Agarwal Floresta - Java
Certificate SignedDindoshi, Mumbai Suburban 400063 |Promoter: Homewell Realty LLP
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Buildings
- 1
- Unit types
- —204 units in all
- Address
- C.t.s No. 1b/7, 1b/7/1 To 4 And 8, 8/1 To 8 And 9a, 9a/1 To 12 (Slum Plot) And C.t.s No. 1/B/10/B (Non-Slum Plot) Of Village Dindoshi, Taluka Borivali, And C.t.s No 581/A/18 (Pt), 581/A/18/1-9, 581/A/19 (Pt) And 581/A/19/1-23 Of Village Malad, Panch Bavadi, Goregaon EastPIN 400063
- Designated bank account
- 85
- Developed in phases
- No
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion pushed back 4 months
- Registered
- 7 Jan 2025
- Promised
- 31 Dec 2030
- Revised
- 30 Apr 2031
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51800078684 | 7 Jan 2025 | 31 Dec 2030 | 30 Apr 2031 | Homewell Realty LLP | Project page |
1 building
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| Agarwal Florest-Java | 27 | 204 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
204 units registered
| Type | Carpet area | Units |
|---|---|---|
| — | — | 204 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Documents
1 document held by Deedo, 85 filings listed on MahaRERA's project page
Finance
Legal
Show all 86 documentsShow fewer documents
Migrated
- 4 Copy of Layout Approval (in case of layout)5.pdf · uploaded 25 Jul 2024Source
- 9 Copy of Layout Approval (in case of layout)19.pdf · uploaded 25 Jul 2024Source
- 8 Copy of Layout Approval (in case of layout)14.pdf · uploaded 25 Jul 2024Source
- 7 Copy of Layout Approval (in case of layout)13.pdf · uploaded 25 Jul 2024Source
- 6 Copy of Layout Approval (in case of layout)8.pdf · uploaded 25 Jul 2024Source
- 5 Copy of Layout Approval (in case of layout)6 (3).pdf · uploaded 25 Jul 2024Source
- 3 Copy of Layout Approval (in case of layout)3 (3).pdf · uploaded 25 Jul 2024Source
- 2 Copy of Layout Approval (in case of layout)2.pdf · uploaded 25 Jul 2024Source
- 1 Copy of Layout Approval (in case of layout)1 lay out (3).pdf · uploaded 25 Jul 2024Source
- 1 Proforma of Allotment letterjava allotment letter 16 11 24 (1).pdf · uploaded 25 Jul 2024Source
- 1 Declaration in FORM B1 Declaration in FORM B (1).pdf · uploaded 25 Jul 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)1 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf · uploaded 25 Jul 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Java revised 27-11-2024.pdf · uploaded 25 Jul 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)1 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf · uploaded 25 Jul 2024Source
- 1 Commencement Certificates / NA Order for plotted development1 Commencement Certificates _ NA Order for plotted development (2).pdf · uploaded 25 Jul 2024Source
- 1 Building Plan Approval / NA Order for plotted development1 Building Plan Approval _ NA Order for plotted development (4).pdf · uploaded 25 Jul 2024Source
- 1 Declaration about Commencement CertificateCC Declaration Dated.pdf · uploaded 25 Jul 2024Source
- 1 CERSAI detailsCersai.pdf · uploaded 25 Jul 2024Source
- 1 Declaration about all RERA Designated Bank Accounts (Format A)Annexure A of the Bank.pdf · uploaded 25 Jul 2024Source
- 1 Deviation Report with respect to Allotment letterHOMEWELL DEVIATION (1).pdf · uploaded 25 Jul 2024Source
- 1 b Details of encumbrances concerned to LegalLegal Encumbrance.pdf · uploaded 25 Jul 2024Source
- 1 Deviation Report with respect to model copy of AgreementDeviation report Final signed.pdf · uploaded 25 Jul 2024Source
- 1 Proforma of Agreement for saleProforma of Agreement final.pdf · uploaded 25 Jul 2024Source
- 1 Disclosure of Interest in Other Real Estate Organizations1 Disclosure of Interest in Other Real Estate Organizations (5).pdf · uploaded 25 Jul 2024Source
- 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)Format B Banker Letter.pdf · uploaded 25 Jul 2024Source
- 1 Disclosure for secured/unsecured finance availed for the projectDisclosure of Secured Finance (2).pdf · uploaded 25 Jul 2024Source
- 2 a Details of encumbrances concerned to FinanceEncumbrance self declaration LEGAL.pdf · uploaded 3 Aug 2024Source
- 2 b Details of encumbrances concerned to LegalEncumbrance self declaration LEGAL.pdf · uploaded 3 Aug 2024Source
- 1 Other – TechnicalAnnexure A Signed.pdf · uploaded 5 Aug 2024Source
- 1 Other – FinanceRera letter.pdf · uploaded 18 Nov 2024Source
- 2 Commencement Certificates / NA Order for plotted development3 Commencement Certificates _ NA Order for plotted development (1).pdf · uploaded 27 Nov 2024Source
- 2 Declaration about Commencement Certificateoutput (2).pdf · uploaded 27 Nov 2024Source
- 3 a Details of encumbrances concerned to FinanceFinance Encumbrance.pdf · uploaded 28 Dec 2024Source
- 3 b Details of encumbrances concerned to LegalFinance Encumbrance.pdf · uploaded 28 Dec 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 21 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 21 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 21 Apr 2025Source
- Withdrawal Update Form 1Form 1_Java_June 25.pdf · uploaded 18 Sep 2025Source
- Withdrawal Update Form 2Form 2_Java_June 25.pdf · uploaded 18 Sep 2025Source
- Withdrawal Update Form 3Form 3_Java_June 25.pdf · uploaded 18 Sep 2025Source
- Form 5 (FY 2024-2025)Final Signed Form 5 Java 2024-25.pdf · uploaded 29 Sep 2025Source
- Withdrawal Update Form 1Form 1_Java_Sept 25 (1).pdf · uploaded 24 Nov 2025Source
- Withdrawal Update Form 2Form 2_Java_Sept 25 (1).pdf · uploaded 24 Nov 2025Source
- Withdrawal Update Form 3Form 3_Java_Sept 25 (3).pdf · uploaded 24 Nov 2025Source
- Withdrawal Update Form 1Form 1_Java_Dec 25.pdf · uploaded 19 Jan 2026Source
- Withdrawal Update Form 2Form 2_Java_Dec 25.pdf · uploaded 19 Jan 2026Source
- Withdrawal Update Form 3Form 3_Java_Dec 25.pdf · uploaded 19 Jan 2026Source
- Withdrawal Update Form 1FORM 1.pdf · uploaded 2 May 2026Source
- Withdrawal Update Form 2FORM 2.pdf · uploaded 2 May 2026Source
- Withdrawal Update Form 3FORM 3.pdf · uploaded 2 May 2026Source
- Form 2A (FY 2025-2026)Form 2A_Java_Mar 26.pdf · uploaded 17 Jun 2026Source
- Withdrawal Update Form 1Form 1_Java_June 26.pdf · uploaded 18 Jul 2026Source
- Withdrawal Update Form 2Form 2_Java_June 26.pdf · uploaded 18 Jul 2026Source
- Withdrawal Update Form 3Form 3_Java_June 26 (1).pdf · uploaded 18 Jul 2026Source
- Form 5 (FY 2025-2026)Signed Form 5 Java FY 2025 26.pdf · uploaded 29 Sep 2026Source
- Withdrawal Update Form 1form 1.pdf · uploaded 10 Oct 2026Source
- Withdrawal Update Form 2form 2.pdf · uploaded 10 Oct 2026Source
- Withdrawal Update Form 3form 3 (7).pdf · uploaded 10 Oct 2026Source
Technical
- Document19.pdf · uploaded 25 Jul 2024Source
- Document14.pdf · uploaded 25 Jul 2024Source
- Document13.pdf · uploaded 25 Jul 2024Source
- Document8.pdf · uploaded 25 Jul 2024Source
- Document6 (3).pdf · uploaded 25 Jul 2024Source
- Document5.pdf · uploaded 25 Jul 2024Source
- Document3 (3).pdf · uploaded 25 Jul 2024Source
- Document2.pdf · uploaded 25 Jul 2024Source
- Document1 lay out (3).pdf · uploaded 25 Jul 2024Source
- Document1 Building Plan Approval _ NA Order for plotted development (4).pdf · uploaded 25 Jul 2024Source
- Other – TechnicalAnnexure A Signed.pdf · uploaded 5 Aug 2024Source
- DocumentSale bldg no1 Amended letter.pdf · uploaded 6 Nov 2025Source
- DocumentPlans 1 highlighted.pdf · uploaded 26 Aug 2026Source
- DocumentPlans 2-7.pdf · uploaded 26 Aug 2026Source
- DocumentPlans 8-14.pdf · uploaded 26 Aug 2026Source
- DocumentPlans 15-20.pdf · uploaded 26 Aug 2026Source
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Dindoshi, Borivali taluka
Survey, CTS, gat or plot numbers
Boundaries
- North
- driveway
- South
- agarwal floresta OAK
- East
- layout driveway
- West
- 18 30 mt wide dp road
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Chartered accountant | Rajesh Ahuja | — |
| Engineer | Anand Yadav | — |
| Engineer | Ashfaque Razzaque Qazi | — |
Source: MahaRERA project page. Contact details are not shown.