Deedo IDDL-PAL-MANDE10 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects5
Registrations5
Completion still due50 past their date
Median extension4 months100% of registrations extended
Regulatory cases0none on MahaRERA's lists
10 in 10 registrations run late here
5 MahaRERA registrations in Mande
5 extended, not yet due
Extended registrations moved their completion date by a median of 4 months.
Projects in Mande
5 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Riddhi Siddhi ApartmentShree Siddhivinayak Enterprise | Due Apr 2027, extended 4 mo | — | 0% |
| Blossom AvenueDilipkumar Ambalal Jain | Due Apr 2031, extended 4 mo | — | 0% |
| Rajlaxxmi ParkSaphale Land Developers LLP | Due Apr 2031, extended 4 mo | — | 0% |
| Nine Star Prestige Building No. 1Nine Home Creators | Due Apr 2027, extended 4 mo | — | 55% |
| Nine Star Prestige Building No. 2Nine Home Creators | Due Apr 2027, extended 4 mo | — | 29% |
Nearby: other localities in Palghar
Most active promoters
- Nine Home Creators2 projects
- Dilipkumar Ambalal Jain1 project
- Saphale Land Developers LLP1 project
- Shree Siddhivinayak Enterprise1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology