RERA projects in Bavdhan Khurd
13 projects under 13 MahaRERA registrations, registered 2023–2026. None has an extended completion date on record.
13RERA projects
13Registrations
13Completion still due0 past their completion date
—Median extension beyond promised date0% of registrations extended
0Regulatory casesnone on MahaRERA's lists
9Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2023 | 1 |
| 2024 | 1 |
| 2025 | 7 |
| 2026 | 4 |
Projects in Bavdhan Khurd
13 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Urban Business BourseUrban Cityscape Greens LLP | PC1260002602181 | 7 Oct 2026 | 31 Dec 2028 | — | Not yet due | 0 |
| C3 Chandani Chowk CentralAarambh Developers | PM1260002601747 | 2 Sep 2026 | 31 Dec 2029 | — | Not yet due | 0 |
| Venkatesh Serenique- Phase -1Shree Venkatesh Buildcon Pvt Ltd | PM1261012601412 | 3 Aug 2026 | 30 Sep 2031 | — | Not yet due | 0 |
| Infinia AvalonSunil Wamanrao Shinde | PR1260002502477 | 25 Feb 2026 | 31 Dec 2029 | — | Not yet due | 0 |
| Hill ViewContigo Realty LLP | PR1260002501799 | 16 Dec 2025 | 31 Dec 2030 | — | Not yet due | 0 |
| Nandanvan Phase IIWh Constructions | PR1261012501145 | 9 Oct 2025 | 31 Dec 2027 | — | Not yet due | 0 |
| Emerald OasisKokate Realty LLP | PR1260002500958 | 25 Sep 2025 | 31 Aug 2028 | — | Not yet due | 0 |
| PolarisThe Excellaa | P52100080233 | 9 May 2025 | 31 Dec 2030 | — | Not yet due | 0 |
| Sun Valley By Bramhacorp - Phase 1Contigo Realty LLP | P52100080203 | 6 May 2025 | 31 Dec 2030 | — | Not yet due | 0 |
| Shangrila HeightsShangrila Height Realty LLP | P52100079619 | 17 Mar 2025 | 31 Dec 2028 | — | Not yet due | 0 |
| KGS OneM/s.Extrude Realtors | P52100078893 | 20 Jan 2025 | 20 Apr 2027 | — | Not yet due | 0 |
| The Berries StudioS Realty LLP | P52100077388 | 13 Aug 2024 | 31 Oct 2027 | — | Not yet due | 0 |
| cloud 51Oree Reality Pvt Ltd | P52100050833 | 9 May 2023 | 31 Dec 2028 | — | Not yet due | 0 |
Other localities in Mulshi
- Wakad298 projects
- Punawale183 projects
- Tathwade163 projects
- Bavadhan Bk83 projects
- Hinjavadi (Ct)82 projects
- Sus80 projects
- Bhugaon77 projects
- Mahalunge68 projects
- Man67 projects
- Thergaon56 projects
- Pirangut49 projects
- Kasar Amboli43 projects
Most active promoters
By projects registered here, as named on MahaRERA.
- Contigo Realty LLP2 projects
- Aarambh Developers1 project
- Kokate Realty LLP1 project
- M/s.Extrude Realtors1 project
- Oree Reality Pvt Ltd1 project
- Shangrila Height Realty LLP1 project
- Shree Venkatesh Buildcon Pvt Ltd1 project
- S Realty LLP1 project
- Sunil Wamanrao Shinde1 project
- The Excellaa1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology