Devarai
Certificate SignedAalandi, Pune 412105 |Promoter: S R Shah Atul Enterprises
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Buildings
- 1
- Unit types
- 1BHK, 2BHK143 units in all
- Address
- Gat No 188, Dudulgoan, DudulgaonPIN 412105
- Designated bank account
- 48
- Developed in phases
- No
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 30 Dec 2026
- Registered
- 21 Jan 2020
- Promised
- 30 Dec 2026
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100024110 | 21 Jan 2020 | 30 Dec 2026 | 30 Dec 2026 | S R Shah Atul Enterprises | Project page |
1 building
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| Devrai | 13 | 143 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
105 of 143 units booked (73%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 33.95 sq m · 365 sq ft | 24 | 19 |
| 1BHK | 34.99 sq m · 377 sq ft | 24 | 21 |
| 1BHK | 35.15 sq m · 378 sq ft | 24 | 20 |
| 2BHK | 47.16 sq m · 508 sq ft | 24 | 20 |
| 2BHK | 47.21 sq m · 508 sq ft | 24 | 12 |
| 2BHK | 47.38 sq m · 510 sq ft | 11 | 9 |
| 2BHK | 47.42 sq m · 510 sq ft | 12 | 4 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Documents
1 document held by Deedo, 53 filings listed on MahaRERA's project page
Finance
- PAN CardPan card.pdf · uploaded 1 Jan 2020Source
Legal
Migrated
- 1 PAN CardPan card.pdf · uploaded 1 Jan 2020Source
- 1 Copy of the legal title reportsearch report.pdf · uploaded 1 Jan 2020Source
- 1 Building Plan Approval / NA Order for plotted developmentscan08790.pdf · uploaded 1 Jan 2020Source
- 1 Commencement Certificates / NA Order for plotted developmentC C.pdf · uploaded 1 Jan 2020Source
Show all 54 documentsShow fewer documents
Migrated
- 1 Declaration in FORM BB form.pdf · uploaded 1 Jan 2020Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)arc cert.pdf · uploaded 1 Jan 2020Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA_Certificate.pdf · uploaded 1 Jan 2020Source
- 1 Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 2 Jan 2020Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)engineer cert.pdf · uploaded 2 Jan 2020Source
- 1 Details of encumbrancesencumbrance cer 188-20200106104401.pdf · uploaded 6 Jan 2020Source
- 1 Proforma of Allotment letterShree Gajanan Prasann1.pdf · uploaded 16 Jan 2020Source
- 2 Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 14 Feb 2020Source
- 2 Building Plan Approval / NA Order for plotted development2.pdf · uploaded 14 Feb 2020Source
- 3 Building Plan Approval / NA Order for plotted development3.pdf · uploaded 14 Feb 2020Source
- 4 Building Plan Approval / NA Order for plotted development4.pdf · uploaded 14 Feb 2020Source
- 5 Building Plan Approval / NA Order for plotted development5.pdf · uploaded 14 Feb 2020Source
- 2 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 14 Feb 2020Source
- 2 Proforma of Allotment letterAgreement Blank DEVRAI.pdf · uploaded 25 Jul 2021Source
- 3 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 13 Aug 2021Source
- 1 Declaration about Commencement CertificateDeclaration Certificate.pdf · uploaded 26 Aug 2021Source
- 3 Copy of Layout Approval (in case of layout)scan0046.pdf · uploaded 5 Oct 2021Source
- 4 Commencement Certificates / NA Order for plotted developmentscan0047.pdf · uploaded 5 Oct 2021Source
- 3 Proforma of Allotment letterDEVRAI DREFT Agreemant.pdf · uploaded 23 Oct 2021Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Image_016.pdf · uploaded 30 Oct 2021Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Image_021.pdf · uploaded 30 Oct 2021Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT'S CERTIFICATE.pdf · uploaded 19 Apr 2022Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificate.pdf · uploaded 19 Apr 2022Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 ca Dtd 19-04-2022 fINAL_compressed.pdf · uploaded 19 Apr 2022Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate-Form-1.pdf · uploaded 8 Jun 2023Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate Form-2.pdf · uploaded 8 Jun 2023Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form - 3 Final Signed.pdf · uploaded 8 Jun 2023Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentArchitect Certificate-Form-4 Completion.pdf · uploaded 8 Jun 2023Source
- 1 Architect’s Certificate on Completion of Project (Form 4)FORM 4 Architect Certificate.pdf · uploaded 27 Jan 2025Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCompletion Certificate-Corporation PCMC.pdf · uploaded 27 Jan 2025Source
- 1 Other – TechnicalForm 4 Architect Certificate Promoter Sign.pdf · uploaded 5 Feb 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5 Devrai FY 2019-20.pdf · uploaded 10 Feb 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 Devrai FY 2020-21.pdf · uploaded 10 Feb 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 Devrai FY 2021-22.pdf · uploaded 10 Feb 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 Devrai FY 2022-23.pdf · uploaded 10 Feb 2025Source
Technical
- Documentscan08790.pdf · uploaded 1 Jan 2020Source
- DocumentLayout.pdf · uploaded 2 Jan 2020Source
- DocumentLayout.pdf · uploaded 14 Feb 2020Source
- Document2.pdf · uploaded 14 Feb 2020Source
- Document3.pdf · uploaded 14 Feb 2020Source
- Document4.pdf · uploaded 14 Feb 2020Source
- Document5.pdf · uploaded 14 Feb 2020Source
- Documentscan0046.pdf · uploaded 5 Oct 2021Source
- Other – TechnicalForm 4 Architect Certificate Promoter Sign.pdf · uploaded 5 Feb 2025Source
Technical (Architect)
- DocumentArchitect Certificate-Form-1.pdf · uploaded 8 Jun 2023Source
Technical (Engineer)
- DocumentEngineer Certificate Form-2.pdf · uploaded 8 Jun 2023Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Aalandi
Survey, CTS, gat or plot numbers
Boundaries
- North
- Gat No 188
- South
- Gat No 188
- East
- Gat No 188
- West
- Raod
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Kimaya Associates | — |
| Chartered accountant | Hary Kurup & Associates | — |
| Engineer | Vijay Sampat Wakchaure | — |
| Other | Aditya Contruction | — |
Source: MahaRERA project page. Contact details are not shown.