RERA projects in Shirgaon
13 projects under 15 MahaRERA registrations, registered 2017–2025. 47% have a completion date extended beyond the one promised.
13RERA projects
15Registrationssome projects hold several
3Completion still due12 past their completion date
36 monthsMedian extension beyond promised date47% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 10 |
| 2018 | 1 |
| 2019 | 0 |
| 2020 | 0 |
| 2021 | 1 |
| 2022 | 2 |
| 2023 | 0 |
| 2024 | 0 |
| 2025 | 1 |
Projects in Shirgaon
13 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Ipsit SukhanandIncline Realtors | P99000079687 | 20 Mar 2025 | 31 Dec 2027 | — | Not yet due | 0 |
| Shrushti ResidencySai Viraj Realtors | P99000046577 | 19 Aug 2022 | 31 Dec 2024 | 31 May 2026 | Extended 17 mo | 0 |
| Prithvi Sai Yash ComplexPrithvi Vaastu Developers | P99000032797 | 29 Jan 2022 | 30 Jun 2024 | 30 Jun 2027 | Extended 36 mo | 0 |
| Darpan A WingTHDC Siddhivinayak LLP | P99000030707 | 8 Sep 2021 | 30 Jun 2027 | — | Not yet due | 0 |
| Prithvi RegencyPrithvi Property Developers | P99000015122 | 31 Jan 2018 | 30 Apr 2021 | 30 Apr 2022 | Extended 12 mo | 0 |
| Nirlon SereneNirlon Housing India Pvt Ltd | P99000014593 | 15 Dec 2017 | 31 Oct 2019 | 31 Dec 2024 | Extended 62 mo | 0 |
| Golden Eye Phase IIIKotak Sons | P99000014416 | 29 Nov 2017 | 28 Feb 2019 | 28 Feb 2020 | Extended 12 mo | 0 |
| Sai Yash ComplexMahatma Infrasturcture (India) LLP | P99000013008 | 11 Sep 2017 | 30 Dec 2022 | — | Promised date passed | 0 |
| Swastik LaxmiSwastik Construction | P99000009764 | 22 Aug 2017 | 31 Jan 2018 | — | Promised date passed | 0 |
| Sweet Home Building 1Ipsit Enterprise | P99000009859 | 22 Aug 2017 | 31 Dec 2019 | — | Promised date passed | 0 |
| Golden EyeKotak Sons | P99000003915 | 6 Aug 2017 | 28 Feb 2019 | — | Promised date passed | 0 |
| Vastusrushti NirvanaOrion Realtors | P99000003358 | 5 Aug 2017 | 31 Dec 2018 | — | Promised date passed | 0 |
| Ipsit NavodayIpsit Enterprise | P99000002933, P99000003777, P99000005724 | 4 Aug 2017 | 31 Mar 2019 | 30 Jun 2024 | Extended 63 mo | 0 |
Other localities in Palghar
Most active promoters
By projects registered here, as named on MahaRERA.
- Ipsit Enterprise2 projects
- Kotak Sons2 projects
- Incline Realtors1 project
- Mahatma Infrasturcture (India) LLP1 project
- Nirlon Housing India Pvt Ltd1 project
- Orion Realtors1 project
- Prithvi Property Developers1 project
- Prithvi Vaastu Developers1 project
- Sai Viraj Realtors1 project
- Swastik Construction1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology