Devarai

Certificate Signed

Aalandi, Pune 412105 |Promoter: S R Shah Atul Enterprises

Residential / Group HousingRERAP52100024110
21 Jan 2020Registered with MahaRERA
30 Dec 2026Promised completion
1Building
143Units registered105 booked (73%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
1BHK, 2BHK143 units in all
Address
Gat No 188, Dudulgoan, DudulgaonPIN 412105
Designated bank account
48
Developed in phases
No

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 Dec 2026

Registered
21 Jan 2020
Promised
30 Dec 2026

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210002411021 Jan 202030 Dec 202630 Dec 2026S R Shah Atul EnterprisesProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Devrai13143

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

105 of 143 units booked (73%), as the promoter reported to MahaRERA

1BHK · 72 units2BHK · 71 units
TypeCarpet areaUnitsBooked
1BHK33.95 sq m · 365 sq ft2419
1BHK34.99 sq m · 377 sq ft2421
1BHK35.15 sq m · 378 sq ft2420
2BHK47.16 sq m · 508 sq ft2420
2BHK47.21 sq m · 508 sq ft2412
2BHK47.38 sq m · 510 sq ft119
2BHK47.42 sq m · 510 sq ft124

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 53 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPan card.pdf · uploaded 1 Jan 2020Source

Legal

  • Legal Title reportsearch report.pdf · uploaded 1 Jan 2020Source
  • Declaration Form BB form.pdf · uploaded 1 Jan 2020Source

Migrated

  • 1 PAN CardPan card.pdf · uploaded 1 Jan 2020Source
  • 1 Copy of the legal title reportsearch report.pdf · uploaded 1 Jan 2020Source
  • 1 Building Plan Approval / NA Order for plotted developmentscan08790.pdf · uploaded 1 Jan 2020Source
  • 1 Commencement Certificates / NA Order for plotted developmentC C.pdf · uploaded 1 Jan 2020Source
Show all 54 documentsShow fewer documents

Migrated

  • 1 Declaration in FORM BB form.pdf · uploaded 1 Jan 2020Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)arc cert.pdf · uploaded 1 Jan 2020Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA_Certificate.pdf · uploaded 1 Jan 2020Source
  • 1 Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 2 Jan 2020Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)engineer cert.pdf · uploaded 2 Jan 2020Source
  • 1 Details of encumbrancesencumbrance cer 188-20200106104401.pdf · uploaded 6 Jan 2020Source
  • 1 Proforma of Allotment letterShree Gajanan Prasann1.pdf · uploaded 16 Jan 2020Source
  • 2 Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 14 Feb 2020Source
  • 2 Building Plan Approval / NA Order for plotted development2.pdf · uploaded 14 Feb 2020Source
  • 3 Building Plan Approval / NA Order for plotted development3.pdf · uploaded 14 Feb 2020Source
  • 4 Building Plan Approval / NA Order for plotted development4.pdf · uploaded 14 Feb 2020Source
  • 5 Building Plan Approval / NA Order for plotted development5.pdf · uploaded 14 Feb 2020Source
  • 2 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 14 Feb 2020Source
  • 2 Proforma of Allotment letterAgreement Blank DEVRAI.pdf · uploaded 25 Jul 2021Source
  • 3 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 13 Aug 2021Source
  • 1 Declaration about Commencement CertificateDeclaration Certificate.pdf · uploaded 26 Aug 2021Source
  • 3 Copy of Layout Approval (in case of layout)scan0046.pdf · uploaded 5 Oct 2021Source
  • 4 Commencement Certificates / NA Order for plotted developmentscan0047.pdf · uploaded 5 Oct 2021Source
  • 3 Proforma of Allotment letterDEVRAI DREFT Agreemant.pdf · uploaded 23 Oct 2021Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Image_016.pdf · uploaded 30 Oct 2021Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Image_021.pdf · uploaded 30 Oct 2021Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT'S CERTIFICATE.pdf · uploaded 19 Apr 2022Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificate.pdf · uploaded 19 Apr 2022Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 ca Dtd 19-04-2022 fINAL_compressed.pdf · uploaded 19 Apr 2022Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate-Form-1.pdf · uploaded 8 Jun 2023Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate Form-2.pdf · uploaded 8 Jun 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form - 3 Final Signed.pdf · uploaded 8 Jun 2023Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentArchitect Certificate-Form-4 Completion.pdf · uploaded 8 Jun 2023Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)FORM 4 Architect Certificate.pdf · uploaded 27 Jan 2025Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCompletion Certificate-Corporation PCMC.pdf · uploaded 27 Jan 2025Source
  • 1 Other – TechnicalForm 4 Architect Certificate Promoter Sign.pdf · uploaded 5 Feb 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5 Devrai FY 2019-20.pdf · uploaded 10 Feb 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 Devrai FY 2020-21.pdf · uploaded 10 Feb 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 Devrai FY 2021-22.pdf · uploaded 10 Feb 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 Devrai FY 2022-23.pdf · uploaded 10 Feb 2025Source

Technical

  • Documentscan08790.pdf · uploaded 1 Jan 2020Source
  • DocumentLayout.pdf · uploaded 2 Jan 2020Source
  • DocumentLayout.pdf · uploaded 14 Feb 2020Source
  • Document2.pdf · uploaded 14 Feb 2020Source
  • Document3.pdf · uploaded 14 Feb 2020Source
  • Document4.pdf · uploaded 14 Feb 2020Source
  • Document5.pdf · uploaded 14 Feb 2020Source
  • Documentscan0046.pdf · uploaded 5 Oct 2021Source
  • Other – TechnicalForm 4 Architect Certificate Promoter Sign.pdf · uploaded 5 Feb 2025Source

Technical (Architect)

  • DocumentArchitect Certificate-Form-1.pdf · uploaded 8 Jun 2023Source

Technical (Engineer)

  • DocumentEngineer Certificate Form-2.pdf · uploaded 8 Jun 2023Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Aalandi

Survey, CTS, gat or plot numbers

GAT NO 188

Boundaries

North
Gat No 188
South
Gat No 188
East
Gat No 188
West
Raod

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectKimaya Associates—
Chartered accountantHary Kurup & Associates—
EngineerVijay Sampat Wakchaure—
OtherAditya Contruction—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology