Erandwana, Pune

Deedo IDDL-PUN-ERANDWANA

9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects103
Registrations104some projects hold several
Completion still due4757 past their date
Median extension4 months45% of registrations extended
Regulatory cases0none on MahaRERA's lists

0 deeds a month, 0% of them rentals

Registered sales and rentals, the 24 months to November 2026

Registered sales and rentals by month
MonthSalesRentals
December 202400
January 202500
February 202500
March 202500
April 202500
May 202500
June 202500
July 202500
August 202500
September 202500
October 202500
November 202500
December 202500
January 202600
February 202600
March 202600
April 202610
May 202600
June 202600
July 202600
August 202600
September 202600
October 202600
November 202600

1 sale and 0 rentals in the last 12 months · Source: IGR Maharashtra Index II, registered sale and leave-and-licence deeds

9 in 10 registrations run late here

104 MahaRERA registrations in Erandwana

1 completed11 not yet due36 extended, not yet due56 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Erandwana

103 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Nirman VishnubaugPriveus Lifespaces LLPCompleted—70%
Nirman Aura Wing AGalaxy Hill Paradise LLPCompleted₹12,860—
ManikGokhale ConstructionsCompleted—90%
AaraviKotibhaskar Infrastructures &Developers Pvt.Ltd.Completed—100%
GopalkrupaLagoo Apte DevelopersCompleted—100%
ZelamGokhale ConstructionsCompleted—100%
Swojas PrashantSwojas PropertiesCompleted—100%
Swojas GauriSwojas EnterprisesCompleted——
Meera ResidencySagar DevelopersCompleted——
Madhuvrunda Co-Operative Housing SocietyAakar ConstructionsCompleted—100%
NirmalaTrisha DevelopersCompleted——
70 West AvenueAmol Ajit RavetkarCompleted, extended 1 yr 9 mo—19%
NeelprabhaPandit Javdekar AssociatesCompleted—100%
MauliLagoo ApteCompleted—67%
Swojas ChintamaniSwojas PropertiesCompleted——
YashodhanPandit Javdekar AssociatesCompleted—100%
VisavaPandit Javdekar AssociatesCompleted——
IreneAngal & CoCompleted—89%
Mugdhali Apartment CondominiumKotibhaskar Infrastructures &Developers Pvt.Ltd.Completed—71%
SuhrudGangotree GreenbuildCompleted—62%
Sugam Cooperative Housing Society LimitedKotibhaskar Infrastructures &Developers Pvt.Ltd.Completed—100%
Kool Homes GalaxyEthix VandanCompleted, extended 3 yrs—83%
Nirmiti EliteNirmiti Vastu Creation LLP4 yrs 4 mo late——
SaloniGokhale ConstructionsCompleted, extended 1 yr 11 mo—100%
BharatshreeDarode Jog Redevelopment Pvt Ltd7 yrs 11 mo late—31%
Erandwana market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Pandit Javdekar Associates6 projects
  2. Shree Venkatesh Buildcon Pvt Ltd6 projects
  3. Kotibhaskar Infrastructures &Developers Pvt.Ltd5 projects
  4. Lagoo Apte Developers4 projects
  5. Amol Ajit Ravetkar3 projects
  6. Gokhale Constructions3 projects
  7. Angal & Co2 projects
  8. Archway Estates Db LLP2 projects
  9. Ranjekar Realty Llp2 projects
  10. Swojas Enterprises2 projects

Erandwana, in questions

How many projects in Erandwana run late?

9 in 10 MahaRERA registrations (92 of 104): their completion date was extended or has passed, data through 22 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Erandwana by Deedo. Medians on fewer than 3 deeds are not shown.

Latest deal · Primary sale · Apr 2026

₹2–3.5 Cr

Data through21 Apr 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology