8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects22
Registrations22
Completion still due814 past their date
Median extension4 months18% of registrations extended
Regulatory cases0none on MahaRERA's lists

8 in 10 registrations run late here

22 MahaRERA registrations in Ozar (Ct)

1 completed4 not yet due4 extended, not yet due13 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Ozar (Ct)

22 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Aditi Commercial ComplexAditi BuildconDue Aug 2028——
Shyam B TownCrestline Buildtech Pvt LtdDue Apr 2031, extended 4 mo——
Manas Vishram ComplexMaa Krupa BuildconDue Dec 2027——
Aero CityAero City RealtorsDue Apr 2030, extended 4 mo——
Universal PrideUniversal BuildconDue Apr 2028, extended 4 mo——
Mahalaxmi HeightsPrashant Genu Pagar4 mo late—25%
Shreeram ResidencyParmanand Shrikrishna Patil1 yr 6 mo late—90%
Kalpataru Baug - Phase 2Mr. Anil Ramkrishna Bhambere And Mrs. Vidya Anil BhambereDue Apr 2027, extended 4 mo—32%
Bhumi HeightsBhumi DevelopersCompleted—67%
Martand HeightsTara DevelopersCompleted—30%
Lotus ParkAbhishek Balasaheb DeshmukhCompleted—100%
Nirmal Heights 05Gangaprassad Shivprasad SharmaCompleted——
Shree Ganesh ApartmentSachin Ashok Dhatrak2 yrs 11 mo late——
Rudransh ParkAshok Shivnarayan LaddhaCompleted—15%
Siddhivinayak HeightsSiddhivinayak BuildtechCompleted——
Vinayak NiwasParmanand Shrikrishna PatilCompleted—38%
Sai TaraGurukripa Builders and DevelopersCompleted—40%
Kalpataru Baug - Phase 1Mr. Anil Ramkrishna Bhambere And Mrs. Vidya Anil BhambereDue Dec 2026—92%
Siddhi ParkSiddhi DevelopersCompleted——
Radha TowerSamarth Group4 yrs 11 mo late—75%
Krushna ResidencyKalpataru BuildconCompleted——
Siddhivinayak PlazaSiddhivinayak BuildconCompleted——
Ozar (Ct) market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Mr. Anil Ramkrishna Bhambere And Mrs. Vidya Anil Bhambere2 projects
  2. Abhishek Balasaheb Deshmukh1 project
  3. Aditi Buildcon1 project
  4. Aero City Realtors1 project
  5. Ashok Shivnarayan Laddha1 project
  6. Bhumi Developers1 project
  7. Crestline Buildtech Pvt Ltd1 project
  8. Gangaprassad Shivprasad Sharma1 project
  9. Gurukripa Builders And Developers1 project
  10. Kalpataru Buildcon1 project

Ozar (Ct), in questions

How many projects in Ozar (Ct) run late?

8 in 10 MahaRERA registrations (17 of 22): their completion date was extended or has passed, data through 10 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Ozar (Ct) by Deedo. Medians on fewer than 3 deeds are not shown.

Data through10 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology