Celeste
Deedo IDDP-KOL-9HQKCompletion was pushed back 4 months, to Apr 2028; no MahaRERA orders on record; 27% of its units are booked.
Ujalaiwadi (Ct), Kolhapur 416004 · by Stellar Properties
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2028
- This projectRegistered 5 Oct 2023, completion promised 31 Dec 2027, revised to 30 Apr 2028.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP53000052860
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P53000052860 | 5 Oct 2023 | 31 Dec 2027 | 30 Apr 2028 | Stellar Properties | Project page |
Documents89
1 document held by Deedo, 88 filings listed on MahaRERA's project page
Finance
- PAN CardPAN Card.pdf · uploaded 12 Aug 2023Source
Legal
Migrated
- 1 PAN CardPAN Card.pdf · uploaded 12 Aug 2023Source
- 1 a Details of encumbrances concerned to FinanceEncumbrances concerned to Finance.pdf · uploaded 12 Aug 2023Source
- 2 a Details of encumbrances concerned to FinanceEncumbrances concerned to Legal.pdf · uploaded 12 Aug 2023Source
- 1 b Details of encumbrances concerned to LegalEncumbrances concerned to Finance.pdf · uploaded 12 Aug 2023Source
Show all 89 documentsShow fewer documents
Migrated
- 2 b Details of encumbrances concerned to LegalEncumbrances concerned to Legal.pdf · uploaded 12 Aug 2023Source
- 1 Building Plan Approval / NA Order for plotted developmentSanctioned Plan.pdf · uploaded 12 Aug 2023Source
- 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 12 Aug 2023Source
- 1 Declaration about Commencement CertificateDeclaration about CC.pdf · uploaded 12 Aug 2023Source
- 1 Declaration in FORM BForm B - Promoter.pdf · uploaded 12 Aug 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate.pdf · uploaded 12 Aug 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate.pdf · uploaded 12 Aug 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate.pdf · uploaded 12 Aug 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A.pdf · uploaded 12 Aug 2023Source
- 1 Proforma of Allotment letterAllottment Letter - New.pdf · uploaded 12 Aug 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBank Account Declaration.pdf · uploaded 12 Aug 2023Source
- 1 Deviation Report with respect to Allotment letterNo Deviation - Allotment Letter.pdf · uploaded 12 Aug 2023Source
- 1 Copy of the legal title reportLegal Title and Search Report.pdf · uploaded 23 Aug 2023Source
- 1 CERSAI detailsCERSAI_Search_Report_200278138163_For_Asset_Based_Search_23_08_2023_12_34_38_123.pdf · uploaded 23 Aug 2023Source
- 1 Copy of Layout Approval (in case of layout)Layout Plan.pdf · uploaded 25 Aug 2023Source
- 1 Proforma of Agreement for saleAgreement to Sell as per RERA Act.pdf · uploaded 13 Sep 2023Source
- 1 Deviation Report with respect to model copy of AgreementDeviation Report New.pdf · uploaded 13 Sep 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 20 Jan 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 20 Jan 2024Source
- 1 Disclosure of sold/ booked inventorySold Inventory.pdf · uploaded 20 Jan 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 23 Jan 2024Source
- 2 Building Plan Approval / NA Order for plotted developmentMYSCAN_20240313_0009.pdf · uploaded 26 Apr 2024Source
- 3 Building Plan Approval / NA Order for plotted developmentMYSCAN_20240313_0010.pdf · uploaded 26 Apr 2024Source
- 2 Commencement Certificates / NA Order for plotted developmentCeleste prarambha pramanpatra (1).pdf · uploaded 26 Apr 2024Source
- 2 Declaration about Commencement CertificateFormat D.pdf · uploaded 26 Apr 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 26 Apr 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 26 Apr 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A.pdf · uploaded 26 Apr 2024Source
- 2 Disclosure of sold/ booked inventorySold Inventory.pdf · uploaded 26 Apr 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 26 Apr 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 2A.pdf · uploaded 26 Apr 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architects_Certificate[1].pdf · uploaded 13 Aug 2024Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect.pdf · uploaded 13 Aug 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificate.pdf · uploaded 13 Aug 2024Source
- 3 Disclosure of sold/ booked inventoryDiscloser_of_sold[1].pdf · uploaded 13 Aug 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Charted_accountant_certificate[1].pdf · uploaded 13 Aug 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate.pdf · uploaded 19 Oct 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 19 Oct 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate.pdf · uploaded 19 Oct 2024Source
- 2 Disclosure of sold/ booked inventoryDiscloser of sold Booking Inventory.pdf · uploaded 19 Oct 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5.pdf · uploaded 19 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate.pdf · uploaded 22 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Charted Accountant Certificate Form 3.pdf · uploaded 22 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate.pdf · uploaded 22 Jan 2025Source
- 1 Disclosure of sold/ booked inventoryDiscloser of sold.pdf · uploaded 22 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate.pdf · uploaded 19 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Chartered Accountant Certificate Form 3_compressed.pdf · uploaded 19 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate.pdf · uploaded 19 Apr 2025Source
- 1 Disclosure of sold/ booked inventoryDisclosure Of Inventory Sold.pdf · uploaded 19 Apr 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23) (29).pdf · uploaded 19 Apr 2025Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A.pdf · uploaded 19 Apr 2025Source
- Withdrawal Update Form 1Form 1.pdf · uploaded 19 Jul 2025Source
- Withdrawal Update Form 2Form 2.pdf · uploaded 19 Jul 2025Source
- Withdrawal Update Form 3FORM 3.pdf · uploaded 19 Jul 2025Source
- Form 5 (FY 2024-2025)Form 5 - 2024-2025 Stellar Properties.pdf · uploaded 29 Sep 2025Source
- Withdrawal Update Form 1Form 1.pdf · uploaded 14 Oct 2025Source
- Withdrawal Update Form 2Form 2.pdf · uploaded 14 Oct 2025Source
- Withdrawal Update Form 3Form 3.pdf · uploaded 14 Oct 2025Source
- Withdrawal Update Form 1Form 1.pdf · uploaded 30 Jan 2026Source
- Withdrawal Update Form 2Form 2.pdf · uploaded 30 Jan 2026Source
- Withdrawal Update Form 3Form 3.pdf · uploaded 30 Jan 2026Source
- Withdrawal Update Form 1Form 1 (19).pdf · uploaded 29 Apr 2026Source
- Withdrawal Update Form 2Form 2 (33).pdf · uploaded 29 Apr 2026Source
- Withdrawal Update Form 3Form 3 (14).pdf · uploaded 29 Apr 2026Source
- Form 2A (FY 2025-2026)Form 2A - Celeste.pdf · uploaded 23 Jun 2026Source
- Withdrawal Update Form 1Form 1.pdf · uploaded 20 Jul 2026Source
- Withdrawal Update Form 2Form 2.pdf · uploaded 20 Jul 2026Source
- Withdrawal Update Form 3Form 3.pdf · uploaded 20 Jul 2026Source
- Form 5 (FY 2025-2026)Form 5 Stellar Properties.pdf · uploaded 24 Sep 2026Source
Technical
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel R.S.NO. 140/A/1/1/C
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- —11 units in all
- Address
- R.s.no. 140/A/1/1/C, Green Park Colony Within Kolhapur Municipal Corporation Area, Near Shivaji UniversityPIN 416004
- Village
- Ujalaiwadi (CT), Karvir taluka
- Location
- 16.66849, 74.25787
- Land area for this project
- 843 sq m (9,071 sq ft)
- Permissible built-up area
- 2,674 sq m (28,785 sq ft)
- Sanctioned built-up area
- 2,674 sq m (28,785 sq ft)
- Designated bank account
- 85
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
R.S.NO. 140/A/1/1/C
Boundaries
- North
- Shivaji University Area And Green Park Colony
- South
- 9 Meter Colony Road
- East
- Remaining Property Of R S No 140-A-1-1-C
- West
- R S No 140-A-1-1-B
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking11 units
11 units registered
| Type | Carpet area | Units |
|---|---|---|
| — | — | 11 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Feet By Meters Through Shweta Gadre | — |
| Chartered accountant | POWAR SAMANT & JADHAV Girish Samant | — |
| Chartered accountant | Shalini Amit Patil | — |
| Engineer | Er Purushottam J Parulekar | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Ujalaiwadi (Ct)
- Punyashlok ResidencyRERA PM1150002602650
- Aero CityRERA PR1150002601876
- Ideal Aero PlazaRERA PC1150002502675
- Varun Flora Township Jasmine BuildingRERA PR1150002502639
- SkylineRERA PR1150002502192
- Sky HeightsRERA PR1150002501532
- Laxmi ResidencyRERA P53000056205
- Gagangiri HeightsRERA P53000055725
All 27 projects in Ujalaiwadi (Ct) · Compare Celeste with another project