Valnai, Mumbai Suburban
Deedo IDDL-MSB-VALNAI8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects33
Registrations33
Completion still due303 past their date
Median extension4 months73% of registrations extended
Regulatory cases0none on MahaRERA's lists
8 in 10 registrations run late here
33 MahaRERA registrations in Valnai
7 not yet due23 extended, not yet due3 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Valnai
33 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Poddar HighgardenMatushree Real Estate Developers Private Limited | Due Sep 2029 | — | — |
| Our Home ChslNamo Realty Ventures LLP | Due Sep 2030, extended 4 mo | — | — |
| Shreeji AmberShreeji Construction | Due Oct 2030, extended 4 mo | — | — |
| Rashmi IconModi's Navnirman Limited | Due Dec 2028, extended 4 mo | — | — |
| BrahmandMahavir Land Developer | Due Apr 2032, extended 4 mo | — | — |
Nearby: other villages in Borivali
Most active promoters
- Shreeji Construction6 projects
- U K Properties2 projects
- Acres Developers (Project Arjun)1 project
- Aditya Arayn Developers Llp1 project
- Ajmera Boulevard Private Limited1 project
- Alliance City Developers Realtors Pvt Ltd1 project
- Ami Modispaces Llp1 project
- Barses Jawhar Anastasio Dsouza1 project
- Chandrakosha Konstruction Private Limited1 project
- Hammad Sadiq Khan1 project
Valnai, in questions
How many projects in Valnai run late?
8 in 10 MahaRERA registrations (26 of 33): their completion date was extended or has passed, data through 22 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Valnai by Deedo. Medians on fewer than 3 deeds are not shown.
Data through22 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology