Deedo IDDL-KOL-UJALAIWADI7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects27
Registrations27
Completion still due1710 past their date
Median extension4 months41% of registrations extended
Regulatory cases1on 1 project
7 in 10 registrations run late here
27 MahaRERA registrations in Ujalaiwadi (Ct)
7 not yet due10 extended, not yet due10 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Ujalaiwadi (Ct)
27 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Punyashlok ResidencyAhilya Builders And Developers | Due Dec 2029 | — | — |
| Aero CityPanjwani Developers | Due Dec 2031 | — | — |
| Ideal Aero PlazaIdeal Developers | Due Apr 2028, extended 4 mo | — | — |
| Varun Flora Township Jasmine BuildingVertex Developers | Due Apr 2031, extended 4 mo | — | — |
| SkylineShree Constructions | Due Apr 2031, extended 4 mo | — | — |
| Sky HeightsKirtikumar Balasaheb Masute | Due Apr 2029, extended 4 mo | — | — |
| Laxmi ResidencyPotdar Constructions | Due Jul 2030, extended 4 mo | — | 13% |
| Gagangiri HeightsGagangiri Sahyadri Builders And Developers | Due Jan 2028 | — | — |
| VBs ELEGANCEB&B Construction | Due Nov 2027 | — | 14% |
| Divine AnthuriumDivine Square Developers | Due Apr 2028, extended 4 mo | — | 12% |
| Dinanath HeightsShriganesh Builders And Developers | Completed | — | 16% |
| CelesteStellar Properties | Due Apr 2028, extended 4 mo | — | — |
| Shree Mahalaxmi Villas Phase-2Maitri Associates | Completed | — | — |
| Vishwamurti HeightsMayuresh Rajvardhan Builders and Developers | Completed | — | 20% |
| Ideal TowersIdeal Developers | Due Apr 2028, extended 4 mo | — | 83% |
| RajgadMahadev Builders & Developers | Due Apr 2028, extended 4 mo | — | — |
| Nisarg ResidencyShital Popat Gade | 2 yrs 1 mo late | — | — |
| Dharti apartmentPrithviraj Kakade Constructions PVT LTD | 3 yrs 2 mo late | — | — |
| Varun Flora Township - Marigold BldgVertex Developers | Due Apr 2027, extended 4 mo | — | 36% |
| Anita PrideGirish Vasudev Joshi | Completed, extended 1 yr | — | 100% |
| Narayanee EnclaveNarayanee Infra | Completed | — | 16% |
| Basav-Jyoti HeightsJyotiveer Builders and Developers | 1 yr 11 mo late | — | — |
| Varun Flora Township - Lotus BldgVertex Developers | Completed | — | 52% |
| Shree Mahalaxmi Villas Phase-IMaitri Associates | Completed | — | 67% |
| Shree Punyai ResidencyShree Vardhaman Construction | Completed | — | 50% |
Nearby: other municipal areas in Karvir
Most active promoters
- Vertex Developers4 projects
- Ideal Developers2 projects
- Maitri Associates2 projects
- Ahilya Builders And Developers1 project
- B&B Construction1 project
- Divine Square Developers1 project
- Gagangiri Sahyadri Builders And Developers1 project
- Girish Vasudev Joshi1 project
- Jyotiveer Builders And Developers1 project
- Kirtikumar Balasaheb Masute1 project
Ujalaiwadi (Ct), in questions
How many projects in Ujalaiwadi (Ct) run late?
7 in 10 MahaRERA registrations (20 of 27): their completion date was extended or has passed, data through 5 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Ujalaiwadi (Ct) by Deedo. Medians on fewer than 3 deeds are not shown.
Data through5 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology