Manor, Palghar

4 in 10 MahaRERA registrations here have pushed their completion date back.

RERA projects5
Registrations5
Completion still due14 past their date
Median extension20 months40% of registrations extended
Regulatory cases0none on MahaRERA's lists
Manor market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

10 in 10 registrations run late here

5 MahaRERA registrations in Manor

1 extended, not yet due4 past even the latest date

Extended registrations moved their completion date by a median of 20 months.

Projects in Manor

5 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Amin ComplexGajarya Associates4 yrs 7 mo late—15%
15 Manor - Belvedere 2RV InfraDue Apr 2027, extended 4 mo—68%
The Riverrine, Private Riverside EstateRiver View Enclave7 yrs 10 mo late——
Riddhi Siddhi ParkRiddhi Siddhi Builders7 yrs 7 mo late—35%
Suncity ComplexSwastik Builder And Developers7 yrs 7 mo late—62%

Most active promoters

  1. Gajarya Associates1 project
  2. Riddhi Siddhi Builders1 project
  3. River View Enclave1 project
  4. RV Infra1 project
  5. Swastik Builder And Developers1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology