Deedo IDDP-PUN-02Z5Completion was pushed back 4 months, to Nov 2026; no MahaRERA orders on record; 50% of its units are booked.
Aalandi, Pune 412105 · by G T Buildcon
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Nov 2026
- This projectRegistered 19 Jul 2023, completion promised 31 Jul 2026, revised to 30 Nov 2026.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100052014
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100052014 | 19 Jul 2023 | 31 Jul 2026 | 30 Nov 2026 | G T Buildcon | Project page |
Documents83
1 document held by Deedo, 82 filings listed on MahaRERA's project page
Finance
- PAN CardGT pancard.pdf · uploaded 21 Jun 2023Source
Legal
Migrated
- 1 PAN CardGT pancard.pdf · uploaded 21 Jun 2023Source
- 1 Copy of the legal title reportlegal title.pdf · uploaded 21 Jun 2023Source
- 1 a Details of encumbrances concerned to FinanceFinancial.pdf · uploaded 21 Jun 2023Source
- 1 b Details of encumbrances concerned to LegalFinancial.pdf · uploaded 21 Jun 2023Source
Show all 83 documentsShow fewer documents
Migrated
- 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate_compressed.pdf · uploaded 21 Jun 2023Source
- 1 Declaration about Commencement CertificateCircular 32.pdf · uploaded 21 Jun 2023Source
- 1 Declaration in FORM BPromoter Form B.pdf · uploaded 21 Jun 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)architecture certificate.pdf · uploaded 21 Jun 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer certificate.pdf · uploaded 21 Jun 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsPromoter declration 1.pdf · uploaded 21 Jun 2023Source
- 2 Disclosure of Interest in Other Real Estate OrganizationsPromoter declaration 2.pdf · uploaded 21 Jun 2023Source
- 1 Proforma of Allotment letterAllotment letter_compressed.pdf · uploaded 21 Jun 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBank Declaration.pdf · uploaded 21 Jun 2023Source
- 1 Deviation Report with respect to Allotment letterno deviation allotment.pdf · uploaded 21 Jun 2023Source
- 1 Deviation Report with respect to model copy of Agreementno deviation afs.pdf · uploaded 21 Jun 2023Source
- 1 Copy of Layout Approval (in case of layout)layout plan final.pdf · uploaded 22 Jun 2023Source
- 1 Building Plan Approval / NA Order for plotted developmentlayout plan final.pdf · uploaded 22 Jun 2023Source
- 1 CERSAI detailsCERSAI_Search_Report_200272258247_For_Asset_Based_Search_22_06_2023_15_22_44_051.pdf · uploaded 22 Jun 2023Source
- 1 Proforma of Agreement for saleAFS FINAL DRAFT.pdf · uploaded 26 Jun 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final upload Form 3.pdf · uploaded 3 Jul 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 29 Feb 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 29 Feb 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Upload.pdf · uploaded 8 Mar 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 8 Mar 2024Source
- 1 Disclosure of sold/ booked inventorySold Circular Upload.pdf · uploaded 8 Mar 2024Source
- 2 Disclosure of sold/ booked inventorySold Circular.pdf · uploaded 8 Mar 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 9 Aug 2024Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 9 Aug 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 9 Aug 2024Source
- 3 Disclosure of sold/ booked inventorySold Circular.pdf · uploaded 9 Aug 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Q2_compressed.pdf · uploaded 9 Aug 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Q3_compressed.pdf · uploaded 9 Aug 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Q4_compressed.pdf · uploaded 9 Aug 2024Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Q1 24-25.pdf · uploaded 9 Aug 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 20 Oct 2024Source
- 1 Disclosure of sold/ booked inventorySold Circular.pdf · uploaded 20 Oct 2024Source
- Form 1Form 1 Q2 FY 23-24.pdf · uploaded 12 Dec 2025Source
- Form 2Form 2 Q2 FY 23-24.pdf · uploaded 12 Dec 2025Source
- Form 3Form 3 Q2 FY 23-24.pdf · uploaded 12 Dec 2025Source
- Disclosure of Sold and Booked InventoryPromoter Disclosure Q2 FY 23-24.pdf · uploaded 12 Dec 2025Source
- Form 1Form 1 Q3 FY 23-24.pdf · uploaded 12 Dec 2025Source
- Form 2Form 2 Q3 FY 23-24.pdf · uploaded 12 Dec 2025Source
- Form 3Form 3 Q3 FY 23-24.pdf · uploaded 12 Dec 2025Source
- Disclosure of Sold and Booked InventoryPromoter Disclosure Q3 FY 23-24.pdf · uploaded 12 Dec 2025Source
- Form 1Form 1 Q4 FY 23-24.pdf · uploaded 12 Dec 2025Source
- Form 2Form 2 Q4 FY 23-24.pdf · uploaded 12 Dec 2025Source
- Form 3Form 3 Q4 FY 23-24.pdf · uploaded 12 Dec 2025Source
- Disclosure of Sold and Booked InventoryPromoter Disclosure Q4 FY 23-24.pdf · uploaded 12 Dec 2025Source
- Form 1Form 1 Q1 FY 24-25.pdf · uploaded 12 Dec 2025Source
- Form 2Form 2 Q1 FY 24-25.pdf · uploaded 12 Dec 2025Source
- Form 3Form 3 Q1 FY 24-25.pdf · uploaded 12 Dec 2025Source
- Disclosure of Sold and Booked InventoryPromoter Disclosure Q1 FY 24-25.pdf · uploaded 12 Dec 2025Source
- Form 5 (FY 2023-2024)Form 5 FY 23-24.pdf · uploaded 15 Dec 2025Source
- Form 1Form 1 Q2 FY 24-25.pdf · uploaded 20 Dec 2025Source
- Form 2Form 2 Q2 FY 24-25.pdf · uploaded 20 Dec 2025Source
- Form 3Form 3 Q2 FY 24-25.pdf · uploaded 20 Dec 2025Source
- Disclosure of Sold and Booked InventoryPromoter Disclosure Q2 FY 24-25.pdf · uploaded 20 Dec 2025Source
- Form 1Form 1 Q3 FY 2024-25.pdf · uploaded 20 Dec 2025Source
- Form 2Form 2 Q3 FY 2024-25.pdf · uploaded 20 Dec 2025Source
- Form 3Form 3 Q3 FY 2024-25.pdf · uploaded 20 Dec 2025Source
- Disclosure of Sold and Booked InventoryPromoters disclosure Q3 FY 2024-25.pdf · uploaded 20 Dec 2025Source
- Form 1Form 1 Q4 FY 2024-25.pdf · uploaded 20 Dec 2025Source
- Form 2Form 2 Q4 FY 2024-25.pdf · uploaded 20 Dec 2025Source
- Form 3Form 3 Q4 FY 2024-25.pdf · uploaded 20 Dec 2025Source
- Disclosure of Sold and Booked InventoryPromoters disclosure Q4 FY 2024-25.pdf · uploaded 20 Dec 2025Source
- Withdrawal Update Form 1Form 1 Q1 FY 2025-26.pdf · uploaded 20 Dec 2025Source
- Withdrawal Update Form 1Form 1 Q2 FY 2025-26.pdf · uploaded 20 Dec 2025Source
- Withdrawal Update Form 2Form 2 Q1 FY 2025-26.pdf · uploaded 20 Dec 2025Source
- Withdrawal Update Form 2Form 2 Q2 FY 2025-26.pdf · uploaded 20 Dec 2025Source
- Withdrawal Update Form 3Form 3 Q1 FY 2025-26.pdf · uploaded 20 Dec 2025Source
- Withdrawal Update Form 3Form 3 Q2 FY 2025-26.pdf · uploaded 20 Dec 2025Source
- Form 5 (FY 2024-2025)Form 5 FY 24-25.pdf · uploaded 20 Dec 2025Source
Technical
Technical (Architect)
Technical (Engineer)
- DocumentForm 2 Q2 FY 2025-26.pdf · uploaded 20 Dec 2025Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel SURVEY NO 109/1/18 AT CHOWISAWADI
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- —12 units in all
- Address
- Survey No 109/1/18 At Chowisawadi, Chowisawadi, ChowisawadiPIN 412105
- Village
- Aalandi
- Location
- 18.62466, 73.85154
- Land area for this project
- 500 sq m (5,382 sq ft)
- Permissible built-up area
- 898 sq m (9,669 sq ft)
- Sanctioned built-up area
- 698 sq m (7,516 sq ft)
- Designated bank account
- 108
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
SURVEY NO 109/1/18 AT CHOWISAWADI
Boundaries
- North
- By 20 Ft Road
- South
- By 12 Ft Road
- East
- By Property Of Mr Kisan Pandurangvasant Arjun And
- West
- By Property Of Mr Sudhakar Haribhau Panhale
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking12 units
12 units registered
| Type | Carpet area | Units |
|---|---|---|
| — | — | 12 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Patil Bugade Associates | — |
| Chartered accountant | Pgmj And Associates | — |
| Chartered accountant | R B Waghire And Company | — |
| Engineer | Shubham Hadawale | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Aalandi
- VrindaRERA P52100048911
- KantidhanRERA P52100034212
- Swapnalok ResidencyRERA P52100030466
- Dnyanai ResidencyRERA P52100029021
- Kale ResidencyRERA P52100029014
- DevaraiRERA P52100024110
- Radhe HarmonyRERA P52100021137
- Maitri AarambhRERA P52100020902
All 23 projects in Aalandi · Compare Asha Paradise with another project