Source
  • 2 Proforma of Allotment letterDraft agreement declaration.pdf · uploaded 30 Sep 2017Source
  • 3 Proforma of Allotment letterPhasing Declaration.pdf · uploaded 30 Sep 2017Source
  • 1 PAN CardVednirmitee Pan Card.pdf · uploaded 9 Jun 2018Source
  • 1 Commencement Certificates / NA Order for plotted developmentcommencement Certificate.pdf · uploaded 9 Jun 2018Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentArchitect Completion Letter.PDF · uploaded 12 Aug 2021Source
  • 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCOMPLETION RECEIPT.PDF · uploaded 12 Aug 2021Source
  • 3 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCompletion certificate.PDF · uploaded 5 Jul 2022Source
  • 4 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentBhogavata Patr.PDF · uploaded 29 Sep 2022Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.PDF · uploaded 30 Jan 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Form 5- 2018-2019.PDF · uploaded 20 Feb 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5 - 2019-2020.PDF · uploaded 20 Feb 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 - 2020-2021.PDF · uploaded 20 Feb 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 - 2021-2022.PDF · uploaded 20 Feb 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.PDF · uploaded 1 Apr 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Form 2A.PDF · uploaded 11 Apr 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2A.PDF · uploaded 11 Apr 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A.PDF · uploaded 11 Apr 2023Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)नोंदणी प्रमाणपत्र.PDF · uploaded 19 Apr 2023Source
  • 1 Declaration about Commencement CertificateDeclaration about Commencement Certificate.PDF · uploaded 20 Apr 2023Source
  • 1 Disclosure of sold/ booked inventoryDISCOLSURE OF SOLD BOOKED INVENTORY.PDF · uploaded 22 Apr 2023View
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.PDF · uploaded 9 May 2023Source
  • 5 Architect’s Certificate on Completion of Project (Form 4)Form 4.PDF · uploaded 30 Jun 2023Source

Technical

  • DocumentLayout Plan.PDF · uploaded 31 Jul 2017Source
  • DocumentFloor Plan.PDF · uploaded 31 Jul 2017Source

Technical (Architect)

  • DocumentForm 1.PDF · uploaded 9 May 2023Source

Technical (Engineer)

  • DocumentForm 2.PDF · uploaded 30 Jan 2023Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel Sr. No. 388/1

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK, 2 BHK184 units in all
Address
Sr. No. 388/1PIN 410501
Village
medankarwadi, Khed taluka
Land area for this project
9,244 sq m (99,501 sq ft)
Permissible built-up area
9,245 sq m (99,507 sq ft)
Sanctioned built-up area
4,077 sq m (43,884 sq ft)
Recreational open space
650 sq m (6,997 sq ft)
Designated bank account
76
Developed in phases
Yes

Survey, CTS, gat or plot numbers

Sr. No. 388/1

Land as published on MahaRERA's project page

Sr. No. 388/1

Boundaries

North
Gat No 388 oblic 1and Grampanchyayat Road
South
Gat No 388 oblic 1 and proposed Road
East
Gat No 386 and Gat No 388 oblic 1 part
West
Gat No 389 and Gat No 392

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking184 units

84 of 184 units booked (46%), as the promoter reported to MahaRERA

1BHK · 152 units2BHK · 16 units2 BHK · 16 units
BuildingTypeCarpet areaUnitsBooked
Aabhas Phase I1BHK39.66 sq m · 427 sq ft44
Aabhas Phase I1BHK39.66 sq m · 427 sq ft44
Aabhas Phase I1BHK39.76 sq m · 428 sq ft33
Aabhas Phase I1BHK39.76 sq m · 428 sq ft33
Aabhas Phase I1BHK40.7 sq m · 438 sq ft44
Aabhas Phase I1BHK40.7 sq m · 438 sq ft44
Aabhas Phase I1BHK40.8 sq m · 439 sq ft33
Aabhas Phase I1BHK40.8 sq m · 439 sq ft33
Show all 32 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
Aabhas Phase I1BHK41.01 sq m · 441 sq ft44
Aabhas Phase I1BHK41.01 sq m · 441 sq ft43
Aabhas Phase I1BHK41.93 sq m · 451 sq ft33
Aabhas Phase I1BHK41.93 sq m · 451 sq ft33
Aabhas Phase I1BHK41.98 sq m · 452 sq ft33
Aabhas Phase I1BHK41.98 sq m · 452 sq ft33
Aabhas Phase I1BHK43.2 sq m · 465 sq ft44
Aabhas Phase I1BHK43.2 sq m · 465 sq ft43
Aabhas Phase I1BHK46.61 sq m · 502 sq ft77
Aabhas Phase I1BHK46.61 sq m · 502 sq ft77
Aabhas Phase I2BHK54.38 sq m · 585 sq ft77
Aabhas Phase I2BHK54.38 sq m · 585 sq ft77
Aabhas Phase II1BHK34.18 sq m · 368 sq ft160
Aabhas Phase II1BHK34.53 sq m · 372 sq ft80
Aabhas Phase II1BHK34.64 sq m · 373 sq ft160
Aabhas Phase II1BHK35.08 sq m · 378 sq ft160
Aabhas Phase II1BHK35.08 sq m · 378 sq ft160
Aabhas Phase II1BHK39.76 sq m · 428 sq ft20
Aabhas Phase II1BHK40.8 sq m · 439 sq ft20
Aabhas Phase II1BHK41.93 sq m · 451 sq ft20
Aabhas Phase II1BHK41.98 sq m · 452 sq ft20
Aabhas Phase II1BHK46.61 sq m · 502 sq ft22
Aabhas Phase II2 BHK51.28 sq m · 552 sq ft160
Aabhas Phase II2BHK54.38 sq m · 585 sq ft20

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals6

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectMr Aniruddhe Tanaji Shinde—
ArchitectMr Milind Anil Joshi—
EngineerRamchandra Krushnarao Randhave—
OtherMandar Damodar Khadilkar—
OtherSomnath Baban More—
OtherUmesh Sopan Kondhare—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Medankarwadi

All 12 projects in Medankarwadi · Compare Aabhas Phase I with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology