41 projects under 41 MahaRERA registrations, registered 2023–2026. 68% have a completion date extended beyond the one promised.
Locality
41RERA projects
41Registrations
37Completion still due4 past their completion date
4 monthsMedian extension beyond promised date68% of registrations extended
0Regulatory casesnone on MahaRERA's lists
53Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2023 | 9 |
| 2024 | 9 |
| 2025 | 12 |
| 2026 | 11 |
Projects in Kanheri
41 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Vraj BhumiSamarpan Buildtech LLP | PM1180002602416 | 18 Oct 2026 | 31 Dec 2029 | — | Not yet due | 0 |
| Avyukta TattvaShivoham Infrahomes LLP | PM1180002602283 | 14 Oct 2026 | 31 Dec 2030 | — | Not yet due | 0 |
| Dps EliteBp Infra Buildcon LLP | PM1180002602242 | 9 Oct 2026 | 1 Mar 2029 | 1 Mar 2029 | Not yet due | 0 |
| Krishnagiri Upavan Co-Operative Housing Society LimitedSamarpan Homes & Developers | PM1180002601384 | 31 Jul 2026 | 31 Dec 2029 | 30 Apr 2030 | Extended 4 mo | 0 |
| Radiance RegaliaRadiance Builders And Developers LLP | PM1180002601210 | 16 Jul 2026 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Tarun Yuvak Sangh ChslOssia developers | PR1180002600368 | 7 May 2026 | 30 Sep 2028 | 30 Jan 2029 | Extended 4 mo | 0 |
| Ipsit Deep DarshanIpsit Incline | PM1180002600345 | 5 May 2026 | 31 Dec 2029 | 30 Apr 2030 | Extended 4 mo | 0 |
| Shiv JayaNavkarmik Infra & Development Private Limited | PM1180002503042 | 25 Mar 2026 | 31 Mar 2029 | 31 Jul 2029 | Extended 4 mo | 0 |
| Rijin TwinstarSurbhi Construction | PM1180002502693 | 10 Mar 2026 | 30 Nov 2029 | 30 Mar 2030 | Extended 4 mo | 0 |
| Narayan ResidencyNarayan Vventures | PR1180002502305 | 10 Feb 2026 | 30 Jan 2030 | 30 May 2030 | Extended 4 mo | 0 |
| Avvirahi PlatinumAvvirahi Infra LLP | PC1180002502102 | 20 Jan 2026 | 25 Dec 2030 | 25 Apr 2031 | Extended 4 mo | 0 |
| 66 InfiniaParsh Realtors | PM1180002501822 | 17 Dec 2025 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Rishabraj Forest FrontRishabraj Estate Developers Pvt Ltd | PM1180002501049 | 1 Oct 2025 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Parshuram HeightsSpacewalk Realty LLP | PR1180002500660 | 26 Aug 2025 | 30 Sep 2028 | 30 Jan 2029 | Extended 4 mo | 0 |
| Shreenath RegencyShreenathji Infracon Build Private Limited | PM1180002500476 | 5 Aug 2025 | 31 Oct 2027 | 31 Oct 2027 | Not yet due | 0 |
| Megh Mahal ChslSamarpan Homes & Developers | PM1180002500265 | 14 Jul 2025 | 31 Dec 2027 | 31 Dec 2027 | Not yet due | 0 |
| Nirala OpalShree Nirala Construction | PM1180002500249 | 10 Jul 2025 | 30 Jun 2029 | 30 Oct 2029 | Extended 4 mo | 0 |
| Avyukta MeghaKhushi Spaces LLP | PM1180002500211 | 4 Jul 2025 | 30 Dec 2028 | 30 Dec 2028 | Not yet due | 0 |
| Devikunj Co-Operative Housing Society LimitedYogiraj Builders And Developers | P51800080293 | 19 May 2025 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| Amaira PallazoTaramati Builders And Developers Private Limited | P51800080189 | 6 May 2025 | 30 Nov 2030 | 30 Mar 2031 | Extended 4 mo | 0 |
| Diwali DarshanOmkar Engineers And Contractors | P51800080143 | 30 Apr 2025 | 1 Feb 2027 | 1 Feb 2027 | Not yet due | 0 |
| Meera Upvan Co-Operative Housing Society LimitedYogiraj Builders And Developers | P51800080078 | 23 Apr 2025 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| Swanand Co-Operative Housing Society LimitedSamarpan Homes & Developers | P51800079662 | 20 Mar 2025 | 31 Dec 2027 | 31 Dec 2027 | Not yet due | 0 |
| Ava MapleAva Lifespaces Private Limited | P51800078650 | 30 Dec 2024 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Rajdeep Co-Operative Housing Society LtdSamarpan Buildtech LLP | P51800078508 | 19 Dec 2024 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
Other localities in Borivali
Most active promoters
By projects registered here, as named on MahaRERA.
- Samarpan Homes & Developers5 projects
- Ossia developers2 projects
- Parsh Realtors2 projects
- Samarpan Buildtech LLP2 projects
- Yogiraj Builders And Developers2 projects
- Astrum Reality Private Limited1 project
- Ava Lifespaces Private Limited1 project
- Avvirahi Infra LLP1 project
- Beautiful Properties Private Limited1 project
- Bp Infra Buildcon LLP1 project
Data through18 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology