Residential / Group Housing · 2 buildings · 29 unitsRERA P52100028982

Aabhas Phase II

Deedo IDDP-PUN-TSG2

Its promised completion date, Oct 2024, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 17% of its units are booked.

Medankarwadi, Pune 410501 · by Vednirmitee Realities

Delivery2 yrs 1 mo past duePromised Oct 2024 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales17% booked5 of 29 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Its promised completion date, Oct 2024, has passed and MahaRERA does not show it completed

  • This projectRegistered 23 Apr 2021, completion promised 27 Oct 2024, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100028982
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210002898223 Apr 202127 Oct 202427 Oct 2024Vednirmitee RealitiesProject page
Documents32

1 document held by Deedo, 31 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardVednirmitee Pan Card.pdf · uploaded 20 Mar 2021Source

Legal

  • Legal Title reportSearch Title Report.pdf · uploaded 7 Apr 2021Source
  • Declaration Form BFormb.pdf · uploaded 13 Apr 2021Source
  • OtherObjection to the draft development plan of PMRDA.PDF · uploaded 17 Jan 2022Source

Migrated

  • 1 PAN CardVednirmitee Pan Card.pdf · uploaded 20 Mar 2021Source
  • 1 Copy of Layout Approval (in case of layout)layout.PDF · uploaded 20 Mar 2021Source
  • 1 Building Plan Approval / NA Order for plotted developmentRevised NA Order-.pdf · uploaded 20 Mar 2021Source
Show all 32 documentsShow fewer documents

Migrated

  • 1 Commencement Certificates / NA Order for plotted development2019 new comm cert.PDF · uploaded 20 Mar 2021Source
  • 1 Details of encumbrancesdeclaration.PDF · uploaded 23 Mar 2021Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Ca form 3.pdf · uploaded 23 Mar 2021Source
  • 1 Proforma of Allotment letterRera agreement.pdf · uploaded 23 Mar 2021Source
  • 2 Proforma of Allotment letterALLOTMENT LETTER.PDF · uploaded 31 Mar 2021Source
  • 1 Copy of the legal title reportSearch Title Report.pdf · uploaded 7 Apr 2021Source
  • 1 Declaration in FORM BFormb.pdf · uploaded 13 Apr 2021Source
  • 1 OtherObjection to the draft development plan of PMRDA.PDF · uploaded 17 Jan 2022Source
  • 1 Other – TechnicalDeclaration.PDF · uploaded 25 Jan 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5.PDF · uploaded 30 Jan 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.PDF · uploaded 1 Apr 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.PDF · uploaded 1 Apr 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.PDF · uploaded 1 Apr 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.PDF · uploaded 1 Apr 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2 A.PDF · uploaded 3 Apr 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2 A.PDF · uploaded 3 Apr 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5.PDF · uploaded 7 Apr 2023Source
  • 2 Other – TechnicalDeclaration cum explanation of Project.PDF · uploaded 14 Apr 2023Source

Technical

  • Documentlayout.PDF · uploaded 20 Mar 2021Source
  • DocumentRevised NA Order-.pdf · uploaded 20 Mar 2021Source
  • Other – TechnicalDeclaration.PDF · uploaded 25 Jan 2023Source
  • Other – TechnicalDeclaration cum explanation of Project.PDF · uploaded 14 Apr 2023Source

Technical (Architect)

  • DocumentForm 1.PDF · uploaded 1 Apr 2023Source

Technical (Engineer)

  • DocumentForm 2.PDF · uploaded 1 Apr 2023Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel SR. NO. 388/1

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK29 units in all
Address
Sr. No. 388/1, Medankarwadi Road, MedankarwadiPIN 410501
Village
medankarwadi, Khed taluka
Land area for this project
5,420 sq m (58,339 sq ft)
Permissible built-up area
5,420 sq m (58,339 sq ft)
Sanctioned built-up area
1,420 sq m (15,283 sq ft)
Recreational open space
650 sq m (6,997 sq ft)
Designated bank account
76
Developed in phases
Yes

Survey, CTS, gat or plot numbers

SR. NO. 388/1

Land as published on MahaRERA's project page

SR. NO. 388/1

Boundaries

North
Gat No 388 Oblic 1 And Grampanchyayat Road
South
Gat No 388 Oblic 1 And Proposed Road
East
Gat No 386 And Gat No 388 Oblic 1 Part
West
Gat No 389 And Gat No 392

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking29 units

5 of 29 units booked (17%), as the promoter reported to MahaRERA

1BHK · 19 units2BHK · 10 units
BuildingTypeCarpet areaUnitsBooked
A wing1BHK40.04 sq m · 431 sq ft11
A wing1BHK41.16 sq m · 443 sq ft21
A wing1BHK42.46 sq m · 457 sq ft21
A wing1BHK42.55 sq m · 458 sq ft21
A wing1BHK47.19 sq m · 508 sq ft21
A wing2BHK54.63 sq m · 588 sq ft20
B Wing1BHK35.3 sq m · 380 sq ft40
B Wing1BHK41.9 sq m · 451 sq ft40
Show all 11 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
B Wing1BHK45.99 sq m · 495 sq ft20
B Wing2BHK55.93 sq m · 602 sq ft40
B Wing2BHK57.13 sq m · 615 sq ft40

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectMr Anirudha Tanaji Shinde—
ArchitectMr Milind Anil Joshi—
Chartered accountantkAILASH R MUNDADA& CO—
EngineerRamchandra Krushnarao Randhave—

Source: MahaRERA project page. Contact details are not shown.