Dindoshi, Mumbai Suburban
Deedo IDDL-MSB-DINDOSHI8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects16
Registrations16
Completion still due151 past their date
Median extension4 months69% of registrations extended
Regulatory cases0none on MahaRERA's lists
8 in 10 registrations run late here
16 MahaRERA registrations in Dindoshi
4 not yet due11 extended, not yet due1 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Dindoshi
16 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Je And Vee ShraddhaJenvee Infrastructure Pvt Ltd | Due Dec 2031 | — | — |
| Sheetal SangamDGS Township Pvt Ltd | Due Dec 2031 | — | — |
| Jeandveesaidham - A WingJe And Vee Infrastructure | Due Apr 2030, extended 4 mo | — | — |
| Pearl IconBahist Enterprises Pvt Ltd | Due Apr 2031, extended 4 mo | — | — |
| Agarwal Floresta - JavaHomewell Realty LLP | Due Apr 2031, extended 4 mo | — | — |
Nearby: other villages in Borivali
Most active promoters
- Je And Vee Infrastructure3 projects
- Bahist Enterprises Pvt Ltd1 project
- Bp Infra Realtors Llp1 project
- Dgs Township Pvt Ltd1 project
- Garnet Construction Ltd1 project
- Homewell Realty LLP1 project
- Je And Vee Developers1 project
- Jenvee Infrastructure Pvt Ltd1 project
- Kabra And Associates1 project
- Mars Lifespaces(Yash) Private Limited1 project
Dindoshi, in questions
How many projects in Dindoshi run late?
8 in 10 MahaRERA registrations (12 of 16): their completion date was extended or has passed, data through 29 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Dindoshi by Deedo. Medians on fewer than 3 deeds are not shown.
Data through29 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology