Charoli, Pune
Deedo IDDL-PUN-CHAROLI9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects27
Registrations27
Completion still due252 past their date
Median extension4 months85% of registrations extended
Regulatory cases0none on MahaRERA's lists
9 in 10 registrations run late here
27 MahaRERA registrations in Charoli
2 not yet due23 extended, not yet due2 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Charoli
27 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Urban Homes A WingLotus Properties | 7 mo late | — | 36% |
| Tanish ParkTanish Developers | Due Apr 2028, extended 4 mo | — | 44% |
Nearby: other localities in Haveli
Most active promoters
- D R Gavhane Landmarks Llp2 projects
- Pride Builders Llp2 projects
- Swastik Buildtech2 projects
- Amg Landmark1 project
- Balaji Promoters1 project
- Bhosale Housing LLP1 project
- Charholi Infrastructure Llp1 project
- Deepchandra Developers Private Limited1 project
- Defense Warrior Properties1 project
- Kamlesh Manjibhai Raghwani1 project
Charoli, in questions
How many projects in Charoli run late?
9 in 10 MahaRERA registrations (25 of 27): their completion date was extended or has passed, data through 24 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Charoli by Deedo. Medians on fewer than 3 deeds are not shown.
Data through24 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology