Residential / Group Housing · 7 buildings · 157 unitsRERA P52100002694

Bharatshree

Deedo IDDP-PUN-K66Q

Completion was pushed back 3 years and 3 months to Mar 2022, and that date has passed too; no MahaRERA orders on record; 31% of its units are booked.

Erandwana, Pune 411038 · by Darode Jog Redevelopment Pvt Ltd

Delivery7 yrs 11 mo latePromised Dec 2018 · revised Mar 2022 · that date has passed tooRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales31% booked49 of 157 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 3 years and 3 months to Mar 2022, and that date has passed too

  • This projectRegistered 2 Aug 2017, completion promised 31 Dec 2018, revised to 30 Mar 2022, and still not shown completed today.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

7 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100002694
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000026942 Aug 201731 Dec 201830 Mar 2022Darode Jog Redevelopment Pvt LtdProject page
Documents52

3 documents held by Deedo, 49 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Other

  • OtherDate not statedView

Finance

  • PAN CardPAN CARD.pdf · uploaded 14 Jul 2017Source

Legal

  • Declaration Form BDecalaration .pdf · uploaded 24 Jul 2017Source
  • Legal Title reportTITLE OPINION .pdf · uploaded 24 Jul 2017Source
  • Legal Title reportTITLE.pdf · uploaded 23 Oct 2017Source
  • Legal Title reportTITLE.pdf · uploaded 23 Oct 2017Source
Show all 52 documentsShow fewer documents

Legal

  • Legal Title reportTITLE.pdf · uploaded 23 Oct 2017Source
  • OtherDeclaration.pdf · uploaded 12 Sep 2020Source
  • OtherConsent.pdf · uploaded 12 Sep 2020Source
  • OtherARCHITECT WORK PROGRESS REPORT.pdf · uploaded 16 Oct 2020Source
  • OtherBAR CHART 1.pdf · uploaded 16 Oct 2020Source
  • OtherBAR CHART 2.pdf · uploaded 16 Oct 2020Source
  • OtherSociety Letter.pdf · uploaded 24 May 2022Source

Migrated

  • 1 PAN CardPAN CARD.pdf · uploaded 14 Jul 2017Source
  • 1 Details of encumbrancesMortgage Deed II.pdf · uploaded 14 Jul 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERTIFICATE .pdf · uploaded 14 Jul 2017Source
  • 1 Copy of the legal title reportTITLE OPINION .pdf · uploaded 24 Jul 2017Source
  • 1 Copy of Layout Approval (in case of layout)layout .pdf · uploaded 24 Jul 2017Source
  • 1 Building Plan Approval (IOD)layout .pdf · uploaded 24 Jul 2017Source
  • 1 Declaration in FORM BDecalaration .pdf · uploaded 24 Jul 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)architect CERTIFICATE.pdf · uploaded 25 Jul 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENGINEERS CERTIFICATE .pdf · uploaded 25 Jul 2017Source
  • 1 Certificates of CA (Form 3)CA certificate .pdf · uploaded 25 Jul 2017Source
  • 1 Proforma of Allotment letterdarode jog-bharatshree society-erandwane-RERA agb.pdf · uploaded 25 Jul 2017Source
  • 2 Copy of the legal title reportTITLE.pdf · uploaded 23 Oct 2017Source
  • 3 Copy of the legal title reportTITLE.pdf · uploaded 23 Oct 2017Source
  • 4 Copy of the legal title reportTITLE.pdf · uploaded 23 Oct 2017Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Bharatshree_Architect Certificate.pdf · uploaded 16 Jan 2020Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)200117 - RERA Certificate (Form-I)_compressed_compressed.pdf · uploaded 17 Jan 2020Source
  • 2 Certificates of CA (Form 3)FORM 3 .pdf · uploaded 24 Jan 2020Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)FORM 5 - BHARATSHREE.pdf · uploaded 25 Feb 2020Source
  • 1 OtherDeclaration.pdf · uploaded 12 Sep 2020Source
  • 2 OtherConsent.pdf · uploaded 12 Sep 2020Source
  • 3 OtherARCHITECT WORK PROGRESS REPORT.pdf · uploaded 16 Oct 2020Source
  • 4 OtherBAR CHART 1.pdf · uploaded 16 Oct 2020Source
  • 5 OtherBAR CHART 2.pdf · uploaded 16 Oct 2020Source
  • 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)211217 RERA Certificate.pdf · uploaded 18 Dec 2021Source
  • 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)220125- Certificate -A, B, C, D, E(Signed).pdf · uploaded 28 Feb 2022Source
  • 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)211223 - RERA Certificate(Revised)Signed1.pdf · uploaded 28 Mar 2022Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer certificate.pdf · uploaded 29 Mar 2022Source
  • 1 Declaration about Commencement CertificateDECLARATION ABOUT C C .pdf · uploaded 8 Apr 2022Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)QUARTERLY QUALITY ASSURANCE FORM 2A.pdf · uploaded 8 Apr 2022Source
  • 1 CERSAI detailsCERSAI.pdf · uploaded 8 Apr 2022Source
  • 1 Disclosure of sold/ booked inventoryCIRCULAR 29.pdf · uploaded 8 Apr 2022View
  • 6 OtherSociety Letter.pdf · uploaded 24 May 2022Source
  • 7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)VK NOC.pdf · uploaded 22 Feb 2023Source

Technical

  • Documentlayout .pdf · uploaded 24 Jul 2017Source
  • Documentlayout .pdf · uploaded 24 Jul 2017Source

Technical (Architect)

  • DocumentVK NOC.pdf · uploaded 22 Feb 2023Source

Technical (Engineer)

  • DocumentEngineer certificate.pdf · uploaded 29 Mar 2022Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 104/1 CTS NO 141PART ERANDWANE, S.NO 103/1

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1RK, 2.5BHK, 2BHK, 1BHK, 2 BHK, 3BHK, Club House157 units in all
Address
S.no 103/1 And 104/1 Cts No 141 Part Erandwane, Bharatkunj, ErandwanePIN 411038
Village
Pune (M Corp.), Pune City taluka
Land area for this project
6,225 sq m (67,005 sq ft)
Permissible built-up area
9,776 sq m (1,05,223 sq ft)
Sanctioned built-up area
8,887 sq m (95,658 sq ft)
Designated bank account
220
Developed in phases
Yes

Survey, CTS, gat or plot numbers

104/1 CTS NO 141PART ERANDWANES.NO 103/1

Land as published on MahaRERA's project page

S.NO 103/1 AND 104/1 CTS NO 141 PART ERANDWANE

Boundaries

North
SNo 103 CTS NO 141
South
By Road and S No 39
East
By S No 37
West
By S No 104 part

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking157 units

49 of 157 units booked (31%), as the promoter reported to MahaRERA

1RK · 2 units2.5BHK · 12 units2BHK · 84 units1BHK · 13 units2 BHK · 9 units3BHK · 37 unitsClub House · 0 units
BuildingTypeCarpet areaUnitsBooked
A Wing1RK26.38 sq m · 284 sq ft10
A Wing1RK28.45 sq m · 306 sq ft10
A Wing2.5BHK60.74 sq m · 654 sq ft62
A Wing2.5BHK60.85 sq m · 655 sq ft62
A Wing2BHK49.36 sq m · 531 sq ft61
A Wing2BHK49.69 sq m · 535 sq ft61
A Wing2BHK54.79 sq m · 590 sq ft11
A Wing2BHK54.82 sq m · 590 sq ft41
Show all 54 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
A Wing2BHK60.85 sq m · 655 sq ft61
B Wing1BHK36.57 sq m · 394 sq ft31
B Wing1BHK36.78 sq m · 396 sq ft10
B Wing1BHK36.79 sq m · 396 sq ft20
B Wing1BHK36.98 sq m · 398 sq ft20
B Wing1BHK37.55 sq m · 404 sq ft30
B Wing1BHK38.26 sq m · 412 sq ft10
B Wing1BHK38.64 sq m · 416 sq ft10
B Wing2 BHK49.56 sq m · 533 sq ft33
B Wing2BHK49.25 sq m · 530 sq ft30
B Wing2BHK49.57 sq m · 534 sq ft20
B Wing2BHK49.9 sq m · 537 sq ft30
B Wing2BHK54.28 sq m · 584 sq ft31
B Wing2BHK54.57 sq m · 587 sq ft32
B Wing2BHK55.06 sq m · 593 sq ft20
B Wing2BHK55.39 sq m · 596 sq ft31
B Wing3BHK63.81 sq m · 687 sq ft10
B Wing3BHK63.99 sq m · 689 sq ft20
B Wing3BHK64.31 sq m · 692 sq ft31
B Wing3BHK64.64 sq m · 696 sq ft10
B Wing3BHK65.77 sq m · 708 sq ft20
B Wing3BHK65.78 sq m · 708 sq ft11
B Wing3BHK66.09 sq m · 711 sq ft31
Club HouseClub House80 sq m · 861 sq ft00
C Wing2 BHK56.67 sq m · 610 sq ft31
C Wing2BHK56.14 sq m · 604 sq ft32
C Wing2BHK56.3 sq m · 606 sq ft32
C Wing2BHK56.51 sq m · 608 sq ft32
C Wing3BHK67.74 sq m · 729 sq ft31
C Wing3BHK68.37 sq m · 736 sq ft31
C Wing3BHK69.04 sq m · 743 sq ft30
C Wing3BHK69.7 sq m · 750 sq ft31
D Wing2 BHK54.96 sq m · 592 sq ft31
D Wing2BHK55.3 sq m · 595 sq ft30
D Wing2BHK55.41 sq m · 596 sq ft30
D Wing2BHK55.78 sq m · 600 sq ft30
D Wing2BHK56.06 sq m · 603 sq ft61
D Wing2BHK56.46 sq m · 608 sq ft60
E Wing2BHK56.14 sq m · 604 sq ft33
E Wing2BHK56.3 sq m · 606 sq ft31
E Wing2BHK56.51 sq m · 608 sq ft31
E Wing2BHK56.67 sq m · 610 sq ft32
E Wing3BHK67.74 sq m · 729 sq ft32
E Wing3BHK68.44 sq m · 737 sq ft33
E Wing3BHK69.04 sq m · 743 sq ft32
E Wing3BHK69.7 sq m · 750 sq ft33

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals2

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectArc Chandrakant Asalkar—
EngineerJW Consultantst—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Erandwana

All 103 projects in Erandwana · Compare Bharatshree with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology