3 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects25
Registrations25
Completion still due223 past their date
Median extension13 months4% of registrations extended
Regulatory cases0none on MahaRERA's lists

3 in 10 registrations run late here

25 MahaRERA registrations in Bhusawal (Ct)

16 completed1 not yet due8 past even the latest date

Extended registrations moved their completion date by a median of 13 months.

Projects in Bhusawal (Ct)

25 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Casa De RoyaleRaka ConstructionsDue Dec 2027——
Laxmi HeightsPrajakt Shivaji PatilCompleted——
VighnarajPatil MahajanCompleted——
Pride ResidencySumit Mahendra Chordia1 yr 11 mo late—10%
Vastu VandanManohar Ganpat WaniCompleted——
All 25 projects →
Bhusawal (Ct) market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Nearby: other municipal areas in Bhusawal

Most active promoters

  1. Rajesh Raka3 projects
  2. Vishal Rajendra Natkar3 projects
  3. Patil Mahajan2 projects
  4. Prajakt Shivaji Patil2 projects
  5. Raka Constructions2 projects
  6. Sumit Mahendra Chordia2 projects
  7. Ajmal Khan Musa Khan1 project
  8. Chintamani Construction1 project
  9. Kalpana Sudhakar Phalak1 project
  10. Manohar Ganpat Wani1 project

Bhusawal (Ct), in questions

How many projects in Bhusawal (Ct) run late?

3 in 10 MahaRERA registrations (8 of 25): their completion date was extended or has passed, data through 21 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Bhusawal (Ct) by Deedo. Medians on fewer than 3 deeds are not shown.

Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology